Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements: (a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord; (i) Such construction shall not, and Tenant’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents; (c) Tenant’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility; (d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility; (e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and (f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, and copies of any new or revised certificates of occupancy.
Appears in 2 contracts
Samples: Merger Agreement (PNK Entertainment, Inc.), Merger Agreement (Pinnacle Entertainment Inc.)
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(i) Such construction shall not, and TenantXxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) TenantXxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire or lease off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, and copies of any new or revised certificates of occupancy.
Appears in 2 contracts
Samples: Master Lease (Gaming & Leisure Properties, Inc.), Master Lease (Eldorado Resorts, Inc.)
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such Tenant shall comply with the applicable building codes and regulations with respect to the construction shall not be commenced until Tenant of the applicable Capital Improvement and shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior with respect to such commencement, including those permits and authorizations required pursuant to any Gaming RegulationsCapital Improvement, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(i) Such construction shall not, and Tenant’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) Tenant’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(eb) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility in accordance with Prudent Industry Practice and in conformity in all material respects with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(fc) Promptly following the completion No later than February 1st of such constructioneach calendar year, Tenant shall deliver present to Landlord an “as builtAnnual Construction Summary” drawings that (i) reports on the Capital Improvements completed during the prior calendar year, (ii) reconciles the Tenant Capital Improvements and the Capital Improvements financed by Landlord with the Annual Capital Improvement Plan established for the prior calendar year, (iii) provides a pictorial representation of such additioneach Facility illustrating which portions of the Facility are Tenant’s Property and which portions are Leased Property, certified as accurate by (iv) provides a written description containing sufficient detail to provide a clear demarcation between Tenant’s Property and the licensed architect or engineer selected by Leased Property respective to each Tenant to supervise such workCapital Improvement in excess of Five Hundred Thousand Dollars ($500,000), and copies (v) is accompanied by a report of any new a nationally recognized accounting firm that confirms, based upon an agreed-upon procedures review, the accuracy of the Annual Construction Summary and that the Capital Improvements have not degraded the structural integrity of the Leased Property. Tenant shall select such nationally recognized accounting firm, subject to the approval of Landlord. Any fees associated with the review of the nationally recognized accounting firm shall be shared equally between Tenant and Landlord. If, as a result of the report from the nationally recognized accounting firm, Landlord determines that a Capital Improvement has impaired the structural integrity or revised certificates value of occupancythe Leased Property or that a Capital Improvement has been improperly designated as Tenant’s Property, Landlord may demand and Tenant shall be obligated to remediate the problems noted by Landlord to the satisfaction of Landlord.
Appears in 2 contracts
Samples: Master Lease (Windstream Services, LLC), Master Lease (Communications Sales & Leasing, Inc.)
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(i) Such construction shall not, and TenantXxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) TenantXxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, and copies of any new or revised certificates of occupancy.
Appears in 2 contracts
Samples: Master Lease (Gaming & Leisure Properties, Inc.), Master Lease (PNK Entertainment, Inc.)
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, required hereunder for all any Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(i) Such construction shall not, and Tenant’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) Tenant’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, and copies of any new or revised certificates of occupancy.
Appears in 2 contracts
Samples: Master Lease (Boyd Gaming Corp), Master Lease (Gaming & Leisure Properties, Inc.)
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no unreimbursed cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(i) Such construction shall not, and Tenant’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(cb) Tenant’s licensed architect or engineer (if any) shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of or the applicable Facility;
(dc) During Initiated after Substantial Completion, during and following completion of such construction, the parking and other amenities which are located in the applicable Facility Leased Property or on the Land of such Facility shall remain adequate for the operation of such Facility the Leased Property for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent (not to be unreasonably withheld) and at no additional unreimbursed expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire or lease off-site parking to serve such Facility the Leased Property as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facilitythe Leased Property;
(ed) All work done in connection with such construction Capital Improvements shall be done promptly constructed by Tenant, without unreimbursed expense to Landlord, in a good, professional and using workmanlike manner so as not to void or make voidable any roof or other warranties, employing materials and resulting in work that is at least as good product and condition as of quality consistent with the remaining areas quality of the applicable Facility Capital Improvements at Comparable Facilities (as and if applicable), free of material defects, and in conformity with all Legal Requirements, includingall applicable encumbrances and all regulations and orders, without limitationrules and regulations of the Board of Fire Insurance Underwriters or any other body exercising similar functions, any applicable minority or women owned business requirementsand in compliance with the terms and conditions of this Lease; and
(fe) Promptly following the completion of such constructionconstruction (from and after completion of the Planned Improvements), Tenant shall shall, if it would be customary to prepare “as built” drawings of such addition, deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, and copies of any new or revised certificates of occupancyoccupancy (and if the Capital Improvements involve any change to the footprint of the Project or the erection of a new building, an ALTA survey for the applicable Leased Property certified to Landlord and any Facility Mortgagee), proof of payment for all labor and materials (including conditional and unconditional lien waivers), and if and to the extent commercially obtainable, copies of guarantees, if any.
