Common use of Delays during construction Clause in Contracts

Delays during construction. Without prejudice to the provisions of Clause 12.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal is not likely to be achieved by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 21 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

AutoNDA by SimpleDocs

Delays during construction. Without prejudice to the provisions of Clause 12.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal is not likely to be achieved completed by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 16 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Delays during construction. from Without prejudice to the provisions of Clause 12.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal is not likely to be achieved by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 12 contracts

Samples: Draft Concession Agreement, Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.212.3, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal Rail System is not likely to be achieved completed by the Scheduled Completion Date, it shall notify the Concessionaire and MOR to this effect, and the Concessionaire shall, within 15 14 (fifteen) days of such notice, by a communication inform the Independent Engineer and MOR in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion DateCOD.

Appears in 4 contracts

Samples: Model Agreement, Model Agreement, Model Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.212.5.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal Port is not likely to be achieved completed by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion DateCOD.

Appears in 3 contracts

Samples: Draft Concession Agreement, Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.212.3.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal Rail System is not likely to be achieved completed by the Scheduled Completion Date, it shall notify the Concessionaire and MOR to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer and MOR in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion DateCOD.

Appears in 3 contracts

Samples: Model Agreement, Model Agreement, Model Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.212.3.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal commissioning of XXX Ropeway is not likely to be achieved by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 3 contracts

Samples: Model Concession Agreement, Model Concession Agreement, Model Concession Agreement

Delays during construction. β€Œ Without prejudice to the provisions of Clause 12.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal Project Completion is not likely to be achieved by the Scheduled Project Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 3 contracts

Samples: Draft Concession Agreement, Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.27.3.2, if the Concessionaire Developer does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal Rail System is not likely to be achieved completed by the Scheduled Completion Date, it shall notify the Concessionaire Developer and MOR to this effect, and the Concessionaire Developer shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer and MOR in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion DateCOD.

Appears in 2 contracts

Samples: Model Agreement, Model Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal Six-Laning is not likely to be achieved by the Scheduled Completion Six-Laning Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal Heliport is not likely to be achieved completed by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal Rail System is not likely to be achieved completed by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal Two- Laning is not likely to be achieved by the Scheduled Completion Two-Laning Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Samples: Concession Agreement

AutoNDA by SimpleDocs

Delays during construction. Without prejudice to the provisions of Clause 12.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal it is not likely to be achieved by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal Project Completion is not likely to be achieved by the Scheduled Project Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Samples: Draft Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.212.3.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal Transmission System is not likely to be achieved completed by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Samples: Transmission Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal Two-Laning is not likely to be achieved by the Scheduled Completion Two-Laning Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal completion is not likely to be achieved by the Scheduled Construction Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.212.3.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal is HealthcareNetworkis not likely to be achieved completed by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Samples: Substitution Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.212.2.1, if the Concessionaire Developer does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that completion of the Bus Terminal construction work is not likely to be achieved by the Scheduled Completion Date, it shall notify the Concessionaire Developer to this effect, and the Concessionaire Developer shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Samples: Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Bus Terminal Two- Laning is not likely to be achieved by the Scheduled Completion Two - Laning Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Samples: Concession Agreement

Time is Money Join Law Insider Premium to draft better contracts faster.