Common use of Delays during construction Clause in Contracts

Delays during construction. Without prejudice to the provisions of Clause 8.3, if Seller does not achieve any of the Project Milestones set forth in Schedule F or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Facility is not likely to be completed by the SCOD, it shall notify Seller and CEB to this effect, and Seller shall, within 15 (fifteen) days of such notice, by a communication through a formal letter inform the Independent Engineer and CEB in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Commercial Operation Date.

Appears in 6 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Energy Supply and Purchase Agreement