Differing Site Condition Notice Sample Clauses

Differing Site Condition Notice. The Contractor shall provide written notice of a differing site condition within 10 calendar days of occurrence in accordance with additional information provided in FAR 52.236-4, Differing Site Condition.
AutoNDA by SimpleDocs
Differing Site Condition Notice. The Contractor shall provide written notice of a differing site condition within 10 days of occurrence following FAR 52.236-2, Differing Site Conditions.

Related to Differing Site Condition Notice

  • Differing Site Conditions (a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or (2) unknown physical conditions at the site(s), of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract. (b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. Work shall not proceed at the affected site, except at the Contractor’s risk, until the Contracting Officer has provided written instructions to the Contractor. If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, the Contractor shall file a claim in writing to the PHA within ten days after receipt of such instructions and, in any event, before proceeding with the work. An equitable adjustment in the contract price, the delivery schedule, or both shall be made under this clause and the contract modified in writing accordingly. (c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in (a) above for giving written notice may be extended by the Contracting Officer. (d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.

  • Site Conditions A. Existing Site Conditions: Information with respect to the site of the Work given in drawings or specifications has been obtained by County's representatives and is believed to be reasonably correct, but the County does not warrant either the completeness or accuracy of such information, and it is the responsibility of the Contractor to verify all such information.

  • SUSPENSIVE CONDITION i) The contract only becomes binding and enforceable once: a. the Parties have signed this contract and the PRODUCER has received a MEATCO confirmation letter stipulating the applicable xxxxxxxxx period and cattle quantity to be delivered to MEATCO; b. MEATCO agrees to provide a xxxxxxxxx allocation to the PRODUCER on a first come first served basis principle, and at the sole discretion of MEATCO; and c. the PRODUCER has provided, within 10 business days of MEATCO’s request, a guarantee or security for the payment of the maximum penalty capable of being imposed in terms of clause A. vi) above to the satisfaction of MEATCO.

  • SUSPENSIVE CONDITIONS 2.1 This entire AGREEMENT is subject to the registration of transfer of ownership of the PROPERTY to the EMPLOYER. In the event that the PROPERTY is not transferred within 6 (six) months from date of signing of this Agreement by the CONTRACTOR, the CONTRACTOR reserves the right to: 2.1.1 increase the CONTRACT SUM, based on the current prices for the building materials, and the CONTRACTOR shall notify the EMPLOYER in writing of such increased cost and the EMPLOYER may then, at his/her option, cancel this agreement by providing written notice of cancellation to the CONTRACTOR within 5 (five) DAYS of receiving written notice from the CONTRACTOR in respect of the increased cost. Should written notice of cancellation not be forthcoming within the aforesaid period, the CONTRACTOR and the EMPLOYER shall proceed with the AGREEMENT at the increased CONTRACT SUM and the EMPLOYER shall be obliged to pay the increase in the CONTRACT SUM to the CONTRACTOR within 21 (twenty one) DAYS of receiving written notice from the CONTRACTOR in respect of the increased cost; or 2.1.2 cancel this AGREEMENT and the parties shall have no claim of whatsoever nature against each other. 2.2 This AGREEMENT is subject further to the EMPLOYER being offered a loan to be secured by a mortgage bond over the PROPERTY and improvements in the amount reflected in Schedule B or such lesser amount as the EMPLOYER may accept, within 30 (thirty) DAYS of the date of the CONTRACTOR’s signature of this AGREEMENT, which period may be extended in the CONTRACTOR’s sole discretion. Should no amount be inserted in the relevant field in the Schedule B, then the suspensive condition contained in this clause will not apply. In the event that the suspensive condition contained in this clause is not fulfilled, this AGREEMENT will lapse and the parties shall have no claim of whatsoever nature against each other.

  • Termination Conditions Such license shall not be terminated or its exploitation enjoined, until and unless: (i) Hitachi has committed a material breach of its obligations under this IP License Agreement, Opto-Device has given written notice of such breach to Hitachi and such breach remains uncured after the Cure Period, or, in the case of a breach, which cannot be cured within such Cure Period, Hitachi has not instituted within such Cure Period steps necessary to remedy the default and/or thereafter has not diligently pursued the same to completion; or (ii) such a material breach is incurable. In the event the breach is a curable breach that cannot be cured within the Cure Period but with respect to which Hitachi has instituted steps necessary to remedy the default and is thereafter diligently pursuing such cure, both parties shall negotiate to determine whether further pursuit of such cure is reasonable. If the parties cannot agree on a resolution in such negotiations, then this issue shall be referred to arbitration pursuant to the arbitration procedures set forth in Exhibit B hereto to decide whether such breach can be cured or any other alternative remedy should be adopted. In the event the breach is an incurable breach, the parties agree that the matter shall be referred to arbitration pursuant to the arbitration procedures set forth in Exhibit B hereto to determine the appropriate remedy. In the event that either party submits the dispute to arbitration, both parties shall cooperate in such binding arbitration in accordance with Exhibit B.

