Delays during construction. Without prejudice to the provisions of Clause19.4.2, if the Mine Developer and Operator does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works and installation of Equipment is delayed, it shall notify the Mine Developer and Operator to this effect, and the Mine Developer and Operator shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve such Project Milestones.
Appears in 2 contracts
Samples: Coal Mining Agreement, Coal Mining Agreement
Delays during construction. Without prejudice to the provisions of Clause19.4.2Schedule-G, if the Mine Developer and Operator does not achieve any of the Project Milestones or the Independent Engineer shall have has reasonably determined that the rate of progress of Construction Works and installation of Equipment is delayed, it shall notify the Mine Developer and Operator to this effect, and the Mine Developer and Operator shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve such Project Milestones.
Appears in 1 contract
Samples: Coal Mining Agreement
Delays during construction. Without prejudice to the provisions of Clause19.4.2Clause 12.5.2, if the Mine Developer and Operator does not achieve any of the Project Milestones or the Independent Engineer shall have in chargehas reasonably determined that the rate of progress of Construction Works and installation installation/ deployment of Equipment is delayed, it shall notify the Mine Developer and Operator to this effect, and the Mine Developer and Operator shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in charge in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve such Project Milestones.
Appears in 1 contract
Samples: Contract Agreement
Delays during construction. Without prejudice to the provisions of Clause19.4.2Clause 12.4.2, if the Mine Developer and Operator does not achieve any of the Project Milestones or the Independent Engineer shall have in charge has reasonably determined that the rate of progress of Construction Works and installation installation/ deployment of Equipment is delayed, it shall notify the Mine Developer and Operator to this effect, and the Mine Developer and Operator shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in charge in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve such Project Milestones.
Appears in 1 contract
Samples: Model Contract Agreement
Delays during construction. Without prejudice to the provisions of Clause19.4.2Clause 12.5.2, if the Mine Developer and Operator does not achieve any of the Project Milestones or the Independent Engineer shall have in charge has reasonably determined that the rate of progress of Construction Works and installation installation/ deployment of Equipment is delayed, it shall notify the Mine Developer and Operator to this effect, and the Mine Developer and Operator shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in charge in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve such Project Milestones.
Appears in 1 contract
Samples: Contract Agreement
Delays during construction. Without prejudice to the provisions of Clause19.4.2Clause 12.4.2, if the Mine Developer and Operator does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works and installation of Equipment is delayed, it shall notify the Mine Developer and Operator to this effect, and the Mine Developer and Operator shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve such Project Milestones.
Appears in 1 contract
Samples: Coal Mining Agreement