Additional Retainage in Disputes Sample Clauses

Additional Retainage in Disputes. In the event a dispute arises between City and Contractor, which dispute is based upon increased costs claimed by Contractor to be occasioned by delays or other actions of another contractor or otherwise, additional retainage in the sum of one and one half (1 1/2) times the amount of any possible liability may be withheld until such time as a final resolution is agreed to by all parties directly or indirectly involved, unless the contractor causing the additional claim furnishes a bond satisfactory to City to indemnify City against the claim. All such monies retained by City may be withheld from Contractor until substantial completion of the Contract.
AutoNDA by SimpleDocs

Related to Additional Retainage in Disputes

  • Calculation Disputes If the Defaulting Party disputes the Non-Defaulting Party’s calculation of the Settlement Amount or Termination Payment, in whole or in part, the Defaulting Party will, within two Business Days of receipt of Non-Defaulting Party’s calculation, provide to the Non- Defaulting Party a detailed written explanation of the basis for such dispute; provided, however, that the Defaulting Party must first transfer Performance Assurance to the Non-Defaulting Party in an amount equal to the full Settlement Amount or Termination Payment, as applicable. References to Defaulting Party and Non-Defaulting Party in this Section include the Potentially Defaulting Party and Potentially Non-Defaulting Party, as applicable.

  • Payment Disputes We will not exercise Our rights under Section 6.3 (Overdue Charges) or 6.4 (Suspension of Service and Acceleration) above if You are disputing the applicable charges reasonably and in good faith and are cooperating diligently to resolve the dispute.

  • Contract Disputes The Parties shall deal in good faith and attempt to resolve potential disputes informally. If the dispute concerning a question of fact arising under the terms of this Contract is not disposed of in a reasonable period of time by the Contractor’s Supervisor and the County‘s project manager as specified in Article 25. Notices by way of the following process, such matter shall be brought to the attention of the County DPA by way of the following process:

  • CLASS-ARBITRATION WAIVER ARBITRATION IS HANDLED ON AN INDIVIDUAL BASIS. IF A DISPUTE IS ARBITRATED, YOU AND WE EXPRESSLY WAIVE ANY RIGHT TO PARTICIPATE AS A CLASS REPRESENTATIVE OR CLASS MEMBER ON ANY CLASS CLAIM YOU MAY HAVE AGAINST US OR WE AGAINST YOU, OR AS A PRIVATE ATTORNEY GENERAL OR IN ANY OTHER REPRESENTATIVE CAPACITY, TO THE MAXIMUM EXTENT PERMITTED BY LAW. YOU AND WE ALSO WAIVE ANY RIGHT TO CLASS ARBITRATION OR ANY CONSOLIDATION OF INDIVIDUAL ARBITRATIONS.

  • Investment disputes 1. Any dispute between an investor of one Contracting Party and the other Contracting party in connection with an investment in the territory of the other Contracting Party shall, as far as possible, be settled amicably through negotiations between the parties to the dispute. The party intending to resolve such dispute through negotiations shall give written notice to the other of its intention.

  • Submission of a Claim to Arbitration 1. An investor that meets the conditions precedent in Article 22 (Conditions Precedent to Submission of a Claim to Arbitration) may submit a claim to arbitration under:

  • Referral to Arbitration: Local Matters a. If the grievance is not resolved at Step Three within ten (10) working days of the meeting referred to in Article A.6.4, the local or the employer where applicable may refer a "local matters grievance," as defined in Appendix 2 and Addenda, to arbitration within a further fifteen (15) working days.

  • Alternative Arbitration Proceedings Alternatively, the Parties may refer the matter to the Nairobi Centre for International Arbitration (NCIA) which offers a neutral venue for the conduct of national and international arbitration with commitment to providing institutional support to the arbitral process.

  • Cost of Arbitration The fees for a single Arbitrator or a Chair of a Board of Arbitration shall be shared equally by the parties. Other costs incurred by each party shall be the responsibility of that party.

  • Level IV - Arbitration Should the grievance remain unresolved at Level III, the UFO may, within twenty (20) days following conclusion of Level III, provide written notice to the District to submit the matter to arbitration.