Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following: a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity; b) the method of shipment or packing; c) the place of delivery; and d) the Related Services to be provided by the Supplier. 33.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order. 33.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 83 contracts
Samples: Framework Agreement, Framework Agreement for Provision of Hotel, Accommodation and Conference Facilities, Framework Agreement
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 . If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 . Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 7 contracts
Samples: Tender Agreement, Tender Agreement, Tender Agreement
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specificationsspecifications, where Goods to be furnished under the Contract are to be specifically specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 7 contracts
Samples: Framework Agreement, Framework Contract, Framework Agreement for Supply of Personal Protective Equipment (Ppes)
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-twenty- eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 6 contracts
Samples: Framework Agreement, Framework Agreement, Framework Agreement
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the The Related Services to be provided by the Supplier.
33.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 5 contracts
Samples: Framework Agreement, Framework Agreement, Framework Agreement
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) : drawings, designs, or specificationsspecifications, where Goods to be furnished under the Contract are to be specifically specifically manufactured for the Procuring Entity;
b) ; the method of shipment or packing;
c) ; the place of delivery; and
d) and the Related Services to be provided by the Supplier.
33.2 . If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 . Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 3 contracts
Samples: Framework Contract, Framework Agreement for Supply of Air Conditioners and Refrigeration Spares, Framework Agreement for Supply of Foodstuff
Change Orders and Contract Amendments. 33.1 33.1. The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 33.2. If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 33.3. Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 3 contracts
Samples: Framework Agreement, Framework Agreement, Tender Agreement
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 . If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of receiptof the Procuring Entity's change order.
33.3 . Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 2 contracts
Samples: Framework Agreement, Framework Agreement
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 . If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight twentyeight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 . Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 2 contracts
Samples: Framework Agreement, Framework Agreement
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 . If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-twenty- eight (28) days from the date of the Supplier's receipt of the Procuring EntityProcuringEntity's change order.
33.3 . Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 2 contracts
Samples: Framework Contract, Framework Contract
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in madein the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-twenty- eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 2 contracts
Change Orders and Contract Amendments. 33.1 The Procuring Entity Purchaser may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
: (a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
Purchaser; (b) the method of shipment or packing;
; (c) the place of delivery; and
and (d) the Related Services to be provided by the Supplier.
33.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's ’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's ’s receipt of the Procuring Entity's Purchaser’s change order.
. 33.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 2 contracts
Samples: Contract Agreement, Contract Agreement
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 87, to make changes within the general scope of the Contract in any one or more of the following:
a) : drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) ; the method of shipment or packing;
c) ; the place of delivery; and
d) and the Related Services to be provided by the Supplier.
33.2 . If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's ’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's ’s receipt of the Procuring Entity's ’s change order.
33.3 . Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services. Subject to the above, no variation in or modification of the terms of the Contract shall be made except by written amendment signed by the parties.
Appears in 2 contracts
Samples: Tender Agreement, Bidding Document
Change Orders and Contract Amendments. 33.1 32.1 The Procuring Entity Purchaser may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one anyone or more of the following:
(a) drawingsDrawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring EntityPurchaser;
(b) the method of shipment or packing;
(c) the place of delivery; and
(d) the Related Services to be provided by the Supplier.
33.2 32.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's ’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Delivery / Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-twenty eight (28) days from the date of the Supplier's ’s receipt of the Procuring Entity's Purchaser’s change order.
33.3 Prices 32.3 Price to be charged changed by the Supplier for any Related Services that might be needed need but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
32.4 Subject to the above, no variation in or modification of the terms of the Contract shall be made except by written amendments signed by the parties.
Appears in 2 contracts
Samples: Service & Maintenance Agreement, Service & Maintenance Agreement and Licensing
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 . If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-twenty- eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 . Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 1 contract
Samples: Tender Agreement
Change Orders and Contract Amendments. 33.1 3.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 3.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 3.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 1 contract
Samples: Framework Agreement
Change Orders and Contract Amendments. 33.1 The Procuring Entity (34.1) Except by mutual agreement in writing between the parties, no change, modification or amendment shall be made to the Contract.
(34.2) Notwithstanding clause (34.1), the Client may at any time order request the Supplier through notice in accordance GCC Clause 8a written notice, to make changes within the general scope of the Contract in any one or more of the following:
a) : drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) Client; the method of shipment or packing;
c) ; the place of delivery; and
d) and tailoring of the Related Services to be provided by the SupplierSupplier to the Client.
