Deficiencies in the Surplus Interconnection Service Request. If Surplus Interconnection Customer fails to provide a completed Surplus Interconnection request to Transmission Provider, Transmission Provider will notify Surplus Interconnection Customer of the deficiencies and Surplus Interconnection Customer will have 15 Business Days, from the date on the Notice, to cure any deficiencies. Failure to timely cure all deficiencies will result in a deemed withdrawal of the Surplus Interconnection Service Request.
Appears in 4 contracts
Samples: Standard Large Generator Interconnection Procedures (Lgip), Settlement Agreement, Standard Large Generator Interconnection Agreement (Lgia)