Construction Contingency. Within the GMP shall be a line item amount representing five percent (5%) of the GMP for the Project ("Construction Contingency"). The Construction Contingency shall originally consist of Dollars ($ ). The Construction Contingency shall be for use by Contractor, as approved by District, to pay for miscellaneous work items that are required to complete the Project, including the coverage of trade scope gaps, missed work, areas of damage that may occur between trades during construction, subcontractor coordination problems, and Contractor coordination errors. The Construction Contingency shall not be used to pay the costs of enhancements or additions to the scope of work included within the District Contingency. Contractor shall obtain written approval from District prior to using the Construction Contingency. The following may be considered, at District's sole discretion, valid Construction Contingency items: (1) overtime and premium time; (2) costs to address safety items; (3) Contractor coordination issues and errors; (4) scope gaps; (5) trade damage; (6) errors or omissions in the Construction Documents on the part of Architect and Architect's consultants; (7) discrepancies with the Construction Documents pertaining to applicable building code requirements; and (8) for other items requested by Contractor if approved by District in District's sole discretion. If, on completion of the Project, funds remain in the Construction Contingency, such funds shall remain unspent and shall be allocated to District, except for any portion of savings added to the Construction Contingency, which savings shall be apportioned at completion of the Project as provided in Section 6 below.
Appears in 3 contracts
Samples: Construction Services Agreement, Construction Services Agreement, Construction Services Agreement
Construction Contingency. Within the GMP shall be a line item amount representing five percent (5%) of the GMP Construction Costs for the Project ("Construction Contingency"). The Construction Contingency shall originally consist of Dollars ($ ). The Construction Contingency shall be for use by Contractor, as approved by District, to pay for miscellaneous work items that are required to complete the Project, including the coverage of trade scope gaps, missed work, areas of damage that may occur between trades during construction, subcontractor coordination problems, and Contractor coordination errors. The Construction Contingency shall not be used to pay the costs of enhancements or additions to the scope of work included within the District Contingency. Contractor shall obtain written approval from District prior to using the Construction Contingency. The following may be considered, at District's sole discretion, valid Construction Contingency items: (1) overtime and premium time; (2) costs to address safety items; (3) Contractor coordination issues and errors; (4) scope gaps; (5) trade damage; (6) errors or omissions in the Construction Documents on the part of Architect and Architect's consultants; (7) discrepancies with the Construction Documents pertaining to applicable building code requirements; and (8) for other items requested by Contractor if approved by District in District's sole discretion. If, on completion of the Project, funds remain in the Construction Contingency, such funds shall remain unspent and shall be allocated to District, except for any portion of savings added to the Construction Contingency, which savings shall be apportioned at completion of the Project as provided in Section 6 below.
Appears in 2 contracts
Samples: Construction Services Agreement, Construction Services Agreement
Construction Contingency. Within the GMP shall be a line item amount representing five percent (5%) of the GMP for the Project ("Construction Contingency"). The Construction Contingency shall originally consist of Dollars and Cents ($ _). The Construction Contingency shall be for use by Contractor, as approved by District, to pay for miscellaneous work items that are required to complete the Project, including the coverage of trade scope gaps, missed work, areas of damage that may occur between trades during construction, subcontractor coordination problems, and Contractor coordination errors. The Construction Contingency shall not be used to pay the costs of enhancements or additions to the scope of work included within the District Contingency. Contractor shall obtain written approval from District prior to using the Construction Contingency. The following may be considered, at District's sole discretion, valid Construction Contingency items: (1) overtime and premium time; (2) costs to address safety items; (3) Contractor coordination issues and errors; (4) scope gaps; (5) trade damage; (6) errors or omissions in the Construction Documents on the part of Architect and Architect's consultants; (7) discrepancies with the Construction Documents pertaining to applicable building code requirements; and (8) for other items requested by Contractor if approved by District in District's sole discretion. If, on completion of the Project, funds remain in the Construction Contingency, such funds shall remain unspent and shall be allocated to District, except for any portion of savings added to the Construction Contingency, which savings shall be apportioned at completion of the Project as provided in Section 6 below.
