Commencement of the Works. Before the commencement of the WUC, the Contractor shall: provide the Principal with a copy of the Contractor’s construction programme referred to in clause 43; effect all insurances required under clauses 7 and 8 and lodge evidence of such with the Superintendent; give the Superintendent seven (7) days’ notice in writing of the proposed date of commencement of the Works; obtain approval from the Superintendent for the nominated Contractor’s Representative; and provide to the principal a geotechnical report specifying the Site’s engineering classification.
Appears in 2 contracts
Samples: Building Agreement, Building Agreement
Commencement of the Works. Before the commencement of the WUC, the Contractor shall: provide the Principal with a copy of the Contractor’s construction programme referred to in clause 43; effect all insurances required under clauses 7 7. and 8 8. and lodge evidence of such with the Superintendent; give the Superintendent seven (7) days’ notice in writing of the proposed date of commencement of the Works; obtain approval from the Superintendent for the nominated Contractor’s Representative; and provide to the principal a geotechnical report specifying the Site’s engineering classification.
Appears in 2 contracts
Samples: Building Agreement, Building Agreement
Commencement of the Works. Before the commencement of the WUC, the Contractor shall: :
11.1. provide the Principal with a copy of the Contractor’s construction programme referred to in clause 43; ;
11.2. effect all insurances required under clauses 7 and 8 and lodge evidence of such with the Superintendent; ;
11.3. give the Superintendent seven (7) days’ notice in writing of the proposed date of commencement of the Works; ;
11.4. obtain approval from the Superintendent for the nominated Contractor’s Representative; and and
11.5. provide to the principal a geotechnical report specifying the Site’s engineering classification.
Appears in 1 contract