Cost Reimbursable, Cost Sharing Milestone Payment Method. (with not to exceed ceiling): Payment is contingent upon satisfactory progress toward completion of milestones as delineated in Project Agreement and acceptable cost share. Payment shall be made based on actual costs incurred in completing milestones up to the maximum amount allowable under the applicable Project Agreement, provided the designated AOR has verified compliance with the Statement of Work and accomplishment of the stated effort. Per (ii) below, either a Status Report identifying any associated technical tasks and the progress toward completion of each milestone, a Deliverable Report, or a Milestone Report is required concurrent with the invoice. An acceptable invoice for reimbursable payment is one that (on the invoice or on the attached Status, Deliverable, or Milestone Report in accordance with each Project Agreement): (i) contains the date of invoice and the Base Agreement number and Project Agreement number; (ii) identifies any associated technical milestones and the progress toward completion of each milestone; (iii) includes a report of the cost share expended towards the accomplishment of the SOW tasks and/or milestones. This cost share report may be attached to the invoice if contractor practices make inclusion of such information on the invoice itself impractical. If the cost share report is separate from the invoice, it must be signed by an authorized representative. This cost share report must contain a breakout of the cost share by cost element similar to the level of detail required on the invoice and any in-kind contributions. The preferred method of reporting cost share is to provide an invoice for actual cost incurred with a value for the cost shared amount and the value to be reimbursed by the Government through the CMF; (iv) includes a description of supplies and services, labor costs, subcontractor costs, material costs, travel costs, other direct costs, and extended totals; (v) indicates the current period and cumulative man-hours and costs incurred through the period indicated on the invoice; and
Appears in 3 contracts
Samples: Base Agreement, Base Agreement (Regeneron Pharmaceuticals, Inc.), Base Agreement
Cost Reimbursable, Cost Sharing Milestone Payment Method. (with not to exceed ceiling): Payment is contingent upon satisfactory progress toward completion of milestones as delineated in Research Project Agreement Award and acceptable cost share. Payment shall be made based on actual costs incurred in completing milestones up to the maximum amount allowable under the applicable Research Project AgreementAward, provided the designated AOR has verified compliance with the Statement of Work and accomplishment of the stated effort. Per (ii) below, either Either a Status Report identifying any associated technical tasks and the progress toward completion of each milestone, a Deliverable Report, or a Milestone Report is required concurrent with the invoice. An acceptable invoice for reimbursable payment is one that (on the invoice or on the attached Status, Deliverable, or Milestone Report in accordance with each Research Project AgreementAward):
(i) 6.1.4.1. contains the date of invoice and the Base Agreement number and Research Project Agreement Award number;
(ii) 6.1.4.2. identifies any associated technical milestones and the progress toward completion of each milestone;
(iii) 6.1.4.3. includes a report of the cost share expended towards the accomplishment of the SOW tasks and/or milestones. This cost share report may be attached to the invoice if contractor practices make inclusion of such information on the invoice itself impractical. If the cost share report is separate from the invoice, it must be signed by an authorized representative. This cost share report must contain a breakout of the cost share by cost element similar to the level of detail required on the invoice and any in-kind contributions. The preferred method of reporting cost share is to provide an invoice for actual cost incurred with a value for the cost shared amount and the value to be reimbursed by the Government through the CMFCM;
(iv) 6.1.4.4. includes a description of supplies and services, labor costs, subcontractor costs, material costs, travel costs, other direct costs, indirect costs, and extended totals; (v) ;
6.1.4.5. indicates the current period and cumulative man-hours and costs incurred through the period indicated on the invoice; and
6.1.4.6. contains the following certification statement: “I certify that the amounts invoiced are for costs incurred in accordance with the agreement, the work reflected has been performed, and prior payment has not been received.” Authorized Signature
Appears in 2 contracts
Samples: Base Agreement, Base Agreement
