Correction Time Objectives. 8.3.1 Boeing's objective for making Corrections is 10 working days for avionics and electronic Boeing Products, 30 working days for Corrections of other Boeing Products performed at Boeing's facilities, and 40 working days for Corrections of other Boeing Products performed at a Boeing subcontractor's facilities. The objectives are measured from the date Boeing receives the defective Boeing Product and a valid claim to the date Boeing ships the Correction.
Appears in 4 contracts
Samples: Aircraft General Terms Agreement (Copa Holdings, S.A.), Aircraft General Terms Agreement (Hawaiian Airlines Inc/Hi), Aircraft General Terms Agreement (Amtran Inc)
Correction Time Objectives. 8.3.1 Boeing's ’s objective for making Corrections is 10 working days for avionics and electronic Boeing Products, 30 working days for Corrections of other Boeing Products performed at Boeing's facilities, ’s facilities and 40 working days for Corrections of other Boeing Products performed at a Boeing subcontractor's ’s facilities. The objectives are measured from the date Boeing receives the defective Boeing Product and a valid claim to the date Boeing ships the CorrectionCorrected Boeing Product.
Appears in 4 contracts
Samples: Purchase Agreement (Fedex Corp), Letter Agreement (Fedex Corp), Aircraft General Terms Agreement (Fedex Corp)
Correction Time Objectives. 8.3.1 Boeing's objective for making Corrections is 10 working days for avionics and electronic Boeing Products, 30 working days for Corrections of other Boeing Products performed at Boeing's facilities, facilities and 40 working days for Corrections of other Boeing Products performed at a Boeing subcontractor's facilities. The objectives are measured from the date Boeing receives the defective Boeing Product and a valid claim to the date Boeing ships the CorrectionCorrected Boeing Product.
Appears in 2 contracts
Samples: Aircraft General Terms Agreement (Alaska Air Group, Inc.), Aircraft General Terms Agreement (Alaska Air Group Inc)
Correction Time Objectives. 8.3.1 Boeing's ’s objective for making Corrections is 10 working days for avionics and electronic Boeing Products, 30 working days for Corrections of other Boeing Products performed at Boeing's ’s facilities, and 40 working days for Corrections of other Boeing Products performed at a Boeing subcontractor's ’s facilities. The objectives are measured from the date Boeing receives the defective Boeing Product and a valid claim to the date Boeing ships the Correction.
Appears in 1 contract
Samples: Aircraft General Terms Agreement (Copa Holdings, S.A.)
Correction Time Objectives. 8.3.1 Boeing's objective for making Corrections is 10 ten (10) working days for avionics and electronic Boeing Products, 30 thirty (30) working days for Corrections of other Boeing Products performed at Boeing's facilities, facilities and 40 forty (40) working days for Corrections of other Boeing Products performed at a Boeing subcontractor's facilities. The objectives are measured from the date Boeing receives the defective Boeing Product and a valid claim to the date Boeing ships the CorrectionCorrected Boeing Product.
Appears in 1 contract
Correction Time Objectives. 8.3.1 Boeing's objective for making Corrections is 10 ten (10) working days for avionics and electronic Boeing Products, 30 thirty (30) working days for Corrections of other Boeing Products performed at Boeing's facilities, facilities and 40 forty (40) working days for Corrections of other Boeing Products performed at a Boeing subcontractor's facilities. The objectives are measured from the date Boeing receives the defective Boeing Product and a valid claim to the date Boeing ships the Correction.
Appears in 1 contract
Correction Time Objectives. 8.3.1 9.3.1 Boeing's objective for making Corrections is 10 working days for avionics and electronic Boeing Products, 30 working days for Corrections of other Boeing Products performed at Boeing's facilitiesfa- cilities, and 40 working days for Corrections of other Boeing Products performed at a Boeing subcontractor's facilities. The objectives are measured from the date Boeing receives the defective Boeing Product and a valid claim to the date Boeing ships the Correction.
Appears in 1 contract
Correction Time Objectives. 8.3.1 Boeing's ’s objective for making Corrections is 10 ten (10) working days for avionics and electronic Boeing Products, 30 thirty (30) working days for Corrections of other Boeing Products performed at Boeing's facilities, ’s facilities and 40 forty (40) working days for Corrections of other Boeing Products performed at a Boeing subcontractor's ’s facilities. The objectives are measured from the date Boeing receives the defective Boeing Product and a valid claim to the date Boeing ships the CorrectionCorrected Boeing Product.
Appears in 1 contract
Samples: Aircraft General Terms Agreement (Southwest Airlines Co)
Correction Time Objectives. 8.3.1 1.8.3.1 Boeing's objective for making Corrections is 10 working days for avionics and electronic Boeing ProductsSpare Parts, 30 working days for Corrections of other Boeing Products Spare Parts performed at Boeing's facilities, and 40 working days for Corrections of other Boeing Products Spare Parts performed at a Boeing subcontractor's facilities. The objectives are measured from the date Boeing receives the defective Boeing Product Spare Part and a valid claim to the date Boeing ships the Correction.
Appears in 1 contract
Samples: General Terms Agreement (Spirit AeroSystems Holdings, Inc.)
Correction Time Objectives. 8.3.1 1.8.3.1 Boeing's objective for making Corrections is 10 ten (10) working days for avionics and electronic Boeing ProductsSpare Parts, 30 thirty (30) working days for Corrections of other Boeing Products Spare Parts performed at Boeing's facilities, and 40 forty (40) working days for Corrections of other Boeing Products Spare Parts performed at a Boeing subcontractor's facilities. The objectives are measured from the date Boeing receives the defective Boeing Product Spare Part and a valid claim to the date Boeing ships the CorrectionCorrected Boeing Spare Part.
Appears in 1 contract
Correction Time Objectives. 8.3.1 9.3.1 Boeing's objective for making Corrections is 10 working days for avionics and electronic Boeing Products, 30 working days for Corrections of other Boeing Products performed at Boeing's facilities, and 40 working days for Corrections of other Boeing Products performed at a Boeing subcontractor's facilities. The objectives are measured from the date Boeing receives the defective Boeing Product and a valid claim to the date Boeing ships the Correction.
Appears in 1 contract
Samples: Aircraft General Terms Agreement (Continental Airlines Inc /De/)