Change of Scope Order Sample Clauses

Change of Scope Order. 14.3.1 The Concessionaire shall, within 15 days of receipt of the Change of Scope Notice, provide to the Independent Engineer such information as is necessary and reasonable together with the preliminary documentation and details, including the calculations, where necessary, in support of the following: (a) the impact which the Change of Scope is likely to have on the Construction Works or on the O&M in the event the Change of Scope is in respect of the Construction Period or in the O&M Period respectively; (b) the budgeted estimate of the Additional Cost to be incurred by the Concessionaire for implementing the Change of Scope; (c) the estimated additional time (number of days) that the Concessionaire would require to achieve Construction Completion consequent to the Change of Scope and any delay, if any, in the Final Expiry Date; (d) any extensions in the timelines and relaxation of the obligations/dutiesof the Concessionaire under this Agreement resulting from the Change of Scope. 14.3.2 The Independent Engineer shall after reviewing the information, documentation and the budgeted estimate of the Additional Cost submitted by the Concessionaire under this Section 14.3 (Change of Scope Order), settle the rates, approve the designs and forward the budgeted estimates of the Additional Cost, as duly certified by the (Independent Engineer and the Independent Auditor) in consultation with the Concessionaire, to the GoS. Notwithstanding anything to the contrary set out herein, in the event the Concessionaire disagrees with the determinations of the Independent Engineer, the Concessionaire shall not be obligated to implement the Change of Scope. 14.3.3 The GoS may, within a period of fifteen (15) days from the date of receipt of such statement, issue an order in writing to the Concessionaire, through the Independent Engineer instructing the Concessionaire to affect the Change of Scope (the “Change of Scope Order”) provided however (subject to Section 14.3.5); the final Additional Cost shall be computed by taking into account the actual work executed by the Concessionaire, as measured and certified by the Independent Engineer, at the rates agreed in the Change of Xxxxx Order.
AutoNDA by SimpleDocs
Change of Scope Order. Save for the advance payment under Section 16.3.5(a), the Authority shall progressively pay the Additional Cost in accordance with sub-section 16.3.5 of this Section 16.3 (
Change of Scope Order or any other modality as mutually agreed between the Parties, only upon receiving a certificate from the Independent Engineer confirming that the Concessionaire has completed the relevant milestone(s) of the works in accordance with the Change of Scope Order.

Related to Change of Scope Order

  • Change of Scope (i) The Authority may, notwithstanding anything to the contrary contained in this Agreement, require the Contractor to make modifications/ alterations to the Works (“Change of Scope”) within a period of six months counted from the Appointed Date. Upon the Authority making its intention known to the Contractor for the specific Change of Scope, be it positive or negative, the Contractor shall submit his proposal for the said Change of Scope involving additional cost or reduction in cost. Any such Change of Scope shall be made and valued in accordance with the provisions of this Article 13. (ii) Provided that any such Change of Scope, excluding major structures (e.g. Major Bridge/ ROB/ RUB/ Flyover/ elevated road of more than 50 m length) may be required and agreed to be executed between the parties beyond the period of six months of the Appointed Date but before expiry of 50% of the original Scheduled Construction Period of the Project Highway, subject to the condition that it shall not entail any claims (e.g. Extension of Time/ Prolongation related claims), against the Authority. (iii) The Change of Scope shall mean the following: (a) change in specifications of any item of Works; (b) omission of any work from the Scope of the Project except under Clause 8.3 (iii); provided that, subject to Clause 13.5, the Authority shall not omit any Work under this Clause in order to get it executed by any other authority; and / or (c) any additional Work, Plant, Materials or services which are not included in the Scope of the Project, including any associated Tests on completion of construction.