  • Delivery Condition Subtenant acknowledges that it takes possession of the Subleased Premises in its “as is” condition, and further acknowledges that Sublandlord has made no representations or warranties of any kind or nature, whether express or implied, with respect to the Subleased Premises, the remainder of the Premises, the common areas, or the Building, nor has Sublandlord agreed to undertake or perform any modifications, alterations, or improvements to the Subleased Premises, the remainder of the Premises, the common areas or the Building which would inure to Subtenant’s benefit.

  • Delivery Conditions (a) The Delivery Conditions are as follows: (i) At Seller’s expense, Seller shall have secured all Governmental and grid operations approvals as are necessary for the safe and lawful operation and maintenance of the Project and to enable Seller to deliver Distribution Services at the Initial Contract Capacity to Buyer. (ii) Seller shall have posted collateral as required by Section 10.4(a)(ii). (iii) Seller shall have submitted for Buyer’s review a Project Safety Plan incorporating the elements described in Appendix XII, which must demonstrate Seller’s ability to comply with the Safety Requirements on the IDD and for the Delivery Term. (iv) Seller shall have delivered to Buyer the Safety Attestation in accordance with Section 2(a) of Appendix XIV. (v) As of the IDD, no Seller’s Event of Default shall have occurred and remain uncured. (vi) At Seller’s expense, Seller or Contractor shall have constructed or caused to be constructed the Project as of the IDD and submitted the Certification for Commercial Operation in Appendix VII-A to enable (A) Seller to satisfy the obligations of the Seller herein and (B) the Project to deliver Distribution Services at the Contract Capacity to Buyer. (vii) At Seller’s expense, Seller shall have installed any necessary metering to deliver the applicable Distribution Services in accordance with Section 4.1 and any applicable tariffs of the Utility Distribution Company. (viii) Seller shall have met each Critical Milestone set forth in Appendix VI pursuant to Section 2.3.

  • Settlement Notice Requirements Notwithstanding any other provision hereof, a Settlement Notice delivered by Counterparty that specifies Cash Settlement or Net Share Settlement will not be effective to establish a Settlement Date or require Cash Settlement or Net Share Settlement unless Counterparty delivers to Dealer with such Settlement Notice a representation, dated as of the date of such Settlement Notice and signed by Counterparty, containing (x) the provisions set forth in clause (i) under the heading “Additional Representations and Agreements of Counterparty” in Paragraph 7(e) below and (y) a representation from Counterparty that neither Counterparty nor any of its subsidiaries has applied, and shall not until after the first date on which no portion of the Transaction remains outstanding following any final exercise and settlement, cancellation or early termination of the Transaction, apply, for a loan, loan guarantee, direct loan (as that term is defined in the Coronavirus Aid, Relief and Economic Security Act (the “CARES Act”)) or other investment, or receive any financial assistance or relief under any program or facility (collectively “Financial Assistance”) that (I) is established under applicable law (whether in existence as of the Trade Date or subsequently enacted, adopted or amended), including without limitation the CARES Act and the Federal Reserve Act, as amended, and (II) (X) requires under applicable law (or any regulation, guidance, interpretation or other pronouncement of a governmental authority with jurisdiction for such program or facility) as a condition of such Financial Assistance, that Counterparty comply with any requirement not to, or otherwise agree, attest, certify or warrant that it has not, as of the date specified in such condition, repurchased, or will not repurchase, any equity security of Issuer, and that it has not, as of the date specified in the condition, made a capital distribution or will make a capital distribution, or (Y) where the terms of the Transaction would cause Counterparty under any circumstances to fail to satisfy any condition for application for or receipt or retention of the Financial Assistance (collectively “Restricted Financial Assistance”), other than any such applications for Restricted Financial Assistance that were (or would be) made (x) determined based on the advice of outside counsel of national standing that the terms of the Transaction would not cause Counterparty to fail to satisfy any condition for application for or receipt or retention of such Financial Assistance based on the terms of the program or facility as of the date of such advice or (y) after delivery to Dealer evidence or other guidance from a governmental authority with jurisdiction for such program or facility that the Transaction is permitted under such program or facility (either by specific reference to the Transaction or by general reference to transactions with the attributes of the Transaction in all relevant respects).

  • ADDITIONAL SPECIAL CONTRACT CONDITIONS Special Contract Conditions revisions: the corresponding subsections of the Special Contract Conditions referenced below are replaced in their entirety with the following:

  • Delivery Notice Notice of the Aircraft's Delivery Date, given by the Lessee as provided in Section 3.01 of the Participation Agreement and including any notice with respect to a postponed Delivery Date given by the Lessee pursuant to Section 3.05(c) of the Participation Agreement.