Common use of DATE FOR SUBSTANTIAL COMPLETION Clause in Contracts

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 Days – beginning on the date indicated in the Notice to Proceed.

Appears in 9 contracts

Samples: a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov

AutoNDA by SimpleDocs

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 Days – beginning on the date indicated in the Notice to Proceed.Proceed or Order to Work

Appears in 4 contracts

Samples: Supply and Service Agreement, Supply and Service Agreement, a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 1825 Days – beginning on the date indicated in the Notice to ProceedProceed or Order to Work.

Appears in 2 contracts

Samples: a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 Days beginning on the date indicated in the Notice to Proceed.Proceed or Order to Work

Appears in 2 contracts

Samples: www.bidnet.com, a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 1050 Days – beginning on the date indicated in the Notice to Proceed.Proceed or Order to Work

Appears in 2 contracts

Samples: a856-cityrecord.nyc.gov, movablebridgeresource.com

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 Days – beginning on the date indicated in the Notice to Proceed.

Appears in 2 contracts

Samples: Furnish and Install Agreement, a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 180 Consecutive Calendar Days – beginning on the date indicated in the Notice to ProceedProceed or Order to Work.

Appears in 1 contract

Samples: a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 92 Days – beginning on the date indicated in the Notice to ProceedProceed or Order to Work.

Appears in 1 contract

Samples: a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 1458 Days – beginning on the date indicated in the Notice to ProceedProceed or Order to Work.

Appears in 1 contract

Samples: movablebridgeresource.com

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 780 Consecutive Calendar Days – beginning on the date indicated in the Notice to ProceedProceed or Order to Work.

Appears in 1 contract

Samples: a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 Days 365 – beginning on the date indicated in the Notice to Proceed.

Appears in 1 contract

Samples: a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 1573 Days – beginning on the date indicated in the Notice to Proceed.Proceed or Order to Work

Appears in 1 contract

Samples: a856-cityrecord.nyc.gov

AutoNDA by SimpleDocs

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 1095 Days – beginning on the date indicated in the Notice to Proceed.Proceed or Order to Work

Appears in 1 contract

Samples: a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 1095 Days – beginning on the date indicated in the Notice to ProceedProceed or Order to Work.

Appears in 1 contract

Samples: a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 1,095 Days – beginning on the date indicated in the Notice to Proceed.Proceed or Order to Work

Appears in 1 contract

Samples: a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 915 Days – beginning on the date indicated in the Notice to ProceedProceed or Order to Work.

Appears in 1 contract

Samples: a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 1855 Days – beginning on the date indicated in the Notice to ProceedProceed or Order to Work.

Appears in 1 contract

Samples: a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 549 Days – beginning on the date indicated in the Notice to Proceed.

Appears in 1 contract

Samples: a856-cityrecord.nyc.gov

DATE FOR SUBSTANTIAL COMPLETION. The Contractor shall substantially complete the Work in the number of Days indicated to the right. 730 270 Days – beginning on the date indicated in the Notice to Proceed.Proceed or Order to Work

Appears in 1 contract

Samples: www.bidnet.com

Time is Money Join Law Insider Premium to draft better contracts faster.