Change Directives. 7.13.1 A Change Directive may, if necessary: 7.13.1.1 State a proposed basis for adjustment, if any, in the Contract Sum or Contract Times, or both; or 7.13.1.2 Limit the scope of the change in the Work by a fixed adjustment of the Contract Sum. 7.13.2 If a change in the Contractor’s Work must start immediately to avoid an imminent impact to the schedule of the Project, the A/E shall prepare a Change Directive, for the Contracting Authority and Owner’s signatures pursuant to Section 7.13.1, authorizing the Contractor to proceed. 7.13.3 A Change Directive shall be used to direct a change in a Contractor’s Work in the absence of total agreement on the terms of a Change Order. 7.13.3.1 A Change Directive may also be used in the absence of agreement as to whether the subject of the Change Directive actually constitutes a change in the Work. 7.13.4 If the Project is administered using the State’s web-based project management software, the A/E shall prepare and recommend Change Directives for approval, using the “Change Order” or “Contract Modifications” business process with the “Change Directive” workflow.
Appears in 6 contracts
Samples: Professional Services, Professional Services, Architect/Engineer Agreement
Change Directives. 7.13.1 A Change Directive may, if necessary:
7.13.1.1 State a proposed basis for adjustment, if any, in the Contract Sum or Contract Times, or both; or
7.13.1.2 Limit the scope of the change in the Work by a fixed adjustment of the Contract Sum.
7.13.2 If a change in the Contractor’s Work must start immediately to avoid an imminent impact to the schedule of the Project, the A/E shall prepare a Change Directive, for the Contracting Authority and Owner’s signatures pursuant to Section 7.13.1, authorizing the Contractor to proceed.
7.13.3 A Change Directive shall be used to direct a change in a Contractor’s Work in the absence of total agreement on the terms of a Change Order.
7.13.3.1 A Change Directive may also be used in the absence of agreement as to whether the subject of the Change Directive actually constitutes a change in the Work.
7.13.4 If the Project is administered using the State’s web-based project management software, the A/E shall prepare and recommend Change Directives for approval, using the “Change Order” or “Contract Modifications” business process with the “Change Directive” workflow.process
Appears in 1 contract
Samples: Professional Services
Change Directives. 7.13.1 8.13.1 A Change Directive may, if necessary:
7.13.1.1 8.13.1.1 State a proposed basis for adjustment, if any, in the Contract Sum or Contract Times, or both; or
7.13.1.2 8.13.1.2 Limit the scope of the change in the Work by a fixed adjustment of the Contract Sum.
7.13.2 8.13.2 If a change in the Contractor’s Work must start immediately to avoid an imminent impact to the schedule of the Project, the A/E shall prepare a Change Directive, for the Contracting Authority and Owner’s signatures pursuant to Section 7.13.18.13.1, authorizing the Contractor to proceed.
7.13.3 8.13.3 A Change Directive shall be used to direct a change in a Contractor’s Work in the absence of total agreement on the terms of a Change Order.
7.13.3.1 8.13.3.1 A Change Directive may also be used in the absence of agreement as to whether the subject of the Change Directive actually constitutes a change in the Work.
7.13.4 8.13.4 If the Project is administered using the State’s web-based project management software, the A/E shall prepare and recommend Change Directives for approval, using the “Change Order” (Agency/Higher Education) or “Contract Modifications” (School Facilities) business process with the “Change Directive” workflow.
Appears in 1 contract
Samples: Professional Services