Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability. 10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site: 10.1.3.2.1 Overhead and profit; 10.1.3.2.2 Supervision; 10.1.3.2.3 General conditions; 10.1.3.2.4 Xxxxxx & Mobilization (not more than 1%); 10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%); 10.1.3.2.6 Bonds and insurance (not more than 2%); 10.1.3.2.7 Close-out documentation (not less than 3%); 10.1.3.2.8 Demolition; 10.1.3.2.9 Installation; 10.1.3.2.10 Rough-in; 10.1.3.2.11 Finishes; 10.1.3.2.12 Testing;
Appears in 7 contracts
Samples: Facilities Lease, Facilities Lease, Facilities Lease
Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability.
10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site:
10.1.3.2.1 Overhead and profit;
10.1.3.2.2 Supervision;
10.1.3.2.3 General conditions;
10.1.3.2.4 Xxxxxx Layout & Mobilization (not more than 1%);
10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%);
10.1.3.2.6 Bonds and insurance (not more than 23%);
10.1.3.2.7 Close-out documentation (not less than 3%);
10.1.3.2.8 Demolition;
10.1.3.2.9 Installation; ;
10.1.3.2.10 Rough-in; ;
10.1.3.2.11 Finishes;
10.1.3.2.12 Testing;
10.1.3.2.13 Owner and Maintenance Manuals; 10.1.3.2.12 Testing;and
10.1.3.2.14 Punchlist and District acceptance.
Appears in 6 contracts
Samples: Facilities Lease, Facilities Lease, Facilities Lease
Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability.
10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site:
10.1.3.2.1 Overhead and profit;
10.1.3.2.2 Supervision;
10.1.3.2.3 General conditions;
10.1.3.2.4 Xxxxxx & Mobilization (not more than 1%);
10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%);
10.1.3.2.6 Bonds and insurance (not more than 2%);
10.1.3.2.7 Close-out documentation (not less than 3%);
10.1.3.2.8 Demolition;
10.1.3.2.9 Installation; ;
10.1.3.2.10 Rough-in; ;
10.1.3.2.11 Finishes;
10.1.3.2.12 Testing;
10.1.3.2.13 Owner and Maintenance Manuals; 10.1.3.2.12 Testing;and
10.1.3.2.14 Punchlist and District acceptance.
Appears in 4 contracts
Samples: Facilities Lease, Facilities Lease, Facilities Lease
Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability.
10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site:
10.1.3.2.1 Overhead and profit;
10.1.3.2.2 Supervision;
10.1.3.2.3 General conditions;
10.1.3.2.4 Xxxxxx Layout & Mobilization (not more than 1%);
10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%);
10.1.3.2.6 Bonds and insurance (not more than 23%);
10.1.3.2.7 Close-out documentation (not less than 3%);
10.1.3.2.8 Demolition;
10.1.3.2.9 Installation; 10.1.3.2.10 Rough-in; 10.1.3.2.11 Finishes; 10.1.3.2.12 Testing;
Appears in 3 contracts
Samples: Facilities Lease, Facilities Lease, Facilities Lease
Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability.
10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site:
10.1.3.2.1 Overhead and profit;
10.1.3.2.2 Supervision;
10.1.3.2.3 General conditions;
10.1.3.2.4 Xxxxxx Layout & Mobilization (not more than 1%);
10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%);
10.1.3.2.6 Bonds and insurance (not more than 2%);
10.1.3.2.7 Close-out documentation (not less than 3%);
10.1.3.2.8 Demolition;
10.1.3.2.9 Installation; 10.1.3.2.10 Rough-in; 10.1.3.2.11 Finishes; 10.1.3.2.12 Testing;
Appears in 3 contracts
Samples: Facilities Lease, Facilities Lease, Facilities Lease
Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability.
10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site:
10.1.3.2.1 Overhead and profit;
10.1.3.2.2 Supervision;
10.1.3.2.3 General conditions;
10.1.3.2.4 Xxxxxx Layout & Mobilization (not more than 1%);
10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%);
10.1.3.2.6 Bonds and insurance (not more than 22.5%);
10.1.3.2.7 Close-out documentation (not less than 3%);
10.1.3.2.8 Demolition;
10.1.3.2.9 Installation; ;
10.1.3.2.10 Rough-in; ;
10.1.3.2.11 Finishes;
10.1.3.2.12 Testing;
10.1.3.2.13 Owner and Maintenance Manuals; 10.1.3.2.12 Testing;and
10.1.3.2.14 Punchlist and District acceptance.
Appears in 2 contracts
Samples: Facilities Lease, Facilities Lease
Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability.
10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work Work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site:
10.1.3.2.1 Overhead and profit;
10.1.3.2.2 Supervision;
10.1.3.2.3 General conditions;
10.1.3.2.4 Xxxxxx & Mobilization (not more than 1%);
10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%);
10.1.3.2.6 Bonds and insurance (not more than 2%);
10.1.3.2.7 Close-out documentation (not less than 3%);
10.1.3.2.8 Demolition;
10.1.3.2.9 Installation; ;
10.1.3.2.10 Rough-in; ;
10.1.3.2.11 Finishes;
10.1.3.2.12 Testing;
10.1.3.2.13 Owner and Maintenance Manuals; 10.1.3.2.12 Testing;and
10.1.3.2.14 Punchlist and District acceptance.
Appears in 1 contract
Samples: Facilities Lease
Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability.
