Approved Encumbrancer’s Right to Cure Sample Clauses

Approved Encumbrancer’s Right to Cure. Before terminating this Lease for an event of default by Lessee, Lessor shall deliver written notice of intent to terminate to each Approved Encumbrancer who has provided Lessor with Approved Encumbrancer’s mailing address. Approved Encumbrancer shall have the right to cure such default if Lessee fails to do so. Lessor shall accept such performance by the Approved Encumbrancer as though the same had been done or performed by Lessee. Provided all Rent is paid current (including during the 30 Day period granted to Approved Encumbrancer), each Approved Encumbrancer shall have 30 Days more than the time given to Lessee within which to cure a default, which time period will commence upon the later of (i) the delivery of such notice to Approved Encumbrancer or (ii) the expiration of the time period available to Lessee. The Approved Encumbrancer shall have the right to enter upon the Leased Premises to give such performance, and Approved Encumbrancer shall be responsible for any actions or omissions (including any injuries and damage to the Leased Premises) of Approved Encumbrancer and its employees, contractors and designees who enter the Leased Premises. The Approved Encumbrancer may have such additional rights to cure a default by Lessee under this Lease as may be set forth in an Approved Encumbrance. Notwithstanding the period of time granted to Approved Encumbrancer to cure a default by Lessee under this Lease, in no event shall Lessor be prevented, prohibited, limited or impaired in any manner from exercising its rights and remedies as against Lessee under this Lease (except only for a termination of this Lease), and, furthermore, Lessor may take such commercially reasonable actions as Lessor may determine in order to protect and safeguard the Leased Premises, to correct a violation of Legal Requirements, to prevent waste, and to protect the public health and safety.
AutoNDA by SimpleDocs

Related to Approved Encumbrancer’s Right to Cure

  • Buyer’s Rights and Remedies If at any time an Event of Default with respect to Seller has occurred and is continuing, then, unless the Seller has paid in full all of its obligations that are then due, including those under Section 7.2(c) of this Agreement (“Obligations”), the Buyer may exercise one or more of the following rights and remedies: (i) all rights and remedies available to a Secured Party under applicable law with respect to posted Eligible Collateral held by the Buyer, (ii) the right to set-off any amounts payable by the Seller with respect to any Obligations against any posted Eligible Collateral or the Cash equivalent of any posted Eligible Collateral held by the Buyer, or (iii) the right to liquidate any posted Eligible Collateral held by the Buyer and to apply the proceeds of such liquidation of the posted Eligible Collateral to any amounts payable to the Buyer with respect to the Obligations in such order as the Buyer may elect. For purposes of this Paragraph 6, the Buyer may draw on the entire undrawn portion of any Letter of Credit. Cash proceeds that are not applied to the Obligations shall be maintained in accordance with the terms of this CSA. The Seller shall remain liable for amounts due and owing to the Secured Party that remain unpaid after the application, pursuant to this Paragraph 6, of Eligible Collateral to the Obligations.

  • STATE'S RIGHT TO CLEAN UP 6.3.1 If a dispute arises between the Contractor and separate contractors as to their responsibility for cleaning up as required by Paragraph 4.15 of these General Conditions, the State may clean up and charge the cost thereof to the Contractor.

  • OWNER’S RIGHT TO CLEAN UP If a dispute arises among the Design-Builder, separate contractors and the Owner as to the responsibility under their respective contracts for maintaining the premises and surrounding area free from waste materials and rubbish, the Owner may clean up and will allocate the cost among those responsible.

  • DXC’s Right to Inspect DXC may, at any time, inspect the software, Services, or Products and associated manufacturing processes. Inspection may occur at Supplier’s facility, plant or subcontractor’s plant. Supplier will inform its vendors and subcontractors of DXC’s right to inspect and shall secure that right for DXC if necessary.