Appears in 1 contract
Samples: Construction Services Agreement
Construction Contingency. Within the GMP shall be a line item amount representing five percent (5%) of the GMP Construction Cost for the Project ("Construction Contingency"). The Construction Contingency shall originally consist of Dollars ($ ). The Construction Contingency shall be for use by Contractor, as approved by District, to pay for miscellaneous work items that are required to complete the Project, including the coverage of trade scope gaps, missed work, areas of damage that may occur between trades during construction, subcontractor coordination problems, and Contractor coordination errors. The Construction Contingency shall not be used to pay the costs of enhancements or additions to the scope of work included within the District Contingency. Contractor shall obtain written approval from District prior to using the Construction Contingency. The following may be considered, at District's sole discretion, valid Construction Contingency items: (1) overtime and premium time; (2) costs to address safety items; (3) Contractor coordination issues and errors; (4) scope gaps; (5) trade damage; (6) errors or omissions in the Construction Documents on the part of Architect and Architect's consultants; (7) discrepancies with the Construction Documents pertaining to applicable building code requirements; and (8) for other items requested by Contractor if approved by District in District's sole discretion. If, on completion of the Project, funds remain in the Construction Contingency, such funds shall remain unspent and shall be allocated to District, except for any portion of savings added to the Construction Contingency, which savings shall be apportioned at completion of the Project as provided in Section 6 below.
Appears in 1 contract
Samples: Construction Services Agreement
Construction Contingency. Within the GMP shall be a line item amount representing five percent (5%) of the GMP for the Project ("Construction Contingency"). The Construction Contingency shall originally consist of Dollars and Cents ($ ). The Construction Contingency shall be for use by Contractor, as approved by District, to pay for miscellaneous work items that are required to complete the Project, including the coverage of trade scope gaps, missed work, areas of damage that may occur between trades during construction, subcontractor coordination problems, and Contractor coordination errors. The Construction Contingency shall not be used to pay the costs of enhancements or additions to the scope of work included within the District Contingency. Contractor shall obtain written approval from District prior to using the Construction Contingency. The following may be considered, at District's sole discretion, valid Construction Contingency items: (1) overtime and premium time; (2) costs to address safety items; (3) Contractor coordination issues and errors; (4) scope gaps; (5) trade damage; (6) errors or omissions in the Construction Documents on the part of Architect and Architect's consultants; (7) discrepancies with the Construction Documents pertaining to applicable building code requirements; and (8) for other items requested by Contractor if approved by District in District's sole discretion. If, on completion of the Project, funds remain in the Construction Contingency, such funds shall remain unspent and shall be allocated to District, except for any portion of savings added to the Construction Contingency, which savings shall be apportioned at completion of the Project as provided in Section 6 below.
Appears in 1 contract
Samples: Construction Services Agreement
Construction Contingency. Within the GMP shall be a line line-item amount representing five percent (5%) of the GMP for the Project ("Construction Contingency"). The Construction Contingency shall originally consist of Fifty-Five Thousand Dollars and ($ $55,000.00). The Construction Contingency shall be for use by Contractor, as approved by District, to pay for miscellaneous work items that are required to complete the Project, including the coverage of trade scope gaps, missed work, areas of damage that may occur between trades during construction, subcontractor coordination problems, and Contractor coordination errors. The Construction Contingency shall not be used to pay the costs of enhancements or additions to the scope of work included within the District Contingency. Contractor shall obtain written approval from District prior to using the Construction Contingency. The following may be considered, at District's sole discretion, valid Construction Contingency items: (1) overtime and premium time; (2) costs to address safety items; (3) Contractor coordination issues and errors; (4) scope gaps; (5) trade damage; (6) errors or omissions in the Construction Documents on the part of Architect and Architect's consultants; (7) discrepancies with the Construction Documents pertaining to applicable building code requirements; and (8) for other items requested by Contractor if approved by District in District's sole discretion. If, on completion of the Project, funds remain in the Construction Contingency, such funds shall remain unspent and shall be allocated to District, except for any portion of savings added to the Construction Contingency, which savings shall be apportioned at completion of the Project as provided in Section 6 below.
Appears in 1 contract
Samples: Construction Services Agreement
Construction Contingency. Within the GMP shall be a line line-item amount representing five percent (5%) of the GMP Construction Costs for the Project ("Construction Contingency"). The Construction Contingency shall originally consist of Dollars ($ _). The Construction Contingency shall be for use by Contractor, as approved by District, to pay for miscellaneous work items that are required to complete the Project, including the coverage of trade scope gaps, missed work, areas of damage that may occur between trades during construction, subcontractor coordination problems, and Contractor coordination errors. The Construction Contingency shall not be used to pay the costs of enhancements or additions to the scope of work included within the District Contingency. Contractor shall obtain written approval from District prior to using the Construction Contingency. The following may be considered, at District's sole discretion, valid Construction Contingency items: (1) overtime and premium time; (2) costs to address safety items; (3) Contractor coordination issues and errors; (4) scope gaps; (5) trade damage; (6) errors or omissions in the Construction Documents on the part of Architect and Architect's consultants; (7) discrepancies with the Construction Documents pertaining to applicable building code requirements; and (8) for other items requested by Contractor if approved by District in District's sole discretion. If, on completion of the Project, funds remain in the Construction Contingency, such funds shall remain unspent and shall be allocated to District, except for any portion of savings added to the Construction Contingency, which savings shall be apportioned at completion of the Project as provided in Section 6 below.
