Access to the Authority and the Authority’s Engineer. (i) The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement. (ii) The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted access to the Site during any emergency situation, as decided by the Authority’s Engineer.
Appears in 102 contracts
Samples: Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement, Construction Contract
Access to the Authority and the Authority’s Engineer. (i) 8.7.1 The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) 8.7.2 The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted access to the Site during any emergency situation, as decided by the Authority’s Engineer.
Appears in 32 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement (Dca), Draft Contract Agreement
Access to the Authority and the Authority’s Engineer.
(i) The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted access to the Site during any emergency situation, as decided by the Authority’s Engineer.
Appears in 28 contracts
Samples: Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction Agreement, Contract Agreement
Access to the Authority and the Authority’s Engineer. (i) The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted access to the Site during any emergency situation, as decided by the Authority’s Engineer.
Appears in 18 contracts
Samples: Contract Agreement, Contract Agreement, Contract Agreement
Access to the Authority and the Authority’s Engineer. (i) 8.7.1 The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) 8.7.2 The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted unrestricted access to the Site during any emergency situation, as decided by the Authority’s EngineerEmergency.
Appears in 6 contracts
Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects
Access to the Authority and the Authority’s Engineer. (i) 8.7.1 The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s Authority‟s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) 8.7.2 The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted access to the Site during any emergency situation, as decided by the Authority’s Authority‟s Engineer.
Appears in 5 contracts
Samples: Engineering, Procurement and Construction Agreement, Construction Contract, Draft Contract Agreement
Access to the Authority and the Authority’s Engineer. (i) The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted access to the Site site during any emergency situation, as decided by the Authority’s Engineer.
Appears in 2 contracts
Samples: Construction Contract, Construction Contract
Access to the Authority and the Authority’s Engineer. (i) 8.7.1 The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) 8.7.2 The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-un- restricted access to the Site during any emergency situation, as decided by the Authority’s Engineer.
Appears in 2 contracts
Samples: Contract Agreement, Contract Agreement
Access to the Authority and the Authority’s Engineer. (i) The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s 's Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted access to the Site during any emergency situation, as decided by the Authority’s 's Engineer.
Appears in 2 contracts
Samples: Construction Contract, Construction Contract
Access to the Authority and the Authority’s Engineer. (i) The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and its authorized representatives and the Authority’s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted access to the Site during any emergency situation, as decided by the Authority’s Engineer.
Appears in 1 contract
Access to the Authority and the Authority’s Engineer. (i) 8.7.1 The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s Authority‟s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) 8.7.2 The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-un- restricted access to the Site during any emergency situation, as decided by the Authority’s Authority‟s Engineer.
Appears in 1 contract
Samples: Epc Agreement
Access to the Authority and the Authority’s Engineer. (i) 9.7.1 The Right of Way given to the Contractor Concessionaire hereunder shall always be subject to the right of access of the Authority and the Authority’s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) 9.7.2 The Contractor Concessionaire shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted unrestricted access to the Site during any emergency situation, as decided by the Authority’s EngineerEmergency.
Appears in 1 contract
Samples: Concession Agreement
Access to the Authority and the Authority’s Engineer. (i) The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted access to the Site during any emergency situation, as decided by the Authority’s Engineer.
Appears in 1 contract
Samples: Engineering Procurement and Construction (Epc) Agreement
Access to the Authority and the Authority’s Engineer. (i) The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s Engineer and their employees and agents for inspection, viewing viewing, and exercise of their rights and performance of their obligations under this Agreement.
(ii) The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted unrestricted access to the Site during any emergency situationemergency, as decided by the Authority’s Engineer.
Appears in 1 contract
Samples: Engineering Procurement and Construction (Epc) Agreement
Access to the Authority and the Authority’s Engineer. (i) The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s Authority‟s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted access to the Site during any emergency situation, as decided by the Authority’s Authority‟s Engineer.
Appears in 1 contract
Access to the Authority and the Authority’s Engineer. (i) The Right of Way sites given to the Contractor hereunder shall always be subject to the right theright of access of the Authority and the Authority’s Engineer and their employees and agents andagents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted access to the Site during any emergency situation, as decided by the Authority’s Engineer.
Appears in 1 contract
Samples: Construction Contract
Access to the Authority and the Authority’s Engineer. (i) 9.7.1 The Right of Way given to the Contractor Concessionaire hereunder shall always be subject to the right of access of the Authority and the Authority’s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) 9.7.2 The Contractor Concessionaire shall ensure, subject to all relevant safety procedures, procedures that the Authority has un-restricted unrestricted access to the Site during any emergency situation, as decided by the Authority’s EngineerEmergency.
Appears in 1 contract
Samples: Concession Agreement
Access to the Authority and the Authority’s Engineer. (i) 9.7.1 The Right of Way given to the Contractor Concessionaire hereunder shall always be subject to the right of access of the Authority and the Authority’s Authority‟s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) 9.7.2 The Contractor Concessionaire shall ensure, subject to all relevant safety procedures, procedures that the Authority has un-restricted unrestricted access to the Site during any emergency situation, as decided by the Authority’s EngineerEmergency.
Appears in 1 contract
Samples: Concession Agreement
Access to the Authority and the Authority’s Engineer. (i) The Right of Way given to the Contractor hereunder shall always be subject to the right of access of the Authority and the Authority’s Authority‟s Engineer and their employees and agents for inspection, viewing and exercise of their rights and performance of their obligations under this Agreement.
(ii) The Contractor shall ensure, subject to all relevant safety procedures, that the Authority has un-restricted access to the Site during any emergency situation, as decided by the Authority’s Engineer.
Appears in 1 contract
Samples: Epc Agreement