Changes to the Contract Price and Time Sample Clauses

Changes to the Contract Price and Time. 9.1 Change Order 9.2 Change Directives 9.3 Minor Changes In The Work 9.4 Price Adjustment 9.5 Emergencies
AutoNDA by SimpleDocs
Changes to the Contract Price and Time. Delays to the Work
Changes to the Contract Price and Time. A. Delays to the Work: If CM@Risk is delayed in the performance of the Work that will cause a change in the date of Substantial Completion due to acts, omissions, conditions, events, or circumstances beyond its control and due to no fault of its own or those for whom CM@Risk is responsible, the Contract Times and/or Contract Price for performance shall be reasonably revised by Change Order. B. The CM@Risk shall request an increase in the Contract Time by written notice including an estimate of probable effect of delay on progress of the Work. In the case of a continuing delay only one request is necessary. Such notice shall not be later than fourteen (14) Days after such condition or event has been encountered. C. By way of example, events that will entitle CM@Risk to an extension of the Contract Time include acts or omissions of City or anyone under City’s control (including separate contractors), changes in the Work, Differing Site Conditions, Hazardous Conditions, delays by regulating agencies, wars, floods, labor disputes, unusual delay in transportation, epidemics abroad, earthquakes, adverse weather conditions not reasonably anticipated, and other acts of God. D. If adverse weather conditions are the basis for a request for additional Contract Time, such requests shall be documented by data substantiating that weather conditions were abnormal for the period of time and that weather conditions had an adverse effect on the scheduled Substantial Completion. (i) It is understood, however, that permitting the CM@Risk to proceed to complete any Work, or any part of the Work, after the date to which the time of completion may have been extended, shall in no way act as a waiver on the part of the City of any of its legal rights herein. (ii) In addition to CM@Risk’s right to a time extension for those events set forth in this Section, CM@Risk shall also be entitled to an appropriate adjustment of the Contract Price provided, however, that the Contract Price shall not be adjusted for those events set forth in this Section that are beyond the control of both CM@Risk and City, including the events of war, floods, labor disputes, earthquakes, epidemics, adverse weather conditions not reasonably anticipated, and other acts of God.
Changes to the Contract Price and Time. 6.1. Delays to the Work 6.1.1. CM@Risk understands and agrees that if CM@Risk is delayed in the performance of the Work that will cause a change in the date of Substantial Completion due to acts, omissions, conditions, events, or circumstances beyond its control and due to no fault of its own or those for whom CM@Risk is responsible, the Contract Times for performance shall be reasonably extended by Change Order. 6.1.2. The CM@Risk shall request an increase in the Contract Time by written change proposal including an estimate of probable effect of delay on progress of the Work. In the case of a continuing delay only one request is necessary. Such notice shall not be later than fourteen
Changes to the Contract Price and Time. Except as provided herein, Change Orders will be in compliance with Article 9 of the DBIA 535.
Changes to the Contract Price and Time 

Related to Changes to the Contract Price and Time

  • THE CONTRACT PRICE A. This Contract is an indefinite-quantity contract for construction work and services. The Estimated Annual Value of this Contract is $2,000,000. This is only an estimate and may increase or decrease at the discretion of Sourcewell. B. The Contractor shall perform any or all Tasks in the Construction Task Catalog for the Unit Price appearing therein multiplied by the following Adjustment Factors:

  • CHANGES TO THE CONTRACT All contract modifications must be approved by the Dinwiddie County Administrator or his designee. The County will not assume responsibility for the cost of any changes made without proper consent. No fixed-price contract may be increased by more than twenty-five percent (25%) or $50,000, whichever is greater, without advance approval of the Dinwiddie County Board of Supervisors. Changes can be made to the contract in any of the following ways: A. The parties may agree in writing to modify the terms, conditions, or scope of the contract. Any additional goods or services to be provided shall be of a sort that is ancillary to the contract goods or services, or within the same broad product or service categories as were included in the contract award. Any increase or decrease in the price of the contract resulting from such modification shall be agreed to by the parties as a part of their written agreement to modify the scope of the contract. B. The County may order changes within the general scope of the contract at any time by written notice to the Contractor. Changes within the scope of the contract include, but are not limited to, things such as services to be performed, the method of packing or shipment, and the place of delivery or installation. The Contractor shall comply with the notice upon receipt, unless the Contractor intends to claim an adjustment to compensation, schedule, or other contractual impact that would be caused by complying with such notice, in which case the Contractor shall, in writing, promptly notify the County of the adjustment to be sought, and before proceeding to comply with the notice, shall await the County’s written decision affirming, modifying, or revoking the prior written notice. If the County decides to issue a notice that requires an adjustment to compensation, the Contractor shall be compensated for any additional costs incurred as the result of such order and shall give the County a credit for any savings. Said compensation shall be determined by one of the following methods: 1. By mutual agreement between the parties in writing; or 2. By agreeing upon a unit price or using a unit price set forth in the contract, if the work to be done can be expressed in units, and the Contractor accounts for the number of units of work performed, subject to the County’s right to audit the Contractor’s records and/or to determine the correct number of units independently; or 3. By ordering the Contractor to proceed with the work and keep a record of all costs incurred and savings realized. A markup for overhead and profit may be allowed if provided by the contract. The same markup shall be used for determining a decrease in price as the result of savings realized. The Contractor shall present the County with all vouchers and records of expenses incurred and savings realized. The County shall have the right to audit the records of the Contractor as it deems necessary to determine costs or savings. Any claim for an adjustment in price under this provision must be asserted by written notice to the County within thirty (30) days from the date of receipt of the written order from the County. Neither the existence of a claim nor a dispute resolution process, litigation or any other provision of this contract shall excuse the Contractor from promptly complying with the changes ordered by the County or with the performance of the contract generally.

  • C1 Contract Price In consideration of the Contractor’s performance of its obligations under the Contract, the Authority shall pay the Contract Price in accordance with clause C2 (Payment and VAT).

  • Contract Price 3.1 For full and complete performance, OWNER agrees to pay CONTRACTOR the sum of $659,258.00 payable in accordance with the terms hereof and to the satisfaction of the OWNER.

  • Contract Price and Payment In consideration of the Contractor's due and proper performance of its obligations under the Contract, the Contractor may charge the Authority or, as the case may be, any Beneficiary the Contract Price in accordance with this Clause 6. The only sums payable by the Authority or any Beneficiary to the Contractor for the provision of the Services shall be the Contract Price. All other costs, charges, fees and expenses of whatever kind arising out of or in connection with the Contract shall be the responsibility of the Contractor. In accordance with the Contract, where the Contractor is required to provide Deliverables, the Authority or any Beneficiary shall be entitled to withhold payment of the Contract Price pending receipt and acceptance of the Deliverables in accordance with the Specification. Unless otherwise agreed in writing by the Authority or any Beneficiary and the Contractor, within 15 days of the end of each calendar month, the Contractor shall invoice the Authority or, as the case may be, any Beneficiary for any Services provided by the Contractor in that calendar month. Such invoice shall be rendered on the Contractor's own invoice form clearly marked with the Authority’s or the Beneficiary's order number (if any). Invoices must show the period to which they relate and the aspects of the Services for which payment is claimed together with the agreed charging rates and any other details the Authority or the Beneficiary may require. Failure to provide such information will entitle the Authority or the Beneficiary to delay payment of the Contract Price until such information is provided. Subject to Clauses 6.3 and 6.6, the Authority or any Beneficiary shall pay any invoice submitted by the Contractor in accordance with Clause 6.4 within 30 days of receipt by the Authority or the Beneficiary of such invoice. The Authority or the Beneficiary shall pay such invoice(s) by BACS (Bank Automated Clearing System) if it so chooses or any alternate means as agreed between the Authority or the Beneficiary and the Contractor. The Authority and any Beneficiary shall be entitled to deduct from any monies due or to become due to the Contractor any monies owing to the Authority or the Beneficiary from the Contractor. Where the performance of the Contractor does not meet the required standard then a deduction as set out in the Specification or as agreed by the Parties may be made. Except where otherwise stated in the Order, the Contract Price is exclusive of VAT which shall be payable, if applicable, by the Authority or any Beneficiary in addition to such Contract Price. The invoice provided to the Authority or any Beneficiary by the Contractor in accordance with Clause 6.4 shall show the VAT calculations separately. The Contractor will keep accurate books and records in relation to the provision of the Services in accordance with sound and prudent financial management. All such books and records shall be made available to the Authority at regular intervals of not less than quarterly. In the event of the Authority or any Beneficiary breaching Clause 6.5, the Contractor shall be entitled to charge interest on the outstanding amount owed by the Authority or such Beneficiary in accordance with the Late Payment of Commercial Debts (Interest) Act 1998. Subject to Clauses 6.12 and 6.13, the Contract Price shall not be subject to any increase whatsoever by the Contractor during the Contract Period. In the event that the Contract is varied under Clauses 22 or 23 in such a way as to affect the Contract Price and if agreement between the Parties cannot be reached on the adjustment to the Contract Price within 3 months both Parties shall jointly act to resolve the dispute in accordance with Clause 24. If the adjusted Contract Price is not so agreed or certified until after such variation has taken effect, the Authority or any Beneficiary shall continue to pay the Contractor at the rate current prior to the variation but shall pay to the Contractor or be entitled to recover from the Contractor as the case may be such sum if any as is equal to the difference between the amount which should have been paid in accordance with the adjusted Contract Price and the amount which was actually paid. In the event that the Contract ends or is terminated otherwise than at the end of a complete year, the sum payable by the Authority or any Beneficiary under Clause 6 shall be one twelfth of the annual sum which would otherwise have been payable for the complete year for each completed month.

