Crores. The said additional fees/damages shall be levied on a pro-rata basis subject to a maximum of 100% (one hundred percent) of the amount for a delay in the completion of Project by 365 days.
Appears in 6 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Crores. The said additional fees/damages shall be levied on a pro-pro- rata basis subject to a maximum of 100% (one hundred percent) of the amount of Annual Concession Fee for a delay in the completion of Project by 365 days.
Appears in 3 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Crores. The said additional fees/damages shall be levied on a pro-rata basis subject to a maximum of 100% (one hundred percent) of the amount of Annual Concession Fee for a delay in the completion of Project by 365 days.
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Crores. The said additional fees/damages shall be levied on a pro-rata prorata basis subject to a maximum of 100% (one hundred percent) of the amount of Rs. 2.00 Crores for a delay in the completion of construction of Project by within 365 daysdays of scheduled completion date.
Appears in 1 contract
Samples: Concession Agreement
Crores. The said additional fees/damages shall be levied on a pro-rata prorate basis subject to a maximum of 100% (one hundred percent) of the amount of Rs. 2.00 Crores for a delay in the completion of construction of Project by within 365 daysdays of scheduled completion date.
Appears in 1 contract
Samples: Concession Agreement
Crores. The said additional fees/damages shall be levied on a pro-rata prorata basis subject to a maximum of 100% (one hundred percent) of the amount of Rs. 5.00 Crores for a delay in the completion of construction of Project by within 365 daysdays of scheduled completion date.
Appears in 1 contract
Samples: Concession Agreement