Appears in 2 contracts
Samples: Ground Lease (Bally's Chicago, Inc.), Ground Lease (Bally's Chicago, Inc.)
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(ib) Such construction shall not, and, if such Capital Improvement is of a type that would reasonably be expected to require the services of an architect or engineer in connection with customary construction practices for projects of a similar size, scope and Tenantcomplexity, Xxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) TenantIf such Capital Improvement is of a type that would reasonably be expected to require the services of an architect or engineer in connection with customary construction practices for projects of a similar size, scope and complexity, Xxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;; ACTIVE/119768607.18
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, unless such Capital Improvements have not resulted in any changes to the previously delivered “as built” drawings, and copies of any new or revised certificates of occupancy.
Appears in 1 contract
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(i) Such construction shall not, and TenantXxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) TenantXxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant Xxxxxx to supervise such work, and copies of any new or revised certificates of occupancy.
Appears in 1 contract
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such Tenant shall comply with the applicable regulations with respect to the construction shall not be commenced until Tenant of the applicable Capital Improvement and shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to for such commencement, including those permits and authorizations required pursuant to any Gaming RegulationsCapital Improvement, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that ,: (i) any such joinder shall be at no Tenant’s sole cost or expense to Landlordand expense; and (ii) Landlord has the right to pre-approve any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;application; and
(i) Such construction shall not, and Tenant’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) Tenant’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(eb) All work done in connection with such construction construction: (i) shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity all material respects with all Legal RequirementsRequirements and in accordance with Prudent Industry Practice; and (ii) shall be completed in all respects once undertaken by Tenant, includingor otherwise Tenant must restore all affected property, without limitationreal or otherwise, any applicable minority or women owned business requirements; andto its original condition prior to undertaking said work.
(fc) Promptly following No later than fifteen (15) days of the completion end of such constructioneach month, Tenant shall deliver provide to Landlord a “Monthly Construction Summary,” which shall be in form and substance satisfactory to Landlord and which shall include at a minimum the following: (i) reports on all changes and/or repairs to the Leased Assets, including but not limited to, the Capital Improvements completed during the prior calendar month; (ii) a reconciliation of all such Capital Improvements with the Annual Capital Improvement Plan established for such calendar year (or for the previous calendar year with respect to the Quarterly Construction Summary due February 1st); (iii) a pictorial representation of each Leased Asset illustrating which portions of the Leased Asset are, as built” drawings applicable, Tenant Assets, Landlord Retained Assets, and/or Leased Assets; (iv) a written description containing sufficient detail to provide a clear demarcation between Tenant Assets[, Landlord Retained Assets] and the Leased Assets; and (v) a report at Tenant’s cost from a nationally recognized accounting firm that confirms, based upon an agreed-upon procedures review, the accuracy of the Monthly Construction Summary and that the Capital Improvements have not degraded the structural integrity of the Leased Assets. Tenant shall select such nationally recognized accounting firm, subject to the approval of Landlord. If, because of such additionreport, certified Landlord determines that a Capital Improvement has impaired the structural integrity or value of the Leased Assets or that a Capital Improvement has been improperly designated as accurate by the licensed architect or engineer selected by Tenant Assets, Landlord may require Tenant to supervise such work, and copies remediate the problems noted by Landlord to the satisfaction of any new or revised certificates of occupancyLandlord.
