Common use of Concurrent Delay Clause in Contracts

Concurrent Delay. When the completion of the Work is simultaneously delayed by an excusable delay and a delay arising from a cause not designated as excusable, Contractor may not be entitled to a time extension for the period of concurrent delay.

Appears in 62 contracts

Samples: General Construction Services Contract, Construction Contract, Construction Manager at Risk Contract

AutoNDA by SimpleDocs

Concurrent Delay. When the completion of the Work is simultaneously delayed by an excusable delay and a delay arising from a cause not designated as excusable, the Contractor may not be entitled to a time extension for the period of concurrent delay.

Appears in 42 contracts

Samples: Design Build Contract, Construction Management Agreement, Construction Management Agreement

Concurrent Delay. When the completion of the Work is simultaneously delayed by an excusable delay and a delay arising from a cause not designated as excusable, the Contractor may is not be entitled to a time extension for the period of concurrent delay.

Appears in 10 contracts

Samples: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement, Construction Contract

Concurrent Delay. When the completion of the Work is simultaneously delayed by an excusable delay and a delay arising from a cause not designated as excusable, Contractor may not be entitled to a reasonable time extension for the period of concurrent delay, as may be agreed to in writing between Contractor and Owner.

Appears in 3 contracts

Samples: Construction Manager at Risk Contract, Contract for Construction, Contract for Construction

AutoNDA by SimpleDocs

Concurrent Delay. When Notwithstanding anything herein to the contrary, when the completion of the Work is simultaneously delayed by a Weather Day or an excusable delay Excusable Delay and a delay arising from a cause not designated as excusable, Contractor may will not be entitled to a time an extension of Contract Time for the period of concurrent delay.

Appears in 2 contracts

Samples: Construction Manager at Risk Agreement, Professional Services Agreement

Concurrent Delay. When the completion of the Work is simultaneously delayed by an excusable delay and a delay arising from a cause not designated as excusable, Contractor may not be entitled to a time extension for the period of concurrent delay.. {00010282 / v / / LEGAL / FORMS / 11/16/2018}

Appears in 1 contract

Samples: Standard Agreement