Electrical Interconnection. Engineer, design, construct and commission any interconnection facilities needed beyond the generation step up transformer as further described in Exhibit A (“Owner’s Interconnection Facilities”).
Electrical Interconnection. No later than [ ], Seller shall have entered into a [Large/Small/Rule 21/Native Balancing Authority] Generator Interconnection Agreement [For Projects located outside of the CAISO: along with any supplemental arrangements with the CAISO as an affected system owner] providing for the construction of the Electrical Interconnection Upgrades necessary to maintain the “[Full Capacity] [Energy Only] Deliverability Status” (as defined in the CAISO Tariff) of the Project and setting forth:
Electrical Interconnection. No later than [_______________], Seller shall have entered into a [Large/Small] Generator Interconnection Agreement providing for the construction of the Electrical Interconnection Upgrades necessary to maintain the “[Full Capacity] [Energy Only] Deliverability Status” (as defined in the CAISO Tariff) of the Project and setting forth: an estimated in-service interconnection date for the “Participating TO’s Interconnection Facilities,” the “Network Upgrades,” and the “Distribution Upgrades” (as each term is defined in the CAISO Tariff) of no later than [______________] months after Seller provides the Participating Transmission Owner with the appropriate security and written authorization to proceed under its [Large/Small] Generator Interconnection Agreement for the Project, a refundable cost for “Network Upgrades” (as defined in the CAISO Tariff) that Seller would be obligated to pay and would be entitled to reimbursement from the CAISO, a Participating Transmission Owner, or any other affected transmission provider as provided thereunder not exceeding $[____________], and [Note: Seller may propose additional provisions whereby Seller can satisfy this Condition Precedent by buying down the Network Upgrade costs that exceed the foregoing cost cap in a manner that is mutually acceptable to the Parties.] a nonrefundable cost that Seller would be obligated to pay thereunder not exceeding $[______________] (or such greater amount as Seller may approve, in its sole discretion).
Electrical Interconnection. The evacuation of electric power to be generated by the Facility, will be through Chandpur 132/33 kV Grid Substation, Chandpur, Bangladesh. The proposed power plant will be connected to the Chandpur 132/33 kV Grid Substation, Chandpur by a single ckt 132 kV (O/H or U/G, as required) line (Interconnection line) from proposed power plant. This interconnection line will be implemented by the Project Company at its own cost and responsibility. The Company shall be responsible to maintain, operate and repair (including any replacement of the equipment) this interconnection line at its own cost and responsibility during the Term of the Power Purchase Agreement. The Sponsor will also arrange necessary right of way for constructing Electrical Interconnection from its power plant to PGCB’s substation. In addition to that the Project Sponsor will install, operate & maintain separate 132 kV synchronizing breaker for its machine at the high voltage side of step-up Transformer and also construct the connecting lines for connection. The required 132 kV GIS bay extension including circuit breaker, CT, PT, panel etc. of Chandpur 132/33 kV Grid Substation, Chandpur will be implemented by the Project Sponsor at its own cost and responsibility. The Sponsor will arrange necessary land for construction of 132 kV bay (if required). The evacuation system will be completed in consultation and approval of Power Grid Company of Bangladesh (PGCB). The Facility will be constructed at a land near to Chandpur 132/33 kV Grid Substation, Chandpur to be arranged by the Company at its own cost. Required development, filling upto final elevation, leveling, compacting etc. of the land will be the responsibility of the Company. The access road to the Site will also be the responsibility of the Company. The Company shall also generate matching MVARh corresponding to maintain the power factor 0.85 lagging, so that there is no adverse effect on the Grid System. If needed to satisfy the requirement in this Section 3.2, the Company, to enhance the Reactive Power capability of the Facility, at its own cost and expense, shall install a static VAR compensator (SVC), a static synchronous compensator (SATCOM), and/or other reactive support equipment at the Facility. Due to the connection of the Facility to the electrical system, if any impact on grid happens (Like: Low voltage problem, Stability problem, Frequency problem etc.) which needs to be sort out and completion of necessary measures to mitigate...
