Common use of Authorization Required Prior to Parallel Operation Clause in Contracts

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Provider's Transmission System without prior written authorization of the Transmission Provider. The Transmission Provider will provide such authorization once the Transmission Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 25 contracts

Samples: Small Generator Interconnection Agreement (Sgia), Small Generator Interconnection Agreement (Sgia), Small Generator Interconnection Agreement (Sgia)

AutoNDA by SimpleDocs

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Distribution Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Distribution Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Distribution Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Distribution Provider's Transmission Distribution System without prior written authorization of the Transmission Distribution Provider. The Transmission Distribution Provider will provide such authorization once the Transmission Distribution Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 13 contracts

Samples: Small Generator Interconnection Agreement, Small Generator Interconnection Agreement, Interconnection Agreement

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Provider Owner shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Provider Owner shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Provider Owner shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Provider's Owners Transmission System without prior written authorization of the Transmission Provider. Owner The Transmission Provider Owner will provide such authorization once the Transmission Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 10 contracts

Samples: Small Generator Interconnection Agreement, Small Generator Interconnection Agreement, Small Generator Interconnection Agreement

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Distribution Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Distribution Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Distribution Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Distribution Provider's Transmission Distribution System without prior written authorization of the Transmission Distribution Provider. The Transmission Distribution Provider will provide such authorization once the Transmission Distribution Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 10 contracts

Samples: Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Provider Owner shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Provider Owner shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. , The Transmission Provider Owner shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Provider's Owners Transmission System without prior written authorization of the Transmission ProviderOwner. The Transmission Provider Owner will provide such authorization once the Transmission Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 6 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Provider Owner shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Provider Owner shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Provider Owner shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 . The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Provider's Owners Transmission System without prior written authorization of the Transmission Provider. Owner The Transmission Provider Owner will provide such authorization once the Transmission Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 5 contracts

Samples: Small Generator Interconnection Agreement (Sgia), Small Generator Interconnection Agreement (Sgia), Iso Agreement

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-in- service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Provider's Transmission System without prior written authorization of the Transmission Provider. The Transmission Provider will provide such authorization once the Transmission Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 5 contracts

Samples: Small Generator Interconnection Agreement (Sgia), Small Generator Interconnection Agreement (Sgia), Small Generator Interconnection Agreement (Sgia)

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Provider Owner shall use Reasonable Efforts to list any applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Provider Owner shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Provider Owner shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Provider's Owner’s Transmission System without prior written authorization of the Transmission ProviderOwner. The Transmission Provider Owner will provide such authorization once the Transmission Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 3 contracts

Samples: Small Generator Interconnection Agreement (Sgia), Small Generator Interconnection Agreement (Sgia), Small Generator Interconnection Agreement (Sgia)

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Distribution Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Distribution Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Distribution Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Distribution Provider's Transmission Distribution System without prior written authorization of the Transmission Distribution Provider. The Transmission Distribution Provider will provide such authorization once the Transmission Distribution Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Small Generator Interconnection Agreement (Sgia)

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Provider shall use Reasonable Efforts to list applicable parallel operation operational requirements in Attachment 5 of this Agreement. Additionally, the Transmission Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-in- service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Provider's Transmission System without prior written authorization of the Transmission Provider. The Transmission Provider will provide such authorization once the Transmission Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Small Generator Interconnection Agreement (Sgia)

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Distribution Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Distribution Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Distribution Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Provider's Transmission Distribution Providers Distribution System without prior written authorization of the Transmission Distribution Provider. The Transmission Distribution Provider will provide such authorization once the Transmission Distribution Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Small Generator Interconnection Agreement (Sgia)

Authorization Required Prior to Parallel Operation. 2.2.1 3.2.1 The Transmission Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 4 of this Agreement. Additionally, the Transmission Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 3.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Provider's ’s Transmission System without prior written authorization of the Transmission Provider. The Transmission Provider will provide such authorization once the Transmission Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Small Generator Interconnection Agreement (Sgia)

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Provider's Transmission System without prior written authorization of the Transmission Provider. The Transmission Provider will provide such authorization once the Transmission Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Standard Small Generator Interconnection Agreement (Sgia)

Authorization Required Prior to Parallel Operation. 2.2.1 2.2.1. The Transmission Distribution Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Distribution Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Distribution Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 2.2.2. The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Distribution Provider's Transmission Distribution System without prior written authorization of the Transmission Distribution Provider. The Transmission Distribution Provider will provide such authorization once the Transmission Distribution Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Interconnection Agreement

AutoNDA by SimpleDocs

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Distribution Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Distribution Provider shall notify the Interconnection Customer of any changes to changesto these requirements as soon as they are known. The Transmission Distribution Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Distribution Provider's Transmission Distribution System without prior written authorization of the Transmission Distribution Provider. The Transmission Distribution Provider will provide such authorization once the Transmission Distribution Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Small Generator Interconnection Agreement

Authorization Required Prior to Parallel Operation. 2.2.1 2.2.1. The Interconnecting Transmission Provider Owner shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Interconnecting Transmission Provider Owner shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Interconnecting Transmission Provider Owner shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 2.2.2. The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Interconnecting Transmission Provider's Transmission System Owner’s transmission facilities without prior written authorization of the Interconnecting Transmission ProviderOwner. The Transmission Provider will provide such authorization once the Transmission Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Service Agreement

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Provider's Transmission System without prior written authorization of the Transmission Provider. The Transmission Provider will provide such authorization once the Transmission Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Standard Small Generator Interconnection Agreement (Sgia)

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Provider's Transmission System without prior written authorization of the Transmission Provider. The Transmission Provider will provide such authorization once the Transmission Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Standard Small Generator Interconnection Agreement (Sgia)

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Distribution Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Distribution Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Distribution Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Distribution Provider's Transmission ’s Distribution System without prior written authorization of the Transmission Distribution Provider. The Transmission Distribution Provider will provide such authorization once the Transmission Distribution Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Interconnection Agreement

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Provider's ’s Transmission System without prior written authorization of the Transmission Provider. The Transmission Provider will provide such authorization once the Transmission Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Standard Small Generator Interconnection Agreement (Sgia)

Authorization Required Prior to Parallel Operation. 2.2.1 The Transmission Provider All applicable Operating Requirements shall use Reasonable Efforts to list applicable parallel operation requirements be listed in Attachment 5 of this Agreement. Additionally, the Transmission Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Provider and Transmission Owner shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-service date. 2.2.2 The Interconnection Customer shall not interconnect and operate its Small Generating Facility in parallel with the NL Transmission Provider's System or NL Sub-Transmission System without prior written authorization of the Transmission Provider. The Transmission Provider will provide such authorization once upon confirmation with the Transmission Provider receives notification Owner that the Interconnection Customer has complied with all applicable parallel operation requirementsOperating Requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Generator Interconnection Agreement

Authorization Required Prior to Parallel Operation. 2.2.1 2.2.1. The Transmission Distribution Provider shall use Reasonable Efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the Transmission Distribution Provider shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The Transmission Distribution Provider shall make Reasonable Efforts to cooperate with the Interconnection Customer in meeting requirements necessary for the Interconnection Customer to commence parallel operations by the in-in- service date. 2.2.2 2.2.2. The Interconnection Customer shall not operate its Small Generating Facility in parallel with the Transmission Distribution Provider's Transmission Distribution System without prior written authorization of the Transmission Distribution Provider. The Transmission Distribution Provider will provide such authorization once the Transmission Distribution Provider receives notification that the Interconnection Customer has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

Appears in 1 contract

Samples: Interconnection Agreement