  • Price Schedule, Payment Terms and Billing, and Price Adjustments (a) Price Schedule: Price Schedule under this Contract is set forth in Exhibit B.

  • Payment and Contract Price C1 Contract Price C1.1 In consideration of the Contractor’s performance of its obligations under the Contract, the Authority shall pay the Contract Price in accordance with clause C2 (Payment and VAT). C1.2 The Authority shall, in addition to the Contract Price and following evidence of a valid VAT invoice, pay the Contractor a sum equal to the VAT chargeable on the value of the Services supplied in accordance with the Contract. C2 Payment and VAT C2.1 The Authority shall pay all sums due to the Contractor within thirty (30) days of receipt of a valid invoice, submitted Monthly in arrears. C2.2 The Authority shall pay all sums by direct credit transfer into a suitable bank account or by other electronic payment methods as appropriate. C2.3 The Contractor shall ensure that each invoice contains a valid purchase order number. All appropriate references and a detailed breakdown of the Services supplied and any other documentation reasonably required by the Authority to substantiate the invoice should be supplied in accordance with Schedule 2. C2.4 Where the Contractor enters into a sub-contract for the purpose of performing its obligations under the Contract, it shall ensure that a provision is included in such a sub-contract which requires payment to be made of all sums due by the Contractor to the Sub-contractor within a specified period not exceeding thirty (30) days from the receipt of a valid invoice. C2.5 The Contractor shall add VAT to the Contract Price at the prevailing rate as applicable and the Authority shall pay the VAT to the Contractor following its receipt of a valid VAT invoice. C2.6 The Contractor shall indemnify the Authority on a continuing basis against any liability, including any interest, penalties or costs incurred, which is levied, demanded or assessed on the Authority at any time in respect of the Contractor’s failure to account for or to pay any VAT relating to payments made to the Contractor under the Contract. Any amounts due under this clause C2.5 shall be paid by the Contractor to the Authority not less than five (5) Working Days before the date upon which the tax or other liability is payable by the Authority. C2.7 The Contractor shall not suspend the supply of the Services unless the Contractor is entitled to terminate the Contract under clause H2.3 (Termination on Default) for failure to pay undisputed sums of money. Interest shall be payable by the Authority on the late payment of any undisputed sums of money properly invoiced in accordance with the Late Payment of Commercial Debts (Interest) Xxx 0000. C2.8 Where payment by the Authority of all or any part of any invoice rendered or other claim for payment by the Contractor is disputed, this dispute shall be resolved in accordance with the disputed claims procedure as set out in Schedule 2. C3 Recovery of Sums Due C3.1 Wherever under the Contract any sum of money is recoverable from or payable by the Contractor (including any sum which the Contractor is liable to pay to the Authority in respect of any breach of the Contract), the Authority may unilaterally deduct that sum from any sum then due, or which at any later time may become due to the Contractor under the Contract or under any other agreement or contract with the Authority. C3.2 Any overpayment by either Party, whether of the Contract Price or of VAT or otherwise, shall be a sum of money recoverable by the Party who made the overpayment from the Party in receipt of the overpayment. C3.3 The Contractor shall make all payments due to the Authority without any deduction whether by way of set-off, counterclaim, discount, abatement or otherwise unless the Contractor has a valid court order requiring an amount equal to such deduction to be paid by the Authority to the Contractor. C3.4 All payments due shall be made within a reasonable time unless otherwise specified in the Contract, in cleared funds, to such bank or building society account as the recipient Party may from time to time direct. C4 Price adjustment on extension of the Initial Contract Period C4.1 The Contract Price shall apply for the Initial Contract Period. In the event that the Authority agrees to extend the Initial Contract Period pursuant to clause F8 (Extension of Initial Contract Period), the Authority may, where applicable, in the six (6) Month period prior to the expiry of the Initial Contract Period, enter into good faith negotiations with the Contractor (for a period of not more than thirty (30) Working Days) to agree a variation in the Contract Price. For the avoidance of doubt both Parties accept and acknowledge that any Variation to the Contract Price shall not have the effect of altering the economic balance of the Contract during the period of extension in favour of the Contractor in a manner not provided for in the terms of the Contract. C4.2 If the Parties are unable to agree a variation in the Contract Price in accordance with clause C4.1, the Contract shall terminate at the end of the Initial Contract Period. C4.3 If a variation in the Contract Price is agreed between the Authority and the Contractor, the revised Contract Price will take effect from the first day of any period of extension and shall apply during such period of extension. C4.4 Any increase in the Contract Price pursuant to clause C4.1 shall not exceed the percentage change in the Office of National Statistics’ Consumer Prices Index (CPI) (or another such index specified in the Prices & Rates Schedule) between the Commencement Date and the date six (6) Months before the end of the Initial Contract Period.] C5 Euro C5.1 Any requirement of Law to account for the Services in Euro (or to prepare for such accounting) instead of and/or in addition to sterling, shall be implemented by the Contractor at nil charge to the Authority. C5.2 The Authority shall provide all reasonable assistance to facilitate compliance with clause C5.1 by the Contractor. C6 Third Party Revenue C6.1 The Contractor may not obtain any third party revenue, income or credit based on the Services and/or copyright works delivered under this Contract without the express prior written agreement of the Authority.

