City Requested Change in Work. 6.3.1. The City reserves the right to make, at any time during the progress of the Work, such alterations as may be found necessary or in the City’s best interest. 6.3.2. Such alterations and changes in the Work shall not invalidate this Agreement nor release the surety and the CM@Risk agrees to perform the Work as altered, the same as if it had been a part of the original Contract Documents subject to an adjustment to the Contract Price and/or Contract Times in accordance with this Article 6. 6.3.3. The City shall request a Change Proposal from CM@Risk, and an equitable adjustment in the Contract Price and/or Contract Times shall be made in writing and shall be based upon a mutually agreed cost and time. 6.3.4. Design Professional may require minor changes in the Work that do not change the Contract Price or Contract Times using a Field Order through RPR. RPR may issue a Field Order for non-technical, administrative issues. CM@Risk shall submit a Change Proposal if it believes that a Field Order justifies an adjustment in the Contract Price or Contract Times before proceeding with the Work described in the Field Order. 6.3.5. If the City and Contractor agree that the change increases or decreases the Contract Price or the time to achieve Substantial Completion, the City will issue a Change Order within thirty
Appears in 3 contracts
Samples: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement, Construction Manager at Risk Agreement
City Requested Change in Work. 6.3.1. The City reserves the right to make, at any time during the progress of the Work, such alterations as may be found necessary or in the City’s best interest.
6.3.2. Such alterations and changes in the Work shall not invalidate this Agreement nor release the surety and the CM@Risk agrees to perform the Work as altered, the same as if it had been a part of the original Contract Documents subject to an adjustment to the Contract Price and/or Contract Times in accordance with this Article 6.
6.3.3. The City shall request a Change Proposal from CM@Risk, and an equitable adjustment in the Contract Price and/or Contract Times shall be made in writing and shall be based upon a mutually agreed cost and time.
6.3.4. Design Professional may require minor changes in the Work that do not change the Contract Price or Contract Times using a Field Order through RPR. RPR may issue a Field Order for non-technical, administrative issues. CM@Risk shall submit a Change Proposal if it believes that a Field Order justifies an adjustment in the Contract Price or Contract Times before proceeding with the Work described in the Field Order.
6.3.5. If the City and Contractor agree that the change increases or decreases the Contract Price or the time to achieve Substantial Completion, the City will issue a Change Order within thirty