Common use of Delays during construction Clause in Contracts

Delays during construction. If the Concessionaire does not achieve any of the project milestones or the Supervision Committee shall have reasonably determined that the rate of progress of Construction Works is such that Project is not likely to be completed by the Scheduled Completion Date or Scheduled Phase Completion Date, as the case may be, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Supervision Committee in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Samples: Concession Agreement

AutoNDA by SimpleDocs

Delays during construction. If the Concessionaire does not achieve any of the project milestones Project Milestones or the Supervision Committee Engineer-in-charge of the Authority shall have reasonably determined that the rate of progress of Construction Works is such that the Project is not likely to be completed by the Scheduled Completion Date or Scheduled Phase Completion Date, as the case may be, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Supervision Committee Engineer-in- charge in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Samples: Concession Agreement

Delays during construction. If 12.9.1 In the event the Concessionaire does not fails to achieve any of the project milestones Project Milestones or the Supervision Committee Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Project is cannot likely to be completed by achieve Project Completion on or before the Scheduled Project Completion Date or Scheduled Phase Completion Date, as then the case may be, it Independent Engineer shall notify issue a notice to the Concessionaire to this effect, effect and the Concessionaire shall, within 15 (fifteen) 7 days of such notice, by a communication notice inform the Supervision Committee Independent Engineer in reasonable detail about the steps it the Concessionaire proposes to take undertake to expedite progress and the period within which it shall achieve the Project Completion by the Scheduled Project Completion Date.

Appears in 1 contract

Samples: Concession Agreement

AutoNDA by SimpleDocs

Delays during construction. 13.4.1 If the Concessionaire does not achieve any of the project milestones Project Milestones or the Supervision Committee Authority shall have reasonably determined that the rate of progress of Construction Works is such that the Mandatory Project is and Mandatory Sports Infrastructure Project Facilities are not likely to be completed by the Scheduled Completion Date or Scheduled Phase Completion Date, as the case may be, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Supervision Committee Authority in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Scheduled Completion Date.

Appears in 1 contract

Samples: Draft Concession Agreement