  • BUYER’S RIGHT TO CANCEL If after completion of an appraisal by a licensed appraiser, Buyer receives written notice from the Lender or the appraiser that the Property has appraised for less than the Purchase Price (a “Notice of Appraised Value”), Buyer may cancel the REPC by providing written notice to Seller (with a copy of the Notice of Appraised Value) no later than the Financing & Appraisal Deadline referenced in Section 24(c); whereupon the Xxxxxxx Money Deposit shall be released to Buyer without the requirement of further written authorization from Seller.

  • OWNER’S RIGHT TO CARRY OUT THE WORK If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within a ten (10)-calendar day period after receipt of written notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, the Owner may, without prejudice to other remedies the Owner may have, correct such deficiencies. In such case an appropriate Change Order shall be issued deducting from payments then or thereafter due the Contractor the reasonable cost of correcting such deficiencies, including Owner’s expenses and compensation for the Architect’s additional services made necessary by such default, neglect or failure. Such action by the Owner and amounts charged to the Contractor are both subject to prior approval of the Architect. If payments then or thereafter due the Contractor are not sufficient to cover such amounts, the Contractor shall pay the difference to the Owner.

  • STATE'S RIGHT TO CARRY OUT THE WORK 3.4.1 If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within seven days after receipt of written notice from the State to commence and continue correction of such default or neglect with diligence and promptness, the State may, after seven days following receipt by the Contractor of an additional written notice and without prejudice to any other remedy he may have, make good such deficiencies. In such case an appropriate Change Order shall be issued deducting from the payments then or thereafter due the Contractor the cost of correcting such deficiencies, including compensation for the Architect's and the State’s additional services made necessary by such default, neglect or failure. Such action by the State and the amount charged to the Contractor are both subject to review by the Architect under Paragraph 2.2.14 of these General Conditions. If the payments then or thereafter due the Contractor are not sufficient to cover the amounts paid by the State to make good such deficiencies, then the Contractor shall pay the difference to the Owner.

  • Landlord’s Right of Entry Landlord shall be allowed access to the premises, at any reasonable hour for the purpose of examining or exhibiting of same, and for making such repairs or alterations either as Landlord may deem necessary or appropriate or as Tenant may request. Tenants are not allowed to interfere with showings as this is a direct violation of your lease. In the City of Urbana Landlord will give tenants 24 hours notice. While not required in Champaign, Landlord will make reasonable effort to give tenant advance notice and may provide this notice through phone, email, verbal or posting notice. In cases of emergency repairs or due to complaints, Landlord may have to enter the premises with no formal notice.

  • OWNER’S RIGHT TO STOP THE WORK If the Contractor fails to correct Work that is not in accordance with the requirements of the Contract Documents as required by Section 12.2 or repeatedly fails to carry out Work in accordance with the Contract Documents, the Owner may issue a written order to the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, the right of the Owner to stop the Work shall not give rise to a duty on the part of the Owner to exercise this right for the benefit of the Contractor or any other person or entity.

  • Obligation to Notify Owner of Existing Hazardous Materials The Contractor shall immediately notify the Owner and the Design Professional, both orally and in writing, of the presence and location of any physical evidence of, or information regarding the presence of Hazardous Materials at the Site of which it becomes aware. If the Contractor encounters Hazardous Materials on the Site the Contractor shall (i) immediately stop performance of Work or that portion of the Work affected by or affecting such Hazardous Materials; (ii) secure the contaminated area against intrusion; (iii) not disturb or remove the Hazardous Materials; (iv) not proceed, or allow any subcontractor or supplier to proceed, with any Work or other activities in the area affected by such Hazardous Materials until such materials have been properly remediated and until directed in writing to do so by the Owner; and, (v) take any other steps necessary to protect life and health and the surrounding environment. The Contractor shall be entitled to adjustment of the Contract Time and the Contract Sum pursuant to Section 5, Part 2 of these General Conditions in order to compensate for the impact of any required demolition, re-work, shutdown, delay, protection of work, disruption, and start-up resulting from the encountering of such Hazardous Materials on the Site for which the Contractor is not responsible.