Common use of Differing Site Conditions; Inspection Clause in Contracts

Differing Site Conditions; Inspection. 11.2.1 Concealed or latent physical conditions or subsurface conditions at the Site that (i) differ from the conditions indicated in the Contract Documents, or (ii) are of an unusual nature, differing from the conditions ordinarily encountered and generally recognized as inherent in the Work are collectively referred to herein as “Differing Site Conditions.” If Design-Builder encounters a Differing Site Condition, Design-Builder will be entitled to an adjustment in the Contract Price and/or Contract Time(s) to the extent Design-Builder’s cost and/or time of performance are adversely impacted by the Differing Site Condition. 11.2.2 Upon encountering a Differing Site Condition, Design-Builder shall provide prompt written notice to Owner of such condition, which notice shall not be later than fourteen (14) business days after such condition has been encountered. Design-Builder shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.

Appears in 11 contracts

Samples: Lump Sum Design Build Agreement (Advanced BioEnergy, LLC), Lump Sum Design Build Agreement (E Energy Adams LLC), Lump Sum Design Build Agreement (Highwater Ethanol LLC)

AutoNDA by SimpleDocs

Differing Site Conditions; Inspection. 11.2.1 Concealed or latent physical conditions or subsurface conditions at the Site that (i) differ from the conditions indicated in the Contract Documents, or (ii) are of an unusual nature, differing from the conditions ordinarily encountered and generally recognized as inherent in the Work are collectively referred to herein as "Differing Site Conditions." If Design-Builder encounters a Differing Site Condition, Design-Builder will be entitled to an adjustment in the Contract Price and/or Contract Time(scontract time(s) to the extent Design-Builder’s 's cost and/or time of performance are materially adversely impacted by the Differing Site Condition. 11.2.2 Upon encountering a Differing Site Condition, Design-Builder shall provide prompt written notice to Owner of such condition, which notice shall not be later than fourteen (14) business days after such condition has been encountered. Design-Builder shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.

Appears in 2 contracts

Samples: Lump Sum Design Build Agreement (Green Plains Renewable Energy, Inc.), Lump Sum Design Build Agreement (Green Plains Renewable Energy, Inc.)

Differing Site Conditions; Inspection. 11.2.1 Concealed or latent physical conditions or subsurface conditions at the Site that (i) differ from the conditions indicated in the Contract Documents, or (ii) are of an unusual nature, differing from the conditions ordinarily encountered and generally recognized as inherent in the Work are collectively referred to herein as “Differing Site Conditions.” If Design-Builder encounters a Differing Site Condition, Design-Builder will be entitled to an adjustment in the Contract Price and/or Contract Time(s) to the extent Design-Builder’s cost and/or time of performance are adversely impacted by the Differing Site Condition. 11.2.2 Upon encountering a Differing Site Condition, Design-Builder shall provide prompt written notice to Owner of such condition, which notice shall not be later than fourteen (14) business days after such condition has been encountered. Design-Builder shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.. [Name of Project Company] ___ ___, 2006

Appears in 2 contracts

Samples: Master Agreement for Design, Engineering and Construction (US BioEnergy CORP), Master Agreement for Design, Engineering and Construction (US BioEnergy CORP)

Differing Site Conditions; Inspection. 11.2.1 Concealed or latent physical conditions or subsurface conditions at the Site that (i) differ from the conditions indicated in the Contract Documents, or (ii) are of an unusual nature, differing from the conditions ordinarily encountered and generally recognized as inherent in the Work are collectively referred to herein as “Differing Site Conditions.” If Design-Builder Xxxxx encounters a Differing Site Condition, Design-Builder Xxxxx will be entitled to an adjustment in the Contract Price and/or Contract Time(s) and Target Price to the extent Design-Builder’s cost and/or Xxxxx’x time of performance and costs are adversely impacted by the Differing Site Condition. 11.2.2 Upon encountering a Differing Site Condition, Design-Builder Xxxxx shall provide prompt written notice to Owner of such condition, which notice shall not be later than fourteen (14) business days after such condition has been encountered. Design-Builder Xxxxx shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.

Appears in 2 contracts

Samples: Construction Agreement (Aventine Renewable Energy Holdings Inc), Construction Agreement (Aventine Renewable Energy Holdings Inc)

Differing Site Conditions; Inspection. 11.2.1 Concealed or latent physical conditions or subsurface conditions at the Site that (i) differ from the conditions indicated in the Contract Documents, or (ii) are of an unusual nature, differing from the conditions ordinarily encountered and generally recognized as inherent in the Work are collectively referred to herein as “Differing Site Conditions.” If Design-Builder encounters a Differing Site Condition, Design-Builder will be entitled to an Siouxland Ethanol, LLC 27 January 5, 2006 adjustment in the Contract Price and/or Contract Time(scontract time(s) to the extent Design-Builder’s cost and/or time of performance are materially adversely impacted by the Differing Site Condition. 11.2.2 Upon encountering a Differing Site Condition, Design-Builder shall provide prompt written notice to Owner of such condition, which notice shall not be later than fourteen (14) business days after such condition has been encountered. Design-Builder shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.

Appears in 1 contract

Samples: Lump Sum Design Build Agreement (Siouxland Ethanol, LLC)

Differing Site Conditions; Inspection. 11.2.1 Concealed or latent physical conditions or subsurface conditions at the Site that (i) differ from the conditions indicated in the Contract Documents, or (ii) are of an unusual nature, differing from the conditions ordinarily encountered and generally recognized as inherent in the Work are collectively referred to herein as “Differing Site Conditions.” If Design-Builder encounters a Differing Site Condition, Design-Builder will be entitled to an Cardinal Ethanol, LLC December 14, 2006 adjustment in the Contract Price and/or Contract Time(s) to the extent Design-Builder’s cost and/or time of performance are adversely impacted by the Differing Site Condition. 11.2.2 Upon encountering a Differing Site Condition, Design-Builder shall provide prompt written notice to Owner of such condition, which notice shall not be later than fourteen (14) business days after such condition has been encountered. Design-Builder shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.

