Common use of Delays during construction Clause in Contracts

Delays during construction. Without prejudice to the provisions of Clause 12.5.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Port is not likely to be completed by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve COD.

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

AutoNDA by SimpleDocs

Delays during construction. Without prejudice to the provisions of Clause 12.5.212.3.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Port Two-Laning Plus is not likely to be completed achieved by the Scheduled Completion Two-Laning Plus Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve COD.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.5.212.4.(b), if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Port Project is not likely to be completed by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve COD.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.5.212.3.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Port Two-Laning is not likely to be completed achieved by the Scheduled Completion Two-Laning Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve COD.

Appears in 1 contract

Samples: Concession Agreement

AutoNDA by SimpleDocs

Delays during construction. Without prejudice to the provisions of Clause 12.5.212.4.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Port it is not likely to be completed achieved by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve CODthe Project Completion Date.

Appears in 1 contract

Samples: Model Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 12.5.212.3.2, if the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer Expert shall have reasonably determined that the rate of progress of Construction Works is such that the Port Storage Facility is not likely to be completed by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer Expert in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve COD.

Appears in 1 contract

Samples: Concession Agreement