  • Change of Schedule (a) (applicable to full-time employees only) Where an employee's schedule is changed by the Hospital with less than twenty-four (24) hours notice, she shall receive time and one-half (1½) of her regular straight time hourly rate for all hours worked on her next shift. (b) (applicable to regular part-time employees only) Where a regular part-time employee's scheduled shift is cancelled by the Hospital with less than twelve (12) hours notice, she shall receive time and one-half (1½) of her regular straight time hourly rate for all hours worked on her next shift. (The following clause related to No Pyramiding will be incorporated into all collective agreements:)

  • Procedure for Change of Scope 16.2.1 In the event of the Authority determining that a Change of Scope is necessary, it shall issue to the Concessionaire a notice specifying in reasonable detail the works and services contemplated thereunder (the “Change of Scope Notice”). 16.2.2 Upon receipt of a Change of Scope Notice, the Concessionaire shall, with due diligence, provide to the Authority such information as is necessary, together with preliminary Documentation in support of: (a) the impact, if any, which the Change of Scope is likely to have on the Project Completion Schedule if the works or services are required to be carried out during the Construction Period; and (b) the options for implementing the proposed Change of Scope and the effect, if any, each such option would have on the costs and time thereof, including a detailed breakdown by work classifications specifying the material and labour costs calculated in accordance with the schedule of rates applicable to the works assigned by the Authority to its contractors, along with the proposed premium/discount on such rates; provided that the cost incurred by the Concessionaire in providing such information shall be reimbursed by the Authority to the extent such cost is certified by the Independent Engineer as reasonable. 16.2.3 Upon receipt of information set forth in Clause 16.2.2, if the Authority decides to proceed with the Change of Scope, it shall convey its preferred option to the Concessionaire, and the Parties shall, with assistance of the Independent Engineer, thereupon make good faith efforts to agree upon the time and costs for implementation thereof. Upon reaching an agreement, the Authority shall issue an order (the “Change of Scope Order”) requiring the Concessionaire to proceed with the performance thereof. In the event that the Parties are unable to agree, the Authority may, by issuing a Change of Scope Order, require the Concessionaire to proceed with the performance thereof pending resolution of the Dispute, or carry out the works in accordance with Clause 16.5. 16.2.4 The provisions of this Agreement, insofar as they relate to Construction Works and Tests, shall apply mutatis mutandis to the works undertaken by the Concessionaire under this Article 16.

  • Change of Shift (a) Where the regular day, afternoon or night shift of an employee is to be changed, the employee shall be given forty-eight (48) hours’ notice of such change. 11.01 (b) If the employee is given less than forty-eight (48) hours’ notice of such shift change, he shall be paid at the rate of time and one-half (1 ½) for the first changed shift worked.

  • Change in Scope of Work Any change in the scope of the Work, method of performance, nature of materials or price thereof, or any other matter materially affecting the performance or nature of the Work shall not be paid for or accepted unless such change, addition, or deletion is approved in advance and in writing by a valid change order executed by the District. Contractor specifically understands, acknowledges, and agrees that the District shall have the right to request any alterations, deviations, reductions, or additions to the Project or Work, and the cost thereof shall be added to or deducted from the amount of the Contract Price by fair and reasonable valuations. Contractor also agrees to provide the District with all information requested to substantiate the cost of the change order and to inform the District whether the Work will be done by the Contractor or a subcontractor. In addition to any other information requested, Contractor shall submit, prior to approval of the change order, its request for a time extension (if any), as well as all information necessary to substantiate its belief that such change will delay the completion of the Work. If Contractor fails to submit its request for a time extension or the necessary supporting information, it shall be deemed to have waived its right to request such extension.

  • Change Order The Change Order is then submitted to the Project Manager who immediately processes the CO with OPC as required by Bulletin 3.5 and BGS’ Contracting Plan.

  • Payment for Change of Scope Payment for Change of Scope shall be made in accordance with the payment schedule specified in the Change of Scope Order.

  • Attachment A, Scope of Services The scope of services is amended as follows:

  • CHANGE OF T-PIN The Account Holder may change his T-PIN from time to time in accordance with the Bank’s prescribed procedure then prevailing. The Bank shall be entitled, in its reasonable discretion but without liability and without giving any reason, to reject any selection made by the Account Holder as his substituted T-PIN; if the Bank so approves, such substituted T-PIN, shall take effect from the time of receipt by the Bank of such instructions from the Account Holder. The Account Holder shall take all steps not to select such numbers as a substitute T-PIN which may easily be ascertained or otherwise facilitate fraud or forgery.

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).