Cost Reimbursable, Cost Sharing Milestone Payment Method. (with not to exceed ceiling): Payment is contingent upon satisfactory progress toward completion of milestones as delineated in Project Agreement and acceptable cost share. Payment shall be made based on actual costs incurred in completing milestones up to the maximum amount allowable under the applicable Project Agreement, provided the designated AOR has verified compliance with the Statement of Work and accomplishment of the stated effort. Per (ii) below, either a Status Report identifying any associated technical tasks and the progress toward completion of each milestone, a Deliverable Report, or a Milestone Report is required concurrent with the invoice. An acceptable invoice for reimbursable payment is one that (on the invoice or on the attached Status, Deliverable, or Milestone Report in accordance with each Project Agreement):
(i) contains the date of invoice and the Base Agreement number and Project Agreement number;
(ii) identifies any associated technical milestones and the progress toward completion of each milestone;
(iii) includes a report of the cost share expended towards the accomplishment of the SOW tasks and/or milestones. This cost share report may be attached to the invoice if contractor practices make inclusion of such information on the invoice itself impractical. If the cost share report is separate from the invoice, it must be signed by an authorized representative. This cost share report must contain a breakout of the cost share by cost element similar to the level of detail required on the invoice and any in-kind contributions. The preferred method of reporting cost share is to provide an invoice for actual cost incurred with a value for the cost shared amount and the value to be reimbursed by the Government through the CMF;
(iv) includes a description of supplies and services, labor costs, subcontractor costs, material costs, travel costs, other direct costs, and extended totals; ;
(v) indicates the current period and cumulative man-hours and costs incurred through the period indicated on the invoice; and
(vi) contains the following certification statement: “I certify that the amounts invoiced are for costs incurred in accordance with the agreement, the work reflected has been performed, and prior payment has not been received.” Authorized Signature Invoices may be submitted no more frequently than monthly. The PAH shall submit invoices and any necessary supporting documentation via email to XXXX-xxxxxxxx@xxx.xxx. For Cost type Project Agreements, the PAH’s final invoice (completion invoice) will be clearly indicated as such and shall indicate the cumulative amounts incurred and billed to completion, and a written certification of the total hours expended. Actual project costs incurred and cost share performance, if applicable, of each project shall be reported and reviewed each quarter.
Appears in 2 contracts
Samples: Base Agreement, Base Agreement
Cost Reimbursable, Cost Sharing Milestone Payment Method. (with not to exceed ceiling) for Consortium Members not subject to full Cost Accounting Standards on other agreements or contracts): Payment is contingent upon satisfactory progress toward completion of milestones as delineated in each Project Agreement and acceptable cost share, and subject to Article 25, Allowable Costs, paragraph 3. Payment shall be made based on actual costs incurred in completing milestones up to the maximum amount allowable under the applicable Project Agreement, provided the designated AOR has verified compliance with the Statement of Work and accomplishment of the stated effort. Per (iiiii) below, either a Status Report identifying any associated technical tasks and the progress toward completion of each milestone, a Deliverable Reportdeliverable report, or a Milestone Report milestone report is required concurrent with the invoice. An acceptable invoice for reimbursable payment is one that (on the invoice or on the attached Statusstatus, Deliverabledeliverable, or Milestone Report milestone report in accordance with each Project Agreement):
(i) i. Is addressed to the CM and contains the CM’s address; Advanced Technology International
ii. contains the date of invoice, invoice number, and the Base Agreement and prototype project agreement number and (20XX-XXX Project Agreement numberX);
(ii) iii. identifies any associated technical milestones and the progress toward completion of each milestone;
(iii) iv. includes a report of the cost share expended towards the accomplishment of the SOW tasks and/or milestones. This cost share report may be attached to the invoice if contractor practices make inclusion of such information on the invoice itself impractical. If the cost share report is separate from the invoice, it must be signed by an authorized representative. This cost share report must contain a breakout of the cost share by cost element similar to the level of detail required on the invoice and any in-kind contributions. The preferred method of reporting cost share is to provide an invoice for actual cost incurred with a value for the cost shared amount and the value to be reimbursed by the Government through the CMF;