Electrical Interconnection. The evacuation of electric power to be generated by the Facility will be through Netrokona 132/33 KV Grid Substation. The proposed power plant will be connected to the 132 kV bus of Netrokona 132/33 KV Grid Substation by a 132 kV single circuit overhead or underground line (Interconnection line). This said interconnection line from the Facility to Netrokona 132/33 KV Grid Substation will be implemented by the company at its own cost including arrangement of necessary right of way. The company will also construct necessary 132kV bay (GIS or AIS) at Netrokona 132/33 KV Grid Substation including obtaining of necessary land with its own responsibility. In addition to that the sponsor will install, operate and maintain separate 132 kV interfacing breaker for its machine at the high voltage side of step-up Transformer and also construct the connecting lines for connection. The required 132 kV bay extension including circuit breaker, CT, PT, LA, panel etc. of Netrokona 132/33 KV Grid Substation will be implemented by the Company at its own cost and responsibility. The EIF will be completed in consultation and approval of PGCB. The Company shall be responsible to maintain, operate and repair (including any replacement of the equipment) of the Electric Interconnection Facility ascribed in this Section at its own cost and responsibility during the Term of the this Agreement. The Company shall be capable to generate matching MVARh corresponding to maintain the power factor 0.85 lagging at delivery point, so that there is no adverse effect on the Grid System. To satisfy the aforesaid requirement, the company shall install required reactive support equipments at the facility in consultation with PGCB.
Electrical Interconnection. The evacuation of electric power to be generated by the Facility will be through 132/33kV Chuadanga 132/33 Substation, Chuadanga. The proposed power plant will be connected to the 132 kV bus of Chuadanga 132/33Grid Substation by a 132 kV single circuit overhead or underground line (Interconnection line). This said interconnection line from the Facility to Chuadanga substation will be implemented by the company at its own cost including arrangement of necessary right of way. The company will also construct necessary 132kV bay (GIS or AIS) at Chuadanga 132kV substation including obtaining of necessary land with its own responsibility. In addition to that the sponsor will install, operate and maintain separate 132 kV interfacing breaker for its machine at the high voltage side of step-up Transformer and also construct the connecting lines for connection. The required 132 kV bay extension including circuit breaker, CT, PT, LA, panel etc. of 132/33 kV Chuadanga Grid Substation will be implemented by the Company at its own cost and responsibility. The EIF will be completed in consultation and approval of PGCB. The Company shall be responsible to maintain, operate and repair (including any replacement of the equipment) of the Electric Interconnection Facility ascribed in this Section at its own cost and responsibility during the Term of this Agreement.
Electrical Interconnection. Owner shall arrange for the Utility's electrical interconnection facilities between the Electrical Interconnection Point and the Utility's transmission system to be constructed and made available for interconnection with the Facility at the Electrical Interconnection Point at least eight (8) months prior to the Guaranteed Provisional Acceptance Date (provided that Contractor has made the Facility available as reasonably required to permit such interconnection to have been made by such date).
Electrical Interconnection. Engineer, design, construct and commission Contractor’s Interconnection Facilities in accordance with the specifications and requirements of Georgia Power Company as transmission provider. Additionally, Contractor shall (i) prior to the Substantial Completion Date, provide Owner with all required drawings, information, documents, specifications and progress reports as required by Owner and (ii) prior to the Substantial Completion Date, perform any testing and subsequent modifications as required by Owner. Portions of this Exhibit, indicated by the xxxx “[***],” were omitted and have been filed separately with the Securities and Exchange Commission pursuant to the Registrant’s application requesting confidential treatment pursuant to Rule 24b-2 of the Securities Exchange Act of 1934, as amended.
Electrical Interconnection. Facilities BPDB shall, upon request by the Company which shall not be made earlier than one hundred and twenty (120) Days after the Project Effective Date, grant to the Company easements and rights of way as necessary to install, operate, maintain the Electrical Interconnection Facilities, tele-metering and telecommunication facilities and any other facilities that may be required for connecting the Facility to the interconnection and transmission facilities.
Electrical Interconnection. The evacuation of electric power to be generated by the Facility will be through 132/33kV Bhaluka 132/33 Substation, Bhaluka. The proposed power plant will be connected to the 132 kV bus of Xxxxxxx 000/00Xxxx Substation by a 132 kV single circuit overhead or underground line (Interconnection line). This said interconnection line from the Facility to Bhaluka substation will be implemented by the company at its own cost including arrangement of necessary right of way. The company will also construct necessary 132kV bay (GIS or AIS) at Bhaluka 132kV substation including obtaining of necessary land with its own responsibility. In addition to that the sponsor will install, operate and maintain separate 132 kV interfacing breaker for its machine at the high voltage side of step-up Transformer and also construct the connecting lines for connection. The required 132 kV bay extension including circuit breaker, CT, PT, LA, panel etc. of 132/33 kV Bhaluka Grid Substation will be implemented by the Company at its own cost and responsibility. The EIF will be completed in consultation and approval of PGCB. The Company shall be responsible to maintain, operate and repair (including any replacement of the equipment) of the Electric Interconnection Facility ascribed in this Section at its own cost and responsibility during the Term of this Agreement.