Common use of Allowance Work Clause in Contracts

Allowance Work. 6.8.1 CM/GC shall not perform any Allowance Work without prior written authorization to proceed, followed by execution by Owner of a Change Order approving the Specifications for the Allowance Work and the price thereof. 6.8.2 Owner shall be entitled to apply any Allowance line items that are not been fully expended to other line item Allowances that have been fully expended, without any resulting increase in the GMP. 6.8.3 CM/GC has used its best efforts to estimate the price for each line item of the Allowances included in the GMP. If the total Cost of one line item of the Allowance Work exceeds the total price for such line item of the Allowance Work, CM/GC shall immediately notify Owner, and CM/GC shall not perform any more of the Allowance Work line item in excess of such line item price until either (i) the parties agree that the additional Allowance Work will be performed within the then-current line item price without any increase in the GMP or (ii) the parties agree that the Owner will apply other unused Allowance Work funds for another line item to the line item at issue, without any resulting increase in the GMP, or (iii) a Change Order is executed to increase the GMP by the excess cost of the Allowance Work line item, or (iv) the Owner directs in writing the CM/GC to proceed with such line item Allowance Work pending resolution otherwise under this Section 6.8.3. 6.8.4 The Contract Sum shall not include any Allowance items not identified in the GMP Amendment or the GMP Supporting Documents until such allowance item is reduced to a fixed price by Change Order or Amendment. 6.8.5 If at the Final Completion of the Project, any portion of the Allowance funds remains unexpended, the GMP shall be reduced by a corresponding amount via a Change Order or Amendment.

Appears in 5 contracts

Samples: Cm/Gc Contract, Construction Manager/General Contractor Contract, Construction Manager/General Contractor Contract

AutoNDA by SimpleDocs

Allowance Work. 6.8.1 CM/GC shall not perform any Allowance Work without prior written authorization to proceed, followed by execution by Owner of a Change Order approving the Specifications for the Allowance Work and the price thereof. 6.8.2 Owner shall be entitled to apply any Allowance line items that are not been fully expended to other line item Allowances that have been fully expended, without any resulting increase in the GMP. 6.8.3 CM/GC has used its best efforts to estimate the price for each line item of the Allowances included in the GMP. If the total Cost of one line item of the Allowance Work exceeds the total price for such line item of the Allowance Work, CM/GC shall immediately notify Owner, and CM/GC shall not perform any more of the Allowance Work line item in excess of such line item price until either (i) the parties agree that the additional Allowance Work will be performed within the then-current line item price without any increase in the GMP or (ii) the parties agree that the Owner will apply other unused Allowance Work funds for another line item to the line item at issue, without any resulting increase in the GMP, or (iii) a Change Order is executed to increase the GMP by the excess cost of the Allowance Work line item, or (iv) the Owner directs in writing the CM/GC to proceed with such line item Allowance Work pending resolution otherwise under this Section 6.8.3... 6.8.4 The Contract Sum shall not include any Allowance items not identified in the GMP Amendment or the GMP Supporting Documents until such allowance item is reduced to a fixed price by Change Order or Amendment. 6.8.5 If at the Final Completion of the Project, any portion of the Allowance funds remains unexpended, the GMP shall be reduced by a corresponding amount via a Change Order or Amendment.

Appears in 2 contracts

Samples: Cm/Gc Contract, Cm/Gc Contract

Allowance Work. 6.8.1 CM/GC shall not perform any Allowance Work without prior written authorization to proceed, followed by execution by Owner of a Change Order by Amendment approving the Specifications for the Allowance Work and the price thereof. 6.8.2 Owner shall be entitled to apply any Allowance line items that are not been fully expended to other line item Allowances that have been fully expended, without any resulting increase in the GMP. 6.8.3 CM/GC has used its best efforts to estimate the price for each line item of the Allowances included in the GMP. If the total Cost of one line item of the Allowance Work exceeds the total price for such line item of the Allowance Work, CM/GC shall immediately notify Owner, and CM/GC shall not perform any more of the Allowance Work line item in excess of such line item price until either either (i) the parties agree that the additional Allowance Work will be performed within the then-current line item price without any increase in the GMP GMP, or (ii) the parties agree that the Owner will apply other unused Allowance Work funds for another line item to the line item at issue, without any resulting increase in the GMP, or (iii) a Change Order Amendment is executed to increase the GMP by the excess cost of the Allowance Work line item, or (iv) the Owner directs in writing the CM/GC to proceed with such line item Allowance Work pending resolution otherwise under this Section 6.8.3. 6.8.4 The Contract Sum shall not include any Allowance items not identified in the GMP Amendment or the GMP Supporting Documents until such allowance Allowance item is reduced to a fixed price by Change Order or Amendment. 6.8.5 If at the Final Completion of the Project, any portion of the Allowance funds remains unexpended, the GMP shall be reduced by a corresponding amount via a Change Order or Amendment.