(iv) CM; v. includes a description of supplies and services, labor costs, subcontractor costs, material costs, travel costs, other direct costs, fixed fee, if applicable, and extended totals; (v) indicates the current period and cumulative man-hours and costs incurred through the period indicated on the invoice; and;
Appears in 1 contract
Samples: Base Agreement
Cost Reimbursable, Cost Sharing Milestone Payment Method. (with not to exceed ceiling): Payment is contingent upon satisfactory progress toward completion of milestones as delineated in Project Agreement Prototype Award and acceptable cost share. Payment shall be made based on actual costs incurred in completing milestones up to the maximum amount allowable under the applicable Project AgreementPrototype Award, provided the designated AOR has verified compliance with the Statement of Work and accomplishment of the stated effort. Per (ii) below, either a Status Report identifying any associated technical tasks and the progress toward completion of each milestone, a Deliverable Report, or a Milestone Report is required concurrent with the invoice. An acceptable invoice for reimbursable payment is one that (on the invoice or on the attached Status, Deliverable, or Milestone Report in accordance with each Project AgreementPrototype Award):
(i) i. contains the date of invoice and the Base Agreement number and Project Agreement Prototype Award number;
(ii) . identifies any associated technical milestones and the progress toward completion of each milestone;
(iii) . includes a report of the cost share expended towards the accomplishment of the SOW tasks and/or milestones. This cost share report may be attached to the invoice if contractor practices make inclusion of such information on the invoice itself impractical. If the cost share report is separate from the invoice, it must be signed by an authorized representative. This cost share report must contain a breakout of the cost share by cost element similar to the level of detail required on the invoice and any in-kind contributions. The preferred method of reporting cost share is to provide an invoice for actual cost incurred with a value for the cost shared amount and the value to be reimbursed by the Government through the CMF;
(CM; iv) . includes a current period description of supplies and services, labor costs, subcontractor costs, material costs, travel costs, other direct costs, and extended totals; (v) indicates the current period and cumulative man-hours and costs incurred through the period indicated on the invoice; and;
Appears in 1 contract
Samples: Base Agreement
Cost Reimbursable, Cost Sharing Milestone Payment Method. (with not to exceed ceiling): Payment is contingent upon satisfactory progress toward completion of milestones as delineated in Project Agreement Task Assignment and acceptable cost share. Payment shall be made based on actual costs incurred in completing milestones up to the maximum amount allowable under the applicable Project AgreementTask Assignment, provided the designated AOR has verified compliance with the Statement of Work and accomplishment of the stated effort. Per (ii) below, either a Status Report identifying any associated technical tasks and the progress toward completion of each milestone, a Deliverable Report, or a Milestone Report is required concurrent with the invoice. An acceptable invoice for reimbursable payment is one that (on the invoice or on the attached Status, Deliverable, or Milestone Report in accordance with each Project AgreementTask Assignment):
(i) contains the date of invoice and the Base VLC Project Agreement number and Project Agreement Task Assignment number;
(ii) identifies any associated technical milestones and the progress toward completion of each milestone;
(iii) includes a report of the cost share expended towards the accomplishment of the SOW tasks and/or milestones. This cost share report may be attached to the invoice if contractor practices make inclusion of such information on the invoice itself impractical. If the cost share report is separate from the invoice, it must be signed by an authorized representative. This cost share report must contain a breakout of the cost share by cost element similar to the level of detail required on the invoice and any in-kind contributions. The preferred method of reporting cost share is to provide an invoice for actual cost incurred with a value for the cost shared amount and the value to be reimbursed by the Government through the CMF;actual
(iv) includes a description of supplies and services, labor costs, subcontractor costs, material costs, travel costs, other direct costs, and extended totals; ;
(v) indicates the current period and cumulative man-hours and costs incurred through the period indicated on the invoice; and
(vi) contains the following certification statement:
Appears in 1 contract
Samples: Project Agreement