Appears in 1 contract
Samples: Master Lease
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(ib) Such construction shall not, and, if such Capital Improvement is of a type that would reasonably be expected to require the services of an architect or engineer in connection with customary construction practices for projects of a similar size, scope and Tenantcomplexity, Xxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) TenantIf such Capital Improvement is of a type that would reasonably be expected to require the services of an architect or engineer in connection with customary construction practices for projects of a similar size, scope and complexity, Xxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such workwork unless such Capital Improvements have not resulted in any changes to the previously delivered “as built” drawings, and copies of any new or revised certificates of occupancy.
Appears in 1 contract
Construction Requirements for All Capital Improvements. Whether or not LandlordLxxxxxxx’s review and approval is required, required hereunder for all any Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(i) Such construction shall not, and TenantTxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) TenantTxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, and copies of any new or revised certificates of occupancy.
Appears in 1 contract
Samples: Master Lease (Boyd Gaming Corp)
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(b) (i) Such construction shall not, and TenantXxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) TenantXxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire or lease off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, and copies of any new or revised certificates of occupancy.
Appears in 1 contract
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(ib) Such construction shall not, and TenantXxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) TenantXxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto)law; provided, however, with LandlordXxxxxxxx’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, and copies of any new or revised certificates of occupancy.
Appears in 1 contract
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(i) Such construction shall not, and Tenant’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) Tenant’s 's licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, and copies of any new or revised certificates of occupancy.
Appears in 1 contract
Samples: Merger Agreement (Gaming & Leisure Properties, Inc.)
Construction Requirements for All Capital Improvements. Whether or not Landlord’s 's review and approval is required, for all Capital Improvements:
(a) Such Tenant shall comply with the applicable building codes and regulations with respect to the construction shall not be commenced until Tenant of the applicable Capital Improvement and shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior with respect to such commencement, including those permits and authorizations required pursuant to any Gaming RegulationsCapital Improvement, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that that: (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(b) All work done in connection with such construction: (i) Such construction shall be done promptly and using materials and resulting in work that is in accordance with Prudent Industry Practice and in conformity in all material respects with all Legal Requirements; and (ii) shall not, and Tenant’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;Facility; and
(c) Tenant’s licensed architect or engineer No later than February 1st, May 1st, August 1st and November 1st of each calendar year, Tenant shall certify present to Landlord that such architect or engineer believes that a "Quarterly Construction Summary", which shall be in form and substance satisfactory to Landlord and which shall include at a minimum the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, following: (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking reports on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such FacilityCapital Improvements completed during the prior calendar quarter;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, and copies of any new or revised certificates of occupancy.
Appears in 1 contract
Samples: Master Lease
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(i) Such construction shall not, and TenantTxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) TenantTxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable FacilityProperty;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility Leased Improvements or on the Land of such Facility shall remain adequate for the operation of such Facility the Leased Property for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire or lease off-site parking to serve such Facility the Leased Property as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facilitythe Leased Property;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, and copies of any new or revised certificates of occupancy.
Appears in 1 contract
Samples: Lease (Penn National Gaming Inc)
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencementcommencement (if any), including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval in respect of any Landlord as hereinabove provided shall Approved Capital Improvement have been so approved by Landlord;
(b) In the case of any Capital Improvements that consist of adding new structures or enlarging existing structures or cost more than Seventy Five Million Dollars ($75,000,000) (subject to adjustment for the CPI Increase), (i) Such such construction shall not, and Tenant’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) (x) for each Landlord Approved Capital Improvement, Tenant’s general contractor shall certify to Landlord that such general contractor believes that such construction is in compliance with such design and corresponding construction documents and (y) for each Permitted Capital Improvement, Tenant shall certify to Landlord that Tenant believes that such construction is in compliance with such design and corresponding construction documents;
(c) In the case of Permitted Capital Improvements (excluding Cosmetic Alterations), (i) such construction shall not, and Tenant shall certify to Landlord that Tenant believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant shall certify to Landlord that Tenant believes that such construction is in compliance with such design and corresponding construction documents;
(i) In the case of Landlord Approved Capital Improvements (excluding Cosmetic Alterations), Tenant’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes believes, to the best of such architect’s or engineer’s knowledge, and (ii) in the case of Permitted Capital Improvements (excluding Cosmetic Alterations), Tenant shall certify to Landlord that Tenant believes, to the best of Tenant’s knowledge, that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(de) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such the Facility shall remain adequate for the operation of such the Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire or lease off-site parking to serve such the Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such the Facility;
(ef) All work done in connection with such construction shall be done promptly and (i) promptly, (ii) using materials and resulting in work a manner that results in such Capital Improvement being in a condition and of a quality that is at least as good product and condition as the remaining areas of the applicable Facility and (iii) in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(fg) Promptly If applicable in accordance with customary and prudent industry standards or otherwise obtained by Tenant in connection with such construction, promptly following the completion of such constructionany Landlord Approved Capital Improvement, Tenant shall deliver to Landlord “as built” drawings of such additionaddition (or written confirmation from the relevant general contractor or architect that such Capital Improvement has been built in accordance with the plans and specifications), certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, and copies of any new or revised certificates of occupancy.
