Common use of Adjustment of the Work duration schedule Clause in Contracts

Adjustment of the Work duration schedule. the Contractor agrees that whenever it becomes apparent to the County, from the current monthly status review meeting or the schedule, that phasing or JOC Task Order milestone dates will not be met, it will take some or all of the following actions at no additional cost to the County. 1. Increase construction manpower in such quantities and crafts as will eliminate the backlog of Work. 2. Increase the number of working hours per shift, shifts per working day. 3. Reschedule the Work under the JOC Task Order in conformance with all other requirements. The Contractor agrees to be liable for any additional cost incurred by the County for the adjustment of project schedules. 4. Prior to proceeding with any of the above actions, the Contractor agrees to notify and obtain approval from the County’s Project Manager for the proposed schedule changes. If such actions are approved, the Contractor agrees to incorporate the revisions into the schedule.

Appears in 28 contracts

Samples: Job Order Contract, Job Order Contract, Job Order Contract for Electrical Services

AutoNDA by SimpleDocs

Adjustment of the Work duration schedule. the Contractor agrees that whenever it becomes apparent to the County, from the current monthly status review meeting or the schedule, that phasing or JOC Task Order milestone dates will not be met, it will take some or all of the following actions at no additional cost to the County. 1. Increase construction manpower in such quantities and crafts as will eliminate the backlog of Work. 2. Increase the number of working hours per shift, shifts per working day. 3. Reschedule the Work under the JOC Task Order in conformance with all other requirements. The Contractor agrees to be liable for any additional cost incurred by the County for the adjustment of project schedules. 4. Prior to proceeding with any of the above actions, the Contractor agrees to notify and obtain approval from the County’s Project Manager for the fro proposed schedule changes. If such actions are approved, the Contractor agrees to incorporate the revisions into the schedule.

Appears in 1 contract

Samples: Job Order Contract

AutoNDA by SimpleDocs