Change Directive. If the Consultant finds that the conditions at the Place of the Work are not materially different or that no change in the Contract Price or the Contract Time is justified, the Consultant will report the reasons for this finding to the Owner and the Construction Manager in writing.
Appears in 5 contracts
Samples: Construction Manager Agreement, Construction Manager Agreement, Construction Manager Agreement
Change Directive. If the Consultant finds that the conditions at the Place of the Work are not materially different or that no change in the Contract Construction Manager’s Fee for the Work, the Guaranteed Maximum Price or the Contract Time is justified, the Consultant will report the reasons for this finding to the Owner and the Construction Manager in writing.
Appears in 4 contracts
Samples: Construction Manager Agreement, Construction Manager Agreement, Agreement Between Owner and Construction Manager
Change Directive. If the Consultant finds that the conditions at the Place of the Work are not materially different or that no change in the Contract Price or the Contract Time is justified, the Consultant will report the reasons for this finding to the Owner and the Construction Manager Contractor in writing.
Appears in 2 contracts
Samples: Unit Price Contract, Unit Price Contract
Change Directive. If the Consultant finds that the conditions at the Place of the Work are not materially different or that no change in the Contract Construction Managers Fee for the Work, the Guaranteed Maximum Price or the Contract Time is justified, the Consultant will report the reasons for this finding to the Owner and the Construction Manager in writing.
Appears in 1 contract
Samples: Construction Manager Agreement