  • Changes to Specifications All Specifications and any changes thereto agreed to by the parties from time to time shall be in writing, dated and signed by the parties. Any change to the Process shall be deemed a Specification change. No change in the Specifications shall be implemented by Catalent, whether requested by Client or requested or required by any Regulatory Authority, until the parties have agreed in writing to such change, the implementation date of such change, and any increase or decrease in costs, expenses or fees associated with such change (including any change to Unit Pricing). Catalent shall respond promptly to any request made by Client for a change in the Specifications, and both parties shall use commercially reasonable, good faith efforts to agree to the terms of such change in a timely manner. As soon as possible after a request is made for any change in Specifications, Catalent shall notify Client of the costs associated with such change and shall provide such supporting documentation as Client may reasonably require. Client shall pay all costs associated with such agreed upon changes. If there is a conflict between the terms of this Agreement and the terms of the Specifications, this Agreement shall control. Catalent reserves the right to postpone effecting changes to the Specifications until such time as the parties agree to and execute the required written amendment.

  • Price Schedule 35.1. All prices under this agreement are set forth in the attachments designated Table One and Table Two of this Agreement are hereby incorporated into, and made a part of, this Agreement. 35.2. Subject to the provisions of Part B, Section 4 of this Agreement, all rates provided under this Agreement shall remain in effect for the term of this Agreement.

  • Delivery Schedule The Goods specified in the List of Goods are required to be delivered within the acceptable time range (after the earliest and before the final date, both dates inclusive) specified in Section V, Schedule of Requirements. No credit will be given to deliveries before the earliest date, and Tenders offering delivery after the final date shall be treated as non-responsive. Within this acceptable period, an adjustment of [insert the adjustment factor], will be added, for evaluation purposes only, to the Tender price of Tenders offering deliveries later than the “Earliest Delivery Date” specified in Section V, Schedule of Requirements.