Controls and Integration Sample Clauses

Controls and Integration. The existing RTU is sufficient for the scope of this project. Spare I/O points will be used to accommodate the additions required.
AutoNDA by SimpleDocs
Controls and Integration. The existing RTUs are sufficient to accommodate interconnection of the Small Generating Facility. Spare I/O points will be used to accommodate the additions required.
Controls and Integration. The existing RTU is sufficient for the scope of this project. A new I/O card will be installed to accommodate the additions required for the Small Generating Facility. The new protective relays will connect to the existing SEL-2020 communications processors using RS- 232 serial connections. Digital panel meters will be required to provide analog telemetry for the new line position. RE-01 control handles capable of remote operation will be installed for the new circuit breaker for manual trip(open)/close operation of the R215 breaker and to provide necessary status of trip coil(s). A RE-43A/M control handle capable of remote operation shall be installed for breaker R215 to allow for the automatic reclosing function to be enabled or disabled.
Controls and Integration. The existing RTU is sufficient for the scope of this project and spare status/control/analog points will be used to accommodate interconnection of the Small Generating Facility.
Controls and Integration. The Ephratah Substation does not currently have an RTU installed, therefore remote operation and monitoring via the energy management system (“EMS”) is not currently available.
Controls and Integration. The existing RTU is sufficient for the scope of this project with the following modifications: o one (1) new I/O card will be installed to accommodate the additions required; o one (1) RE-01 control handle capable of remote operation for breaker R30 shall be installed to allow for the manual trip(open)/close operation and to provide status of the trip coil(s); and o one (1) RE-43A/M control handle capable of remote operation for breaker R30 shall be installed to allow for enabling/disabling of the automatic reclose function.
Controls and Integration. The existing RTU is sufficient for the scope of this project. Spare status/control/analog points will be used to accommodate the additions required. The new protective relays will connect to the existing SEL-2020 communications processors using RS-232 serial connections.
AutoNDA by SimpleDocs
Controls and Integration. The existing RTU is not sufficient for the scope of this project. Spare I/O points will be used to accommodate the additions required. Construction for an RTU upgrade at Marshville Substation is scheduled to be initiated July 2021. This Agreement assumes that the RTU upgrade will be completed before completion of the Interconnection Customer’s Small Generation Facility. Spare I/O points will be used to accommodate the additions required.
Controls and Integration. The existing RTUs are sufficient for the scope of this project. Spare I/O points will be used to accommodate the additions required. The existing gateway shall be upgraded to a Garrettcom DX-940E with T1 network capability.
Controls and Integration. The existing RTUs are sufficient for the scope of this project. Spare I/O points will be used to accommodate the additions required. The new relays shall be interfaced to the existing SEL-2020B comm processor to allow for remote access of the relay fault logs.