Common use of Alternate Option Clause in Contracts

Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.

Appears in 23 contracts

Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

AutoNDA by SimpleDocs

Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment System Upgrade Facilities by the designated dates.

Appears in 11 contracts

Samples: Transmission Facility Interconnection Agreement, Transmission Facility Interconnection Agreement, Transmission Facility Interconnection Agreement

Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s 's Attachment Facilities by the designated dates.

Appears in 11 contracts

Samples: Service Agreement, Service Agreement, Service Agreement

Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.

Appears in 4 contracts

Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) 30 Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment System Upgrade Facilities by the designated dates.

Appears in 4 contracts

Samples: Service Agreement, Interconnection Agreement, Service Agreement

Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment System Upgrade Facilities by the designated dates.. 12

Appears in 3 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.of

Appears in 3 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission OwnerOwners, the Connecting Transmission Owner Owners shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.National Grid

Appears in 3 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

AutoNDA by SimpleDocs

Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s 's Attachment Facilities by the designated dates.. If Transmission Owner subsequently fails to complete Transmission Owner's Attachment Facilities by the In-Service Date, to the extent necessary to provide back feed power; or fails to complete System Upgrade Facilities by the Initial

Appears in 2 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.Connecting

Appears in 2 contracts

Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s 's Attachment Facilities by the designated dates.. If Transmission Owner subsequently fails to

Appears in 1 contract

Samples: Service Agreement

Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.)

Appears in 1 contract

Samples: Interconnection Agreement

Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.assume

Appears in 1 contract

Samples: Transmission Facility Interconnection Agreement