Total Completion Date definition

Total Completion Date means the date that Total Completion has been achieved, as set out in the Total Completion Certificate;
Total Completion Date means the date on which Total Completion occurs, as established by the Certificate of Total Completion.
Total Completion Date means the date upon which all of the work shall be totally completed.

Examples of Total Completion Date in a sentence

  • Liquidated damages shall apply to the Total Completion Date for the Total Project Work (as may be extended under the Contract) and, when applicable, the Total Completion Date for each Project Segment (as may be extended under the Contract), in accordance with this Agreement and the Special Conditions.

  • PQ5.9.1a For each month from the Effective Date until the Total Completion Date, Project Co shall prepare, and submit to the Province’s Representative within 15 Business Days of the start of the following month, a comprehensive Quality Management System report.

  • Project Co will conduct workplace safety audits in accordance with Good Industry Practice at least once each month during the period between the Effective Date and the Total Completion Date.

  • If the aggregate amount of the Allowed Costs incurred by Project Co as of the Total Completion Date is less than the Target Cost, the Province will pay Project Co a Gainshare Payment valued at 50% of the difference between the Target Cost and the total Allowed Costs incurred.

  • Project Co shall at all times until the Total Completion Date appoint and maintain a property representative as Project Co’s point of contact for dealings between the Province and Project Co on the- 17 -subject matters of this Schedule.

  • Unless the letter of credit is called, it will expire on the date that is the later of: (a) two weeks following the Total Completion Date; and (b) two weeks following the end of the warranty period set out in section 7(a).

  • On or before the last day of each month, up to and including, the Total Completion Date, Project Co shall submit an updated Submittal Schedule to BC Hydro’s Representative for information only.

  • Notify Minister 30 Business Days prior to expected Total Completion Total Completion Date Schedule D3 –Custom Design Features (Optional) Please specify any custom design features that exceed the structural requirements set out in the Long-Term Care Design Guidelines..

  • In the second quarter of 2020, InPower BC General Partnership, a wholly-owned subsidiary of the Company, did not comply with the Lenders Long Stop Date (“LLSD”) under its principal financing document (Common Terms and Intercreditor Agreement) due to a delay in achieving the Total Completion Date on or prior to May 13, 2020.

  • Based on the information contained in this Monthly Progress Report #3 and during this reporting period, Tango believes the construction of the Project can be completed by the Total Completion Date of September 16, 2021 for the Project Budget of $132,100,000.


More Definitions of Total Completion Date

Total Completion Date means the date of Total Completion as determined by the School District’s Representative in accordance with the Contract Documents and set out in the Total Completion Certificate;
Total Completion Date each have the meaning given in Schedule 4;
Total Completion Date means the date when Total Completion of the Work has been achieved as set out in the Certificate of Total Completion.
Total Completion Date means the date on which Total Completion actually occurs. “Total Completion” means that the Utility Plant adheres to all performance criteria and all performance tests as specified in the EPC Contract are complete including, without limitation, complete installation of all materials and equipment in accordance with the EPC Contract requirements, completion of all required tests as specified in the EPC Contract and attainment of the Performance Guarantees, all licenses and permits required to operate the Utility Plant and other customary
Total Completion Date means the date when Total Completion is achieved as certified by the Independent Certifier in accordance with Section 10.2 of this Schedule;

Related to Total Completion Date

  • Final Completion Date means the date on which Final Completion occurs.

  • The Completion Date means the date of completion of the Works as certified by the Employer’s Representative.

  • Substantial Completion Date means the date on which Substantial Completion occurs.

  • Completion Date means the date of completion of the Services by the Service Provider as certified by the Procuring Entity

  • Project Completion Date means the date on which the Completion Certificate is issued;

  • Target Completion Date has the meaning given such term in Section 3.3(b).

  • Construction Completion Date means the Completion Date of the Construction as specified in the Statutory Declaration of Completion for the Project;

  • Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.

  • project completion period means the period of sixty (60) months commencing from and expiring on for the construction and obtaining of Temporary Occupation Permit or Permits for the whole of the Development as provided in clause 3.3;

  • Completion Period means the period starting from the date of issue of "Order" and required to complete the work in all respect.

  • Outside Completion Date shall have the meaning assigned to such term in Section 6.3(d).

  • Substantial Completion means the stage in the progress of the work as determined and certified by the Contracting Officer in writing to the Contractor, on which the work (or a portion designated by the Government) is sufficiently complete and satisfactory. Substantial completion means that the property may be occupied or used for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:

  • Scheduled Completion Date shall be the date set forth in Clause 10.3;

  • Guaranteed Substantial Completion Date or “Guaranteed Substantial Completion Dates” has the meaning set forth in Section 5.3B.

  • Date of Completion with respect to a Project shall mean: (i) the date upon which such Project and all components thereof have been acquired or constructed and are capable of performing the functions for which they were intended, as evidenced by an Engineers’ Certificate filed with the Trustee and the Issuer; or (ii) the date on which the Issuer determines, upon the recommendation of or in consultation with the Consulting Engineer, that it cannot complete such Project in a sound and economical manner within a reasonable period of time as evidenced by an Engineers’ Certificate filed with the Trustee and the Issuer; provided that in each case such certificate of the Consulting Engineer shall set forth the amount of all Costs of such Project which have theretofore been incurred, but which on the Date of Completion is or will be unpaid or unreimbursed.

  • Virtual Completion means the premise is in the opinion of the Employer fit for occupation.

  • COMPLETION TIME means the period by ‘date/month’ specified in the ‘Letter of Intent/Award’ or date mutually agreed upon for handing over of the intended scope of work, the erected equipment/plant which are found acceptable by the Engineer, being of required standard and conforming to the specifications of the Contract.

  • Construction Period means the period commencing from the Appointed Date and ending on the date of the Completion Certificate;

  • Commercial Operation Date means the date on which a Material Project is substantially complete and commercially operable.

  • Practical Completion means the completion of the Project where the building is fit for occupancy and/or purpose.

  • Commercial Operation Date (COD) means the date certified by the DISCOM’s committee upon successful commissioning (as per provisions of the PPA) of the project when all equipments as per rated capacity have been installed and energy has flown into the grid.

  • Construction Commencement Date means the date set out in the Addendum, if applicable, by which you must commence construction of the Hotel. For the Hotel to be considered under construction, youmust have begun to pour concrete foundations for the Hotel or otherwise satisfied any site-specific criteria for “under construction” set out in the Addendum.

  • Start-up period means up to a maximum of 7 Academy Financial Years and covers the period up to and including the first Academy Financial Year in which all age groups are present at the Academy (that is, all the pupil cohorts relevant to the age-range of the Academy will have some pupils present).

  • Time of Completion means the time for completing the execution of and passing the Tests on Completion of the Works of any section or part thereof as stated in the Contract (or as extended under Clause...) calculated from the Commencement Date

  • Mechanical Completion means that (a) all components and systems of the Project have been properly constructed, installed and functionally tested according to EPC Contract requirements in a safe and prudent manner that does not void any equipment or system warranties or violate any permits, approvals or Laws; (b) the Project is ready for testing and commissioning, as applicable; (c) Seller has provided written acceptance to the EPC Contractor of mechanical completion as that term is specifically defined in the EPC Contract.

  • Project Completion means the date, as determined by the Division after consultation with the Recipient, that operation of the Project is initiated or is capable of being initiated, whichever comes first.