Appears in 1 contract
Samples: Site Lease
Construction Contingency. Within the GMP shall be a line item amount representing five percent (5%) of the GMP for to cover the Project Contractor contingency and errors and omissions allowance (collectively the "Construction Contingency"). The Construction Contingency shall originally consist of Dollars ($ ). The Construction Contingency shall be for use by Contractor, as approved by District, to pay for miscellaneous work items that are required to complete the Project, including the coverage of trade scope gaps, missed work, areas of damage that may occur between trades during construction, subcontractor coordination problems, and Contractor coordination errors. The Construction Contingency shall not be used to pay the costs of enhancements or additions to the scope of work included within the District Contingency. Contractor shall obtain written approval from District prior to using the Construction Contingency. The following may be considered, at District's sole discretion, valid Construction Contingency items: (1) overtime and premium time; (2) costs to address safety items; (3) Contractor coordination issues and errors; (4) scope gaps; (5) trade damage; (6) errors or omissions in the Construction Documents on the part of Architect and Architect's consultants; (7) discrepancies with the Construction Documents pertaining to applicable building code requirements; and (8) for other items requested by Contractor if approved by District in District's sole discretion. If, on completion of the Project, funds remain in the Construction Contingency, such funds shall remain unspent and shall be allocated to District, except for any portion of savings added to the Construction Contingency, which savings shall be apportioned at completion of the Project as provided in Section 6 below.
Appears in 1 contract
Samples: Construction Services Agreement
Construction Contingency. Within the GMP shall be a line item amount representing five percent (5%) of the GMP Construction Costs for the Project ("Construction Contingency"). The Construction Contingency shall originally consist of Dollars ($ _). The Construction Contingency shall be for use by Contractor, as approved by District, to pay for miscellaneous work items that are required to complete the Project, including the coverage of trade scope gaps, missed work, areas of damage that may occur between trades during construction, subcontractor coordination problems, and Contractor coordination errors. The Construction Contingency shall not be used to pay the costs of enhancements or additions to the scope of work included within the District Contingency. Contractor shall obtain written approval from District prior to using the Construction Contingency. The following may be considered, at District's sole discretion, valid Construction Contingency items: (1) overtime and premium time; (2) costs to address safety items; (3) Contractor coordination issues and errors; (4) scope gaps; (5) trade damage; (6) errors or omissions in the Construction Documents on the part of Architect and Architect's consultants; (7) discrepancies with the Construction Documents pertaining to applicable building code requirements; and (8) for other items requested by Contractor if approved by District in District's sole discretion. If, on completion of the Project, funds remain in the Construction Contingency, such funds shall remain unspent and shall be allocated to District, except for any portion of savings added to the Construction Contingency, which savings shall be apportioned at completion of the Project as provided in Section 6 below.
Appears in 1 contract
Samples: Construction Services Agreement
Construction Contingency. Within the GMP shall be a line line-item amount representing five percent (5%) of the GMP for the Project ("Construction Contingency"). The Construction Contingency shall originally consist of One Hundred Thousand Dollars ($ $100,000.00). The Construction Contingency shall be for use by Contractor, as approved by District, to pay for miscellaneous work items that are required to complete the Project, including the coverage of trade scope gaps, missed work, areas of damage that may occur between trades during construction, subcontractor coordination problems, and Contractor coordination errors. The Construction Contingency shall not be used to pay the costs of enhancements or additions to the scope of work included within the District Contingency. Contractor shall obtain written approval from District prior to using the Construction Contingency. The following may be considered, at District's sole discretion, valid Construction Contingency items: (1) overtime and premium time; (2) costs to address safety items; (3) Contractor coordination issues and errors; (4) scope gaps; (5) trade damage; (6) errors or omissions in the Construction Documents on the part of Architect and Architect's consultants; (7) discrepancies with the Construction Documents pertaining to applicable building code requirements; and (8) for other items requested by Contractor if approved by District in District's sole discretion. If, on completion of the Project, funds remain in the Construction Contingency, such funds shall remain unspent and shall be allocated to District, except for any portion of savings added to the Construction Contingency, which savings shall be apportioned at completion of the Project as provided in Section 6 below.
Appears in 1 contract
Samples: Construction Services Agreement