Acceptance of Final Design, Project Schedule, and Annual Contract Quantity Sample Clauses

Acceptance of Final Design, Project Schedule, and Annual Contract Quantity. As soon as practicable but in no event longer than thirty (30) Business Days following receipt of the Revised Design, Project Schedule, and Annual Contract Quantity as provided in Section 4.1(e), Purchaser shall provide Seller with either (A) Notice accepting such documents, or (B) Notice explaining why Purchaser does not accept such documents and providing comments. The procedures described in this Section 4.1(f) shall be repeated as necessary until Purchaser has accepted the Revised Design, Project Schedule, and Annual Contract Quantity. Upon Purchaser’s Notice to Seller accepting the Revised Design (whereupon such Revised Design shall be considered the “Final Design”), Project Schedule, and Annual Contract Quantity, such documents shall be deemed final and binding on the Parties, and Schedule 2 (System Description), Schedule 4 (Project Schedule), and Schedule 6 (Annual Contract Quantity), in the forms approved by Purchaser, shall be amended and attached to this Agreement. Each of the foregoing Schedules, including the Final Design, may be amended only upon the written approval of the Parties. For any delay in Purchaser’s review of any applicable document beyond Purchaser’s thirty (30) Business Day review period pursuant to this Section 4.1(f), the Project Schedule (including the Expected Commercial Operation Date) shall be extended on a Day-for-Day basis.
AutoNDA by SimpleDocs

Related to Acceptance of Final Design, Project Schedule, and Annual Contract Quantity

  • Overall Project Schedule The Construction Progress Schedule that is approved by the Owner.

  • Statement of Work The Contractor shall provide the services and staff, and otherwise do all things necessary for or incidental to the performance of work, as set forth below:

  • Preliminary Design Phase During the Preliminary Design Phase, the CONSULTANT shall, if requested by the CITY and accepted by the CONSULTANT as part of a Services Authorization:

  • Development Schedule The Project shall substantially comply with the specific timetables and triggers for action set forth in Article 5 of this Agreement. The parties acknowledge that, as provided in G.S. 160A-400.25(b), the failure to meet a commencement or completion date shall not, in and of itself, constitute a material breach of this Agreement pursuant to G.S. 160A-400.27 but must be judged based upon the totality of the circumstances.

  • Detailed Description of Services / Statement of Work Describe fully the services that Contractor will provide, or add and attach Exhibit B to this Agreement.

  • Final Design Phase A. After acceptance by Owner of the Preliminary Design Phase documents, revised opinion of probable Construction Cost as determined in the Preliminary Design Phase, and/or any other Right of Way plan documents, subject to any Owner-directed modifications or changes in the scope, extent, character, or design requirements of or for the Project, and upon written authorization from Owner, Engineer shall:

  • Construction Progress Schedule; Overall Project Schedule The Contractor shall submit for review by the Design Professional and approval by the Owner a Construction Progress Schedule based upon the Design Professional’s Preliminary Design and Construction Schedule and prepared using a CPM (Critical Path Method) process within sixty days after the Effective Date of the Contract, utilizing a full-featured software package in a form satisfactory to the Design Professional and Owner, showing the dates for commencement and completion of the Work required by the Contract Documents, including coordination of mechanical, plumbing, and electrical disciplines, as well as coordination of the various subdivisions of the Work within the Contract. Milestones must be clearly indicated and sequentially organized to identify the critical path of the Project. The Construction Schedule will be developed to represent the CSI specification divisions. It shall have the minimum number of activities required to adequately represent to the Owner the complete scope of Work and define the Project’s (and each Phase’s if phased) critical path and associated activities. The format of the Construction Progress Schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, inspections for Material Completion and Occupancy Date, and Final Completion Date. The Contractor shall submit, along with the Construction Progress Schedule, the Submittal Schedule for approval by the Design Professional, correlating the associated approval dates for the documents with the Construction Progress Schedule. Upon recommendation by the Design Professional and approval by the Owner, the Construction Progress Schedule shall become the Overall Project Schedule, which shall be utilized by the Design Professional, Owner and Contractor. The Contractor must provide the Design Professional and the Owner with monthly updates of the Overall Project Schedule indicating completed activities and any changes in sequencing or activity durations, including approved change orders. See also Article 3.3.5.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Project Specific Milestones In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: