Differing Site Conditions. (a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or (2) unknown physical conditions at the site(s), of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.
(b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. Work shall not proceed at the affected site, except at the Contractor’s risk, until the Contracting Officer has provided written instructions to the Contractor. If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, the Contractor shall file a claim in writing to the PHA within ten days after receipt of such instructions and, in any event, before proceeding with the work. An equitable adjustment in the contract price, the delivery schedule, or both shall be made under this clause and the contract modified in writing accordingly.
(c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in (a) above for giving written notice may be extended by the Contracting Officer.
(d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.
Differing Site Conditions.
3.19.1 Except as provided in this Section 3.19, Contractor agrees to solely bear the risk, including any additional costs and Delay of any and all concealed and unknown site conditions, without adjustment to the Contract Sum or Contract Time. This provision is applicable if the Project involves digging trenches or other excavations that extend deeper than four (4) feet below the surface. Contractor shall promptly, and before the following conditions are disturbed, provide written notice to City if the Contractor finds any of the following conditions:
.1 Material that Contractor believes may be a hazardous waste, as defined in Section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with the provisions of existing law.
.2 Subsurface or latent physical conditions at the site differing from those indicated by information about the site made available to bidders prior to the deadline for submitting bids.
.3 Unknown physical conditions at the site of any unusual nature, differing materially different from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents.
3.19.2 City shall promptly investigate any of the above the conditions and if City finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in Contractor’s cost of, or the time required for, performance of any part of the Work, shall issue a Change Order under the procedures described in the Contract Documents. The City may, acting in its sole discretion, extend the applicable deadline for submitting a Change Order Request when it is based upon differing conditions subject to Public Contract Code Section 7104.
3.19.3 In the event that a dispute arises between the City and the Contractor regarding any of the matters specified in subsection 3.19.1, above, Contractor shall not be excused from any scheduled completion date provided for in the Contract Documents, but shall proceed with all Work to be performed under the Contract. Contractor shall retain any and all rights provided either by the Contract or by law which pertain to the resolution of disputes between Contractor and City.
Differing Site Conditions. (a) Seller shall promptly, and before the conditions are disturbed, give a written notice to Company of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this Agreement, or (2) physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in this Agreement.
(b) Company shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in Seller's cost of, or the time required for, performing any part of the work under this Agreement, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the Agreement modified in writing accordingly.
(c) No request by Seller for an equitable adjustment under this clause shall be allowed, unless the written notice required in paragraph (a) above is timely given.
Differing Site Conditions. A. Contractor shall promptly, and before the conditions are disturbed, give written notice to the SDSTA and Project Engineer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this Contract, or (2) unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in this Contract.
B. The SDSTA shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any part of the Work under this Contract, whether or not changed as a result of changed conditions, the Contract Sum shall be adjusted as provided in Article III, provided that the Work has been ordered in writing by the SDSTA.
Differing Site Conditions. A. The Contractor shall promptly, and before the conditions are disturbed, give written notice to the OWNER of (1) subsurface or latent physical conditions at the Site which differ materially from those indicated in this Contract, or (2) unknown physical conditions at the Site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract. (“Materially” is defined as conditions causing costs not covered under unit price adjustments in excess of $10,000.00.)
B. The OWNER or authorized representative shall investigate the Site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any part of the Work under this Contract, an equitable adjustment shall be made under this Article and the Contract modified in writing accordingly.
C. No request by the Contractor for an equitable adjustment to the contract under this Article shall be allowed unless the Contractor has given the written notice required; provided that the time prescribed in paragraph (a) for giving written notice may be extended by the OWNER.
D. No request by the Contractor for an equitable adjustment to the Contract for differing site conditions shall be allowed if made after final payment under this Contract.
Differing Site Conditions.
a) The contractor shall promptly, and before such conditions are disturbed, notify the contracting officer in writing of: (1) subsurface or latent physical conditions at the site differing materially from those indicated in this contract; or (2) unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in this contract. The contracting officer shall promptly investigate the conditions, and if the contracting officer finds that such conditions do materially so differ and cause an increase or decrease in the contractor's cost of, or the time required for, performance of any part of the work under this contract, whether or not changed as a result of such conditions, an equitable adjustment shall be made and the contract modified in writing accordingly.
b) No claim of the contractor under this clause shall be allowed unless the contractor has given the notice required in subparagraph "a" above; provided, however, the time prescribed therefore may be extended by the contracting officer.
c) No claim by the contractor for an equitable adjustment hereunder shall be allowed if asserted after final payment under this contract.
Differing Site Conditions. Respond to any notice from Contractor of differing site conditions, including conditions relating to underground facilities such as utilities, and hazardous environmental conditions. Promptly conduct reviews and prepare findings, conclusions, and recommendations for Owner’s use.
Differing Site Conditions. In the event that during the course of the Work CONTRACTOR encounters subsurface or concealed conditions at the Project site which differ materially from those shown on the Contract Documents and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents and Supplementary Conditions; or unknown physical conditions of the Project site, of an unusual nature, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in the locales such as that where the work is to be done, CONTRACTOR shall, within twenty-four (24) hours of their discovery, notify CITY in writing of the existence of the aforesaid conditions. CITY shall, within two (2) business days after receipt of CONTRACTOR's written notice, investigate the site conditions identified by CONTRACTOR. If, in the sole opinion of CITY ENGINEER with the consent of City’s Project Manager, the conditions do materially so differ and cause an increase or decrease in CONTRACTOR's cost of, or the time required for, the performance of any part of the Work, CITY ENGINEER shall recommend an equitable adjustment to the Contract Price, or the Contract Time, or both. If CITY and CONTRACTOR cannot agree on an adjustment in the Contract Price or Contract Time, the adjustment shall be referred to CITY ENGINEER for determination in accordance with the provision for resolving disputes. Should CITY ENGINEER determine that the conditions of the Project site are not so materially different to justify a change in the terms of the Contract, CITY ENGINEER shall so notify CONTRACTOR in writing, stating the reasons, and such determination shall be final and binding upon the parties hereto. No request for an equitable adjustment or change to the Contract Price or Contract Time for differing site conditions shall be allowed if made after the date certified by CITY ENGINEER as the date of substantial completion.
Differing Site Conditions. DB Contractor shall be entitled to an increase in the Price or an extension of a Completion Deadline due to Differing Site Conditions only as provided in Section 4.6.9.1 of the General Conditions and this Section 6.1.
Differing Site Conditions. (a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to BSA of:
(i) subsurface or latent physical conditions at the site which differ materially from those indicated in this Agreement, or
(ii) unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this agreement.
(b) BSA shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performing any part of the work under this Agreement, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and this Agreement modified in writing accordingly.
(c) No Claim by the Contractor for an equitable adjustment under this Article shall be allowed unless the Contractor has given the written notice required by this Article and otherwise complied with the Notification of Claims and Documentation Article.