Appears in 1 contract
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;; ACTIVE/119970514.22
(ib) Such construction shall not, and, if such Capital Improvement is of a type that would reasonably be expected to require the services of an architect or engineer in connection with customary construction practices for projects of a similar size, scope and Tenantcomplexity, Xxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) TenantIf such Capital Improvement is of a type that would reasonably be expected to require the services of an architect or engineer in connection with customary construction practices for projects of a similar size, scope and complexity, Xxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such workwork unless such Capital Improvements have not resulted in any changes to the previously delivered “as built” drawings, and copies of any new or revised certificates of occupancy.
Appears in 1 contract
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(ib) Such construction shall not, and, if such Capital Improvement is of a type that would reasonably be expected to require the services of an architect or engineer in connection with customary construction practices for projects of a similar size, scope and Tenantcomplexity, Xxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) TenantIf such Capital Improvement is of a type that would reasonably be expected to require the services of an architect or engineer in connection with customary construction practices for projects of a similar size, scope and complexity, Xxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, unless such Capital Improvements have not resulted in any changes to the previously delivered “as built” drawings, and copies of any new or revised certificates of occupancy.
Appears in 1 contract
Construction Requirements for All Capital Improvements. Whether or not Landlord’s review and approval is required, for all Capital Improvements:
(a) Such construction shall not be commenced until Tenant shall have procured and paid for all municipal and other governmental permits and authorizations required to be obtained prior to such commencement, including those permits and authorizations required pursuant to any Gaming Regulations, and Landlord shall join in the application for such permits or authorizations whenever such action is necessary; provided, however, that (i) any such joinder shall be at no cost or expense to Landlord; and (ii) any plans required to be filed in connection with any such application which require the approval of Landlord as hereinabove provided shall have been so approved by Landlord;
(i) Such construction shall not, and TenantXxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the design of such |US-DOCS\126208570.12|| construction (as illustrated through the applicable corresponding construction documents) shall not, impair the structural strength of any component of the applicable Facility or overburden the electrical, water, plumbing, HVAC or other building systems of any such component in a manner that would violate applicable building codes or prudent industry practices, and (ii) Tenant’s general contractor shall certify to Landlord that such construction is in compliance with such design and corresponding construction documents;
(c) TenantXxxxxx’s licensed architect or engineer shall certify to Landlord that such architect or engineer believes that the detailed plans and specifications conform to, and comply with, in all material respects all applicable building, subdivision and zoning codes, laws, ordinances and regulations imposed by all governmental authorities having jurisdiction over the Leased Property of the applicable Facility;
(d) During and following completion of such construction, the parking and other amenities which are located in the applicable Facility or on the Land of such Facility shall remain adequate for the operation of such Facility for its Primary Intended Use and in no event shall such parking be less than that which is required by law (including any variances with respect thereto); provided, however, with Landlord’s prior consent and at no additional expense to Landlord, (i) to the extent additional parking is not already a part of a Capital Improvement, Tenant may construct additional parking on the Land; or (ii) Tenant may acquire or lease off-site parking to serve such Facility as long as such parking shall be reasonably proximate to, and dedicated to, or otherwise made available to serve, such Facility;
(e) All work done in connection with such construction shall be done promptly and using materials and resulting in work that is at least as good product and condition as the remaining areas of the applicable Facility and in conformity with all Legal Requirements, including, without limitation, any applicable minority or women owned business requirements; and
(f) Promptly following the completion of such construction, Tenant shall deliver to Landlord “as built” drawings of such addition, certified as accurate by the licensed architect or engineer selected by Tenant to supervise such work, and copies of any new or revised certificates of occupancy.
Appears in 1 contract