Appears in 2 contracts

Samples: Construction Manager/General Contractor Contract, Construction Manager/General Contractor (Cm/Gc) Contract

Allowance Work. 6.8.1 CM/GC shall not perform any Allowance Work without prior written authorization to proceed, followed by execution by Owner of a Change Order approving the Specifications for the Allowance Work and the price thereof. 6.8.2 Owner shall be entitled to apply any Allowance line items that are not been fully expended to other line item Allowances that have been fully expended, without any resulting increase in the GMP. 6.8.3 CM/GC has used its best efforts to estimate the price for each line item of the Allowances included in the GMP. If the total Cost of one line item of the Allowance Work exceeds the total price for such line item of the Allowance Allowances Work, then CM/GC shall immediately notify Owner, and CM/GC shall not perform any more of the Allowance Work line item in excess of such line item price until either (i) the parties agree that the additional Allowance Work will be performed within the then-current line line-item price without any increase in the GMP or (ii) the parties agree that the Owner will apply other unused Allowance Work funds for another line item to the line item at issue, without any resulting increase in the GMP, or (iii) a Change Order is executed to increase the GMP by the excess cost of the Allowance Work line itemWork, or (iv) the Owner directs in writing the CM/GC to proceed with such line item Allowance Work pending resolution otherwise under this Section 6.8.3. 6.8.4 The Contract Sum shall not include any Allowance items not identified in the GMP Amendment or the GMP Supporting Documents until such allowance item is reduced to a fixed price by Change Order or Amendment. 6.8.5 If at the Final Completion of the Project, any portion of the Allowance funds remains unexpended, the GMP shall be reduced by a corresponding amount via a Change Order or Amendment.

Appears in 1 contract

Samples: Construction Manager/General Contractor Contract

AutoNDA by SimpleDocs

Allowance Work. 6.8.1 CM/GC shall not perform any work that is the subject of an Allowance Work (the “Allowance Work”) without prior written authorization to proceed, followed by execution by the Owner of a Change Order approving the Specifications for the Allowance Work and the price thereoffor the Allowance Work. 6.8.2 Owner shall be entitled to apply any Allowance Work line items that are have not been fully expended to other Allowance Work line item Allowances items that have been fully expended, without any resulting increase in the GMP. 6.8.3 CM/GC has used its best efforts to estimate the price for each line item of the Allowances included in the GMP. If the total Cost of one line item cost of the Allowance Work exceeds the total price for such line item of Allowance Work items within the Allowance WorkGMP, CM/GC shall immediately notify Owner, and the CM/GC shall not perform any more of the Allowance Work line item in excess of such line item price amount until either (i) the parties Parties agree that the CM/GC shall perform any additional Allowance Work will be performed within the then-then- current line item price without any increase in the GMP or (ii) the parties agree that the Owner will apply other unused Allowance Work funds for another line item to the line item at issue, without any resulting increase in the GMP, or (iii) a Change Order GMP Amendment is executed to increase the GMP by the excess cost of the Allowance Work line item, or (iv) the Owner directs in writing the CM/GC to proceed with such line item Allowance Work pending resolution otherwise under this Section 6.8.3Work. 6.8.4 The Contract Sum shall must not include any Allowance Work items that are not identified in the GMP Amendment or the GMP Supporting Documents until such allowance Allowance Work item is reduced to a fixed price by Change Order or Amendment. 6.8.5 If at the Final Completion of the Project, Project any portion of the Allowance funds remains unexpended, the GMP shall must be reduced by a corresponding amount via a Change Order or Amendment.

Appears in 1 contract

Samples: Construction Manager/General Contractor Contract