CHANGES IN THE PROJECT – DELAYS – SUSPENSION OF WORK. 10.1 Change Orders - The Owner, without invalidating this Agreement, may order Changes in the Project within the general scope of this Agreement consisting of additions, deletions or other revisions, with the GMP and the Construction Completion Date being adjusted accordingly. All changes in the Project not covered by an authorized contingency shall be authorized by Change Order signed by the Owner before the change is implemented.
Appears in 7 contracts
CHANGES IN THE PROJECT – DELAYS – SUSPENSION OF WORK. 10.1 Change Orders - The Owner, without invalidating this Agreement, may order Changes changes in the Project within the general scope of this Agreement consisting of additions, deletions deletions, or other revisions, with the GMP and the Construction Completion Date construction completion date being adjusted accordingly. All changes in the Project not covered by an authorized contingency shall be authorized by Change Order signed by the Owner before the change is implemented.