Change Directives. The following procedures shall apply with respect to Change Directives: 6.2.1 Upon receipt of a Change Directive signed by the Owner, the Design/Builder shall promptly proceed with the change in the Work involved and advise the Owner of the Design/Builder's agreement or disagreement with the method, if any, provided in the Change Directive for determining the proposed adjustment in the GMP or the Schedule. If the Design/Builder receives a written communication signed by the Owner which the Design/Builder believes is a Change Directive but is not so identified, it shall not proceed with the change in the Work until it receives from the Owner a written confirmation that such communication is in fact a Change Directive. 6.2.2 A Change Directive signed by the Design/Builder indicates the agreement of the Design/Builder with the contents thereof, and shall convert the Change Directive to a Change Order. 6.2.3 If the Design/Builder does not respond promptly or disagrees with the method for adjustment in the GMP or Schedule, the method and adjustment shall be determined as provided in Sections 6.5 or 6.10 below, as applicable. In such case, the Design/Builder shall keep and present, in such form as the Owner may request, an itemized accounting, together with appropriate supporting data. 6.2.4 Pending final determination of cost to the Owner, amounts not in dispute shall be included in Applications for Payment. The amount of credit to be allowed by the Design/Builder to the Owner for a deletion or change which results in a net decrease in the GMP 6.2.5 If the Owner and the Design/Builder do not agree with the adjustment in Schedule or the GMP, such disagreement shall be determined as provided in Section 11.1.
Appears in 5 contracts
Samples: Design/Build Agreement, Design/Build Agreement, Design/Build Agreement
Change Directives. The following procedures shall apply with respect to Change Directives:
6.2.1 Upon receipt of a Change Directive signed by the Owner, the Design/Builder shall promptly proceed with the change in the Work involved and advise the Owner of the Design/Builder's agreement or disagreement with the method, if any, provided in the Change Directive for determining the proposed adjustment in the GMP or the Schedule. If the Design/Builder receives a written communication signed by the Owner which the Design/Builder believes is a Change Directive but is not so identified, it shall not proceed with the change in the Work until it receives from the Owner a written confirmation that such communication is in fact a Change Directive.
6.2.2 A Change Directive signed by the Design/Builder indicates the agreement of the Design/Builder with the contents thereof, and shall convert the Change Directive to a Change Order.
6.2.3 If the Design/Builder does not respond promptly or disagrees with the method for adjustment in the GMP or Schedule, the method and adjustment shall be determined as provided in Sections 6.5 or 6.10 below, as applicable. In such case, the Design/Builder shall keep and present, in such form as the Owner may request, an itemized accounting, together with appropriate supporting data.
6.2.4 Pending final determination of cost to the Owner, amounts not in dispute shall be included in Applications for Payment. The amount of credit to be allowed by the Design/Builder to the Owner for a deletion or change which results in a net decrease in the GMPGMP shall be actual net cost. When both additions and credits covering related Work or substitutions are involved in a change, the allowance for Fee shall be figured on the basis of net increase, if any, with respect to that change.
6.2.5 If the Owner and the Design/Builder do not agree with the adjustment in Schedule or the GMP, such disagreement shall be determined as provided in Section 11.1.in
Appears in 3 contracts
Samples: Design/Build Agreement, Design/Build Agreement, Design/Build Agreement
Change Directives. The following procedures shall apply with respect to Change Directives:
6.2.1 Upon receipt of a Change Directive signed by the Owner, the Design/Builder shall promptly proceed with the change in the Work involved and advise the Owner of the Design/Builder's agreement or disagreement with the method, if any, provided in the Change Directive for determining the proposed adjustment in the GMP or the Schedule. If the Design/Builder receives a written communication signed by the Owner which the Design/Builder believes is a Change Directive but is not so identified, it shall not proceed with the change in the Work until it receives from the Owner a written confirmation that such communication is in fact a Change Directive.
6.2.2 A Change Directive signed by the Design/Builder indicates the agreement of the Design/Builder with the contents thereof, and shall convert the Change Directive to a Change Order.
6.2.3 If the Design/Builder does not respond promptly or disagrees with the method for adjustment in the GMP or Schedule, the method and adjustment shall be determined as provided in Sections 6.5 or 6.10 below, as applicable. In such case, the Design/Builder shall keep and present, in such form as the Owner may request, an itemized accounting, together with appropriate supporting data.
6.2.4 Pending final determination of cost to the Owner, amounts not in dispute shall be included in Applications for Payment. The amount of credit to be allowed by the Design/Builder to the Owner for a deletion or change which results in a net decrease in the GMPGMP shall be actual net cost. When both additions and credits covering related Work or substitutions are involved in a change, the allowance for Fee shall be figured on the basis of net increase, if
6.2.5 If the Owner and the Design/Builder do not agree with the adjustment in Schedule or the GMP, such disagreement shall be determined as provided in Section 11.1.
Appears in 1 contract
Samples: Design/Build Agreement
Change Directives. The following procedures shall apply with respect to Change Directives:
6.2.1 Upon receipt of a Change Directive signed by the Owner, the Design/-Builder shall promptly proceed with the change in the Work involved and advise the Owner of the Design/-Builder's agreement or disagreement with the method, if any, provided in the Change Directive for determining the proposed adjustment in the GMP Contract Price or the Schedule. If the Design/-Builder receives a written communication signed by the Owner which the Design/-Builder believes is a Change Directive but is not so identified, it shall not proceed with the change in the Work until it receives from the Owner a written confirmation that such communication is in fact a Change Directive.
6.2.2 A Change Directive signed by the Design/-Builder indicates the agreement of the Design/-Builder with the contents thereof, and shall convert the Change Directive to a Change Order.
6.2.3 If the Design/-Builder does not respond promptly or disagrees with the method for adjustment in the GMP Contract Price or Schedule, the method and adjustment shall be determined as provided in Sections 6.5 or 6.10 below, as applicable. In such case, the Design/-Builder shall keep and present, in such form as the Owner may request, an itemized accounting, together with appropriate supporting data.
6.2.4 Pending final determination of cost to the Owner, amounts Amounts not in dispute shall be included in Applications for Payment. The amount of credit to be allowed by the Design/-Builder to the Owner for a deletion or change which results in a net decrease in the GMPContract Price shall also be included in Applications for Payment.
6.2.5 If the Owner and the Design/-Builder do not agree with the adjustment in the Schedule or the GMPContract Price, such disagreement shall be determined as provided submitted for dispute resolution in Section 11.1accordance with the provisions of this Agreement.
Appears in 1 contract
Samples: Design Build Agreement