10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site:
10.1.3.2.1 Overhead and profit;
10.1.3.2.2 Supervision;
10.1.3.2.3 General conditions;
10.1.3.2.4 Xxxxxx & Mobilization (not more than 1%);
10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%);
10.1.3.2.6 Bonds and insurance (not more than 2%);
10.1.3.2.7 Close-out documentation (not less than 3%);
10.1.3.2.8 Demolition;
10.1.3.2.9 Installation; 10.1.3.2.10 Rough-in; 10.1.3.2.11 Finishes; 10.1.3.2.12 Testing;
Appears in 1 contract
Samples: Facilities Lease
Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability.
10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site:
10.1.3.2.1 Overhead and profit;
10.1.3.2.2 Supervision;
10.1.3.2.3 General conditions;
10.1.3.2.4 Xxxxxx Layout & Mobilization (not more than 1%);
10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%);
10.1.3.2.6 Bonds and insurance (not more than 2%);
10.1.3.2.7 Close-out documentation (not less than 3%);
10.1.3.2.8 Demolition;
10.1.3.2.9 Installation; ;
10.1.3.2.10 Rough-in; ;
10.1.3.2.11 Finishes;
10.1.3.2.12 Testing;
10.1.3.2.13 Owner and Maintenance Manuals (not less than 2%); 10.1.3.2.12 Testing;and
10.1.3.2.14 Punchlist and District acceptance (not less than 3%).
Appears in 1 contract
Samples: Facilities Lease
Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability.
10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site:
10.1.3.2.1 Overhead and profit;
10.1.3.2.2 Supervision;
10.1.3.2.3 General conditions;
10.1.3.2.4 Xxxxxx & Mobilization (not more than 1%);
10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%);
10.1.3.2.6 Bonds and insurance (not more than 2%);
10.1.3.2.7 Close-out documentation (not less than 3%);
10.1.3.2.8 Demolition;
10.1.3.2.9 Installation; ;
10.1.3.2.10 Rough-in; ;
10.1.3.2.11 Finishes;
10.1.3.2.12 Testing;
10.1.3.2.13 Owner and Maintenance Manuals (not less than 2%); 10.1.3.2.12 Testing;and
10.1.3.2.14 Punchlist and District acceptance (not less than 3%).
Appears in 1 contract
Samples: Facilities Lease
Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability.
10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site:
10.1.3.2.1 Overhead and profit;
10.1.3.2.2 Supervision;
10.1.3.2.3 General conditions;
10.1.3.2.4 Xxxxxx Layout & Mobilization (not more than 1%);
10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%);
10.1.3.2.6 Bonds and insurance (not more than 2%);
10.1.3.2.7 Close-out documentation (not less than 3%);
10.1.3.2.8 Demolition;
10.1.3.2.9 Installation; ;
10.1.3.2.10 Rough-in; ;
10.1.3.2.11 Finishes;
10.1.3.2.12 Testing;
10.1.3.2.13 Owner and Maintenance Manuals; 10.1.3.2.12 Testing;and
10.1.3.2.14 Punchlist and District acceptance.
Appears in 1 contract
Samples: Facilities Lease
Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability.
10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site:
10.1.3.2.1 Overhead and profit;
10.1.3.2.2 Supervision;
10.1.3.2.3 General conditions;
10.1.3.2.4 Xxxxxx & Mobilization (not more than 1%);
10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%);
10.1.3.2.6 Bonds and insurance (not more than 23%);
10.1.3.2.7 Close-out documentation (not less than 3%);
10.1.3.2.8 Demolition;
10.1.3.2.9 Installation; 10.1.3.2.10 Rough-in; 10.1.3.2.11 Finishes; 10.1.3.2.12 Testing;
Appears in 1 contract
Samples: Facilities Lease
Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability.
10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site:
10.1.3.2.1 Overhead and profit;
10.1.3.2.2 Supervision;
10.1.3.2.3 General conditions;
10.1.3.2.4 Xxxxxx & Mobilization (not more than 1%);
10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%);
10.1.3.2.6 Bonds and insurance (not more than 22.5%);
10.1.3.2.7 Close-out documentation (not less than 3%);
10.1.3.2.8 Demolition;
10.1.3.2.9 Installation; ;
10.1.3.2.10 Rough-in; ;
10.1.3.2.11 Finishes;
10.1.3.2.12 Testing;
10.1.3.2.13 Owner and Maintenance Manuals; 10.1.3.2.12 Testing;and
10.1.3.2.14 Punchlist and District acceptance.
Appears in 1 contract
Samples: Facilities Lease
Budget of Project Costs. 10.1.3.1 At each stage of plan review indicated above, Developer will update and refine the budget of the Guaranteed Maximum Price based on the most recent set of design documents. Developer shall also advise the District and the Architect if it appears that the total construction costs may exceed the Guaranteed Maximum Price established by the District and shall make recommendations for corrective action. Developer will further provide input to the District and Architect relative to value of construction, means and methods for construction, duration of construction of various building methods and constructability.
10.1.3.2 In each budget of the Guaranteed Maximum Price, Developer shall include values of scopes of work subdivided into component parts in sufficient detail to serve as the basis for progress payments during construction. This budget of the Guaranteed Maximum Price shall include, at a minimum, the following information divided into at least the following categories for each site:
10.1.3.2.1 Overhead and profit;
10.1.3.2.2 Supervision;
10.1.3.2.3 General conditions;
10.1.3.2.4 Xxxxxx Layout & Mobilization (not more than 1%);
10.1.3.2.5 Submittals, samples, shop drawings (not more than 3%);
10.1.3.2.6 Bonds and insurance (not more than 2%);
10.1.3.2.7 Close-out documentation (not less than 3%);
10.1.3.2.8 Demolition;
10.1.3.2.9 Installation; 10.1.3.2.10 Rough-in; 10.1.3.2.11 Finishes; 10.1.3.2.12 Testing;
Appears in 1 contract
Samples: Facilities Lease