Delays during construction. Without prejudice to the provisions of Clause 14.1, if the rate of progress of Development Works is such that the Development Obligation is not likely to be completed within the time period stipulated, the Concessionaire shall inform the Independent Engineer and the Authority at fortnight intervals, in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Operation Date.
Appears in 7 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Delays during construction. Without prejudice to the provisions of Clause 14.1Article 12.1, if the rate of progress of Development Works is such that the Minimum Development Obligation is not likely to be completed within the time period stipulated, the Concessionaire shall inform the Independent Engineer Expert and the Authority at fortnight intervals, in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Operation DateProject COD.
Appears in 6 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Delays during construction. Without prejudice to the provisions of Clause 14.112.1, if the rate of progress of Development Works is such that the Mandatory Development Obligation is not likely to be completed within the time period stipulated, the Concessionaire shall inform the Independent Engineer and the Authority Expert at fortnight intervals, in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Operation DateProject COD.
Appears in 1 contract
Samples: Concession Agreement
Delays during construction. Without prejudice to the provisions of Clause 14.1Article 12.1, if the rate of progress of Development Works is such that the Minimum Development Obligation is not likely to be completed within the time period stipulated, the Concessionaire shall inform the Independent Engineer Expert and the Authority at fortnight intervals, in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Operation DateCOD of the relevant Phase.
Appears in 1 contract
Samples: Concession Agreement
Delays during construction. Without prejudice to the provisions of Clause 14.1Article 12.1, if the rate of progress of Development Works is such that the Minimum Development Obligation is not likely to be completed within the time period stipulated, the Concessionaire shall inform the Independent Engineer Expert and the Authority at fortnight intervals, in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Operation Date[Project COD]24.
Appears in 1 contract
Samples: Concession Agreement