Claims Procedures. Pursuant to the remedies under Public Contract Code section 9201 and Government Code section 930.2, Contractor, through execution of this Agreement, also agrees to comply with the Claims requirements under Article 20 to quickly and efficiently resolve disputes. Further, to provide a level of accuracy to the records submitted, the District shall have the right to audit books and records pursuant to Article 21 based on the actual costs incurred and to reduce the uncertainty in resolving disputes with limited information.
Appears in 11 contracts
Samples: Construction Services Agreement, Construction Services Agreement, Project Construction Services Agreement
Claims Procedures. Pursuant to the remedies under Public Contract Code section Section 9201 and Government Code section Section 930.2, Contractor, through execution of this Agreement, also agrees to comply with the Claims requirements under of Article 20 4.6 to quickly and efficiently resolve disputesDisputes and Claims. Further, to provide a level of accuracy to the records submitted, the District Owner shall have the right to audit books and records pursuant to Article 21 13.11 based on the actual costs incurred and to reduce the uncertainty in resolving disputes Disputes and Claims with limited information.
Appears in 3 contracts
Samples: Agreement Form, Escrow Agreement, Escrow Agreement
Claims Procedures. Pursuant to the remedies under Public Contract Code section Section 9201 and Government Code section Section 930.2, Contractor, through execution of this Agreement, also agrees to comply with the Claims requirements under this Article 20 to quickly and efficiently resolve disputes. Further, to provide a level of accuracy to the records submitted, the District shall have the right to audit books and records pursuant to Article 21 based on the actual costs incurred and to reduce the uncertainty in resolving disputes with limited information.
Appears in 2 contracts
Samples: Construction Services Agreement, Construction Services Agreement
Claims Procedures. Pursuant to the remedies under Public Contract Code section Section 9201 and Government Code section Section 930.2, Contractor, through execution of this Agreement, also agrees to comply with the Claims requirements under Article 20 to quickly and efficiently resolve disputes. Further, to provide a level of accuracy to the records submitted, the District shall have the right to audit books and records pursuant to Article 21 based on the actual costs incurred and to reduce the uncertainty in resolving disputes with limited information.
Appears in 1 contract
Samples: Construction Services Agreement
Claims Procedures. Pursuant to the remedies under Public Contract Code section 9201 and Government Code section 930.2, Contractor, through execution of this Agreement, also agrees to comply with the Claims requirements under Article 20 to quickly and efficiently resolve disputes. Further, to provide a level of accuracy to the records submitted, the District shall have the right to audit books and records pursuant to Article 21 based on the actual costs incurred and to reduce the uncertainty in resolving disputes with limited information.information.
Appears in 1 contract
Samples: Construction Services Agreement
Claims Procedures. Pursuant to the remedies under Public Contract Code section Section 9201 and Government Code section Section 930.2, Contractor, through execution of this Agreement, also agrees to comply with the Claims requirements under of Article 20 4.6 to quickly and efficiently resolve disputes. Further, to provide a level of accuracy to the records submitted, the District Owner shall have the right to audit books and records pursuant to Article 21 13.11 based on the actual costs incurred and to reduce the uncertainty in resolving disputes with limited information.
Appears in 1 contract
Samples: Agreement