33.2 (34.3) If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's ’s performance of any provisions under the Contract, an equitable adjustment shall be made in agreed between the parties to the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall be accordingly be amended. Any claims by the Supplier for adjustment under this Clause clause must be asserted within twenty-eight twenty (2820) days Working Days from the date of the Supplier's ’s receipt of the Procuring Entity's Client’s change order.
33.3 (34.4) Prices to be charged by the Supplier adjustments for any Related Services that might be needed but which were not included in the Contract change orders pursuant to clause (34.2) shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services, nor in total, exceed twenty percent (20%) of the Contract Price.
Appears in 1 contract
Samples: Contract for the Supply and Installation of Goods and Provision of Maintenance and Training Services
Change Orders and Contract Amendments. 33.1 33.1. The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of moreof the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are Contractare to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 33.2. If any such change causes an increase or decrease in the cost of, or the time required for, ,the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this underthis Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt Supplier'sreceipt of the Procuring Entity's change order.
33.3 33.3. Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 1 contract
Samples: Framework Agreement
Change Orders and Contract Amendments. 33.1 32.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) : drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) ; the method of shipment or packing;
c) ; the place of delivery; and
d) and the Related Services to be provided by the Supplier.
33.2 . 32.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's ’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's ’s receipt of the Procuring Entity's ’s change order.
33.3 . 32.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 1 contract
Samples: Supply and Delivery Contract
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in madein the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 1 contract
Samples: Framework Agreement
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) 33.1 drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) 33.2 the method of shipment or packing;
ca) the place of delivery; and
d) and the Related Services to be provided by the Supplier.
33.2 . If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 . Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 1 contract
Samples: Framework Agreement for Supply and Delivery of Indefinite Quantity of Automotive Gas Oil (Ago)
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be tobe specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 1 contract
Samples: Framework Agreement for Provision of Sanitary Services
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8Clause8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be tobe specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in madein the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 1 contract
Samples: Framework Agreement
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) : drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) Purchaser; the method of shipment or packing;
c) ; the place of delivery; and
d) and the Related Services to be provided by the Supplier.
33.2 . If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's ’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight thirty (2830) days from the date of the Supplier's ’s receipt of the Procuring Entity's ’s change order.
33.3 . Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services. Subject to the above, no variation in or modification of the terms of the Contract shall be made except by written amendment signed by the parties and in the limits provided for by the law on public procurement as modified and completed to date.
Appears in 1 contract
Change Orders and Contract Amendments. 33.1 34.1. The Procuring Entity agency may at any time order the Supplier through notice in accordance with GCC Clause 8, 8 to make changes within the general scope of the Contract in any one or more of the following:
a) a. drawings, designs, designs or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entityagency;
b) b. the method of shipment or packing;
c) c. the place of delivery; and
d) d. the Related Services to be provided by the Supplier.
33.2 34.2. If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's ’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight thirty (2830) days from the date of the Supplier's ’s receipt of the Procuring Entity's agency’s change order.
33.3 34.3. Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
34.4. Subject to the above, no variation in or modification of the terms of the Contract shall be made except by written amendment by the parties.
Appears in 1 contract
Samples: Tender Agreement
Change Orders and Contract Amendments. 33.1 30.1 The Procuring Entity may at any time order the Supplier Lessor through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) : a drawings, designs, or specifications, where Goods Lease Items to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) ; b the method of shipment or packing;
c) ; c the place of delivery; and
d) and d the Related Services to be provided by the SupplierLessor.
33.2 30.2 If any such change causes an increase or decrease in the cost of, or the time required for, the SupplierLessor's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier Lessor for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the SupplierLessor's receipt of the Procuring Entity's change order.
33.3 30.3 Prices to be charged by the Supplier Lessor for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier Lessor for similar services.
Appears in 1 contract
Samples: Framework Contract for Lease of Trucks for Garbage Collection
Change Orders and Contract Amendments. 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following:
a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity;
b) the method of shipment or packing;
c) the place of delivery; and
d) the Related Services to be provided by the Supplier.
33.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the andthe Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order.
33.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
Appears in 1 contract
Samples: Framework Agreement for Supply and Delivery of Working Tools