Change Order Requests. Any party to the construction process may request changes to the Work, compensation or applicable schedules after execution of this Contract, and without invalidating this Contract. Unless otherwise specified herein, the Professional shall prepare the change orders and construction change directives. All Change Order requests shall be in writing and approved prior to the work which is the subject of the Change Order being completed, unless otherwise stated herein. 9.1.1 With respect to such requests for changes by the General Contractor, the General Contractor shall prepare and submit written change order requests to the designated Professional and Owner. 9.1.2 With respect to requests for changes by parties other than the General Contractor, the General Contractor shall promptly review and respond in writing to change order requests submitted by a Professional. 9.1.3 When requested to do so, the General Contractor shall prepare and submit to a Professional drawings, specifications or other data in support of a change order request. 9.1.4 Each change order shall include time and monetary impacts of the change, whether the change order is considered alone or with all other changes during the course of the Project.
Appears in 3 contracts
Samples: Contract for Construction, Contract for Construction, Contract for Construction
Change Order Requests. Any party to the construction process may request changes to the Work, compensation or applicable schedules after execution of this Contract, and without invalidating this Contract. Unless otherwise specified herein, the Professional shall prepare the change orders and construction change directives. All Change Order requests shall be in writing and approved prior to the work which is the subject of the Change Order being completed, unless otherwise stated herein.
9.1.1 With respect to such requests for changes by the General ContractorConstruction Manager, the General Contractor Construction Manager shall prepare and submit written change order requests to the designated Professional and OwnerProfessional.
9.1.2 With respect to requests for changes by parties other than the General ContractorConstruction Manager, the General Contractor Construction Manager shall promptly review and respond in writing to change order requests submitted by a Professional.
9.1.3 When requested to do so, the General Contractor Construction Manager shall prepare and submit to a the Professional drawings, specifications or other data in support of a change order request.
9.1.4 Each Unless the parties agree to reserve it, each change order shall include time and monetary impacts of the change, whether the change order is considered alone or with all other changes during the course of the Project.
Appears in 2 contracts
Samples: Construction Management Agreement, Construction Management Agreement
Change Order Requests. Any party to the construction process may request changes to the Work, compensation or applicable schedules after execution of this Contract, and without invalidating this Contract. Unless otherwise specified hereinin this Agreement, the Professional shall will prepare the change orders and construction change directives. All Change Order requests shall must be in writing and approved prior to the work which is the subject of the Change Order being completed, unless otherwise stated hereinin this Agreement.
9.1.1 With respect to such requests for changes by the General ContractorConstruction Manager, the General Contractor Construction Manager shall prepare and submit written change order requests to the designated Professional and OwnerProfessional.
9.1.2 With respect to requests for changes by parties other than the General ContractorConstruction Manager, the General Contractor Construction Manager shall promptly review and respond in writing to change order requests submitted by a the Professional.
9.1.3 When requested to do so, the General Contractor Construction Manager shall prepare and submit to a the Professional drawings, specifications or other data in support of a change order request.
9.1.4 Each Unless the parties agree to reserve it, each change order shall must include time and monetary impacts of the change, whether the change order is considered alone or with all other changes during the course of the Project.
Appears in 2 contracts
Samples: Construction Management Agreement, Construction Management Agreement