Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.
Appears in 23 contracts
Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement
Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment System Upgrade Facilities by the designated dates.
Appears in 11 contracts
Samples: Transmission Facility Interconnection Agreement, Transmission Facility Interconnection Agreement, Transmission Facility Interconnection Agreement
Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s 's Attachment Facilities by the designated dates.
Appears in 11 contracts
Samples: Service Agreement, Service Agreement, Service Agreement
Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.
Appears in 4 contracts
Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement
Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) 30 Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment System Upgrade Facilities by the designated dates.
Appears in 4 contracts
Samples: Service Agreement, Interconnection Agreement, Service Agreement
Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment System Upgrade Facilities by the designated dates.. 12
Appears in 3 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.of
Appears in 3 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission OwnerOwners, the Connecting Transmission Owner Owners shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.National Grid
Appears in 3 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s 's Attachment Facilities by the designated dates.. If Transmission Owner subsequently fails to complete Transmission Owner's Attachment Facilities by the In-Service Date, to the extent necessary to provide back feed power; or fails to complete System Upgrade Facilities by the Initial
Appears in 2 contracts
Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement
Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.Connecting
Appears in 2 contracts
Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement
Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s 's Attachment Facilities by the designated dates.. If Transmission Owner subsequently fails to
Appears in 1 contract
Samples: Service Agreement
Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.)
Appears in 1 contract
Samples: Interconnection Agreement
Alternate Option. If the dates designated by Developer are acceptable to Connecting Transmission Owner, the Connecting Transmission Owner shall so notify Developer and NYISO within thirty (30) Calendar Days, and shall assume responsibility for the design, procurement and construction of the Connecting Transmission Owner’s Attachment Facilities by the designated dates.assume
Appears in 1 contract