Common use of Delays during construction Clause in Contracts

Delays during construction. If the Concessionaire does not achieve any of the Project Milestone or the Independent Monitor[s] shall have reasonably determined that the rate of progress of Construction Works is such that Project is not likely to be achieved by the Project Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Monitor[s] in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Project Completion Date as the case may be.

Appears in 4 contracts

Samples: Public Private Partnership Agreement, Public Private Partnership Agreement, Public Private Partnership Agreement

AutoNDA by SimpleDocs

Delays during construction. If the Concessionaire does not achieve any of the Project Milestone Milestones or the Independent Monitor[s] Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achieved by the Project Completion Dateachieved, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Monitor[s] Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Scheduled Completion Date indicated in Project Completion Date as the case may beSchedule.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Delays during construction. 13.4.1 If the Concessionaire does not achieve any of the Project Milestone Milestones or the Independent Monitor[s] shall Construction Supervisorshall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achieved by the Project Completion Dateachieved, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Monitor[s] Construction Supervisor in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Scheduled Completion Date indicated in Project Completion Date as the case may beSchedule.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Delays during construction. If the Concessionaire does not achieve any of the Project Milestone project milestones or the Independent Monitor[s] Supervision Committee shall have reasonably determined that the rate of progress of Construction Works ConstructionWorks is such that Project is not likely to be achieved completed by the Project Scheduled Completion Date, Date it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Monitor[s] Supervision Committee in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Project theProject Completion Date as the case may beDate.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. If the Concessionaire does not achieve any of the Project Milestone or the Independent Monitor[s] shall Engineer have reasonably determined that the rate of progress of Construction Works is such that Project is not likely to be achieved by the Project Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Monitor[s] Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Project Completion Date as the case may be.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. If the Concessionaire Concessionaire, does not achieve any of the Project Milestone Milestones or the Independent Monitor[s] Consultant shall have reasonably determined that the rate of progress of Construction Works works is such that Project is not likely to be achieved by the Scheduled Project Completion Date, it shall notify the Concessionaire to this effect, effect and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Monitor[s] Consultant in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Project Completion Date as the case may beDate.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. If the Concessionaire does not achieve any of the Project Milestone Milestones or the Independent Monitor[s] Engineer shall have reasonably determined that the rate of progress of or Construction Works is such that Project [Four-Laning] is not likely to be achieved by the Project Completion Schedules Four-Laning Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (( fifteen) days of such noticenotice , by a communication inform the Independent Monitor[s] Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Project Completion Date as the case may beDate.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. If the Concessionaire does not achieve any of the Project Milestone Milestones or the Independent Monitor[s] Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Project completion is not likely to be achieved by the Project Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Monitor[s] Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Project Completion Date as the case may beDate.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. If the Concessionaire does not achieve any of the Project Milestone Milestones or the Independent Monitor[s] Engineer shall have reasonably determined that the rate of progress of or Construction Works is such that Project Four-Laning is not likely to be achieved by the Project Completion Scheduled Four-Laning Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (( fifteen) days of such noticenotice , by a communication inform the Independent Monitor[s] Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Project Completion Date as the case may beDate.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. If the Concessionaire does not achieve any of the Project Milestone or the Independent Monitor[s] Expert shall have reasonably determined that the rate of progress of Construction Works is such that Project is not likely to be achieved completed by the Project Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Monitor[s] Expert in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Project Completion Date as the case may be.

Appears in 1 contract

Samples: Concession Agreement

AutoNDA by SimpleDocs

Delays during construction. 13.4.1 If the Concessionaire does not achieve any of the Project Milestone Milestones or the Independent Monitor[s] Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achieved by the Project Completion Dateachieved, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Monitor[s] Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Scheduled Completion Date indicated in Project Completion Date as the case may beSchedule.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. β€Œ If the Concessionaire does not achieve any of the Project Milestone Milestones or the Independent Monitor[s] Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achieved by the Project Completion Dateachieved, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Monitor[s] Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Scheduled Completion Date indicated in Project Completion Date as the case may beSchedule.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. If the Concessionaire does not achieve any of the Project Milestone Milestones or the Independent Monitor[s] Engineer-in-charge of the Authority shall have reasonably determined that the rate of progress of Construction Works is such that the Project is not likely to be achieved completed by the Project Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Monitor[s] Engineer-in- charge in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Project Completion Date as the case may beDate.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. If the Concessionaire does not achieve any of the Project Milestone Milestones or the Independent Monitor[s] Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Project is not likely to be achieved by the Project Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Monitor[s] Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Project Completion Date as the case may beDate.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. If the Concessionaire does not achieve any of the Project Milestone project milestones or the Independent Monitor[s] Supervision Committee shall have reasonably determined that the rate of progress of Construction Works is such that Project is not likely to be achieved completed by the Project Scheduled Completion Date or Scheduled Phase Completion Date, as the case may be, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Monitor[s] Supervision Committee in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Project Completion Date as the case may beDate.

Appears in 1 contract

Samples: Concession Agreement