Completion of Works. (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve: (i) Substantial Completion by the Scheduled Substantial Completion Date; and (ii) Final Completion by the Scheduled Final Completion Date.
Appears in 8 contracts
Samples: Project Agreement, Project Agreement, Project Agreement
Completion of Works. (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve:
(i) Phase One Substantial Completion by the Scheduled Phase One Substantial Completion Date;
(ii) Substantial Completion by the Scheduled Substantial Completion Date;
(iii) Phase One Final Completion by the Scheduled Phase One Final Completion Date; and
(iiiv) Final Completion by the Scheduled Final Completion Date.
Appears in 1 contract
Samples: Project Agreement
Completion of Works. (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve:
(i) each Phase Completion by the applicable Scheduled Phase Completion Date;
(ii) Substantial Completion by the Scheduled Substantial Completion Date; and
(iiiii) Final Completion by the Scheduled Final Completion Date.
Appears in 1 contract
Samples: Project Agreement
Completion of Works. (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve:
(i) Early Occupancy Completion by the Scheduled Early Occupancy Completion Date;
(ii) Substantial Completion by the Scheduled Substantial Completion Date; and
(iiiii) Final Completion by the Scheduled Final Completion Date.
Appears in 1 contract
Samples: Project Agreement
Completion of Works. (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve:
(i) Substantial Completion by the Scheduled Substantial Completion Date; and;
(ii) Final Completion by the Scheduled Final Completion Date;
(iii) TIC Completion by the TIC Scheduled Completion Date; and
(iv) TIC Final Completion by the TIC Scheduled Final Completion Date.
(b) Without limiting the generality of Section 20.1(a), Project Co shall complete the Works in accordance with Schedule 15 β Works Schedule.
Appears in 1 contract
Samples: Project Agreement
Completion of Works. (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve:
(i) Interim Completion by the Scheduled Interim Completion Date;
(ii) Substantial Completion by the Scheduled Substantial Completion Date; and
(iiiii) Final Completion by the Scheduled Final Completion Date.
(b) Without limiting the generality of Section 20.1(a), Project Co shall complete the Works in accordance with the Works Schedule.
Appears in 1 contract
Samples: Project Agreement