Common use of Damages for BPDB Delay Clause in Contracts

Damages for BPDB Delay. Should BPDB defer any Commercial Operation Test beyond ten (10) Days form the date on which the tests were originally scheduled pursuant to Section 7.1.1 (b) and such failure results in a delay in the Commercial Operations Date, then the Required Commercial Operations Date shall be extended on a Day-for-Day basis by the number of Days that the testing was deferred (such number of Days to be hereinafter referred to as “the Testing Delay Duration”).

Appears in 4 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

AutoNDA by SimpleDocs

Damages for BPDB Delay. (a) Should BPDB defer any Commercial Operation Operations Test beyond ten (10) Days form from the date on which the tests were originally scheduled pursuant to Section 7.1.1 (b) and such failure results in a delay in the then-prevailing Scheduled Commercial Operations Date, then either Party may, by notice to the Required Commercial Operations Date shall be extended on a Day-for-Day basis by other Party, require the number formation of Days the Testing and Commissioning Committee and, provided that the testing was deferred (such number of Days to be hereinafter referred to as “the Testing Delay Duration”).Certification Date has occurred:

Appears in 4 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

AutoNDA by SimpleDocs

Damages for BPDB Delay. Should (a) For reasons not caused by PGCB, should BPDB defer any Commercial Operation Operations Test beyond ten (10) Days form from the date on which the tests were originally scheduled pursuant to Section 7.1.1 (b) and such failure results in a delay in the then-prevailing Scheduled Commercial Operations Date, then either Party may, by notice to the Required Commercial Operations Date shall be extended on a Day-for-Day basis by other Party, require the number formation of Days the Testing and Commissioning Committee and, provided that the testing was deferred (such number of Days to be hereinafter referred to as “the Testing Delay Duration”).Certification Date has occurred:

Appears in 1 contract

Samples: Power Purchase Agreement