Appears in 1 contract

Samples: Lump Sum Design Build Agreement (Cardinal Ethanol LLC)

Differing Site Conditions; Inspection. 11.2.1 Concealed or latent physical conditions or subsurface conditions at the Site that (i) differ from the conditions indicated in the Contract Documents, or (ii) are of an unusual nature, differing from the conditions ordinarily encountered and generally recognized as inherent in the Work are collectively referred to herein as “Differing Site Conditions.” If Design-Builder encounters a Differing Site Condition, Design-Builder will be entitled to an adjustment in the Contract Price and/or Contract Time(s) to the extent Design-Builder’s cost and/or time of performance are adversely impacted by the Differing Site Condition. 11.2.2 Upon encountering a Differing Site Condition, Design-Builder shall provide prompt written notice to Owner of such condition, which notice shall not be later than fourteen (14) business days after such condition has been encountered. Design-Builder shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.. [Name of Project Company] , 2006

Appears in 1 contract

Samples: Master Agreement for Design, Engineering and Construction (US BioEnergy CORP)

Differing Site Conditions; Inspection. 11.2.1 Concealed or latent physical conditions or subsurface conditions at the Site that (i) differ from the conditions indicated in the Contract Documents, or (ii) are of an unusual nature, differing from the conditions ordinarily encountered and generally recognized as inherent in the Work are collectively referred to herein as “Differing Site Conditions.” If Design-Builder encounters a Differing Site Condition, Design-Builder will be entitled to an adjustment in the Contract Price and/or Contract Time(scontract time(s) to the extent Design-Builder’s cost and/or time of performance are adversely impacted by the Differing Site Condition. 11.2.2 Upon encountering a Differing Site Condition, Design-Builder shall provide prompt written notice to Owner of such condition, which notice shall not be later than fourteen (14) business days after such condition has been encountered. Design-Builder shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.

Appears in 1 contract

Samples: Lump Sum Design Build Agreement (Advanced BioEnergy, LLC)

AutoNDA by SimpleDocs

Differing Site Conditions; Inspection. 11.2.1 11.2.1. Concealed or latent physical conditions or subsurface conditions at the Site that (i) differ from the conditions indicated in the Contract Documents, or (ii) are of an unusual nature, differing from the conditions ordinarily encountered and generally recognized as inherent in the Work are collectively referred to herein as “Differing Site Conditions.” If Design-Builder encounters a Differing Site Condition, Design-Builder will be entitled to an adjustment in the Contract Price and/or Contract Time(scontract time(s) to the extent Design-Builder’s cost and/or time of performance are adversely impacted by the Differing Site Condition. 11.2.2 11.2.2. Upon encountering a Differing Site Condition, Design-Builder shall provide prompt written notice to Owner of such condition, which notice shall not be later than fourteen (14) business days after such condition has been encountered. Design-Builder shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.

Appears in 1 contract

Samples: Lump Sum Design Build Agreement (US BioEnergy CORP)

Differing Site Conditions; Inspection. 11.2.1 Concealed or latent physical conditions or subsurface conditions at the Site that (i) differ from the conditions indicated in the Contract Documents, or (ii) are of an unusual nature, differing from the conditions ordinarily encountered and generally recognized as inherent in the Work are collectively referred to herein as “Differing Site Conditions.” If ADVANCED BIOENERGY, LLC March 16, 2006 Design-Builder encounters a Differing Site Condition, Design-Builder will be entitled to an adjustment in the Contract Price and/or Contract Time(scontract time(s) to the extent Design-Builder’s cost and/or time of performance are adversely impacted by the Differing Site Condition. 11.2.2 Upon encountering a Differing Site Condition, Design-Builder shall provide prompt written notice to Owner of such condition, which notice shall not be later than fourteen (14) business days after such condition has been encountered. Design-Builder shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.

Appears in 1 contract

Samples: Lump Sum Design Build Agreement (Advanced BioEnergy, LLC)

Differing Site Conditions; Inspection. 11.2.1 Concealed or latent physical conditions or subsurface conditions at the Site that (i) differ from the conditions indicated in the Contract Documents, or (ii) are of an unusual nature, differing from the conditions ordinarily encountered and generally recognized as inherent in the Work are collectively referred to herein as “Differing Site Conditions.” If Design-Builder encounters a Differing Site Condition, Design-Builder will be entitled to an adjustment in the Contract Price and/or Contract Time(s) to the extent Design-Builder’s cost and/or time of performance are adversely impacted by the Differing Site Condition. 11.2.2 Upon encountering a Differing Site Condition, Design-Builder shall provide prompt written notice to Owner of such condition, which notice shall not be later than fourteen (14) business days after such condition has been encountered. Design-Builder shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered. 11.2.3 Notwithstanding the foregoing, Design-Builder acknowledges that the Work will be performed in a category D seismic zone as defined by the International Building Code and agrees that such seismic zone classification shall not constitute a Differing Site Condition hereunder.

Appears in 1 contract

Samples: Lump Sum Design Build Contract (Ethanol Grain Processors, LLC)

Differing Site Conditions; Inspection. 11.2.1 Concealed or latent physical conditions or subsurface conditions at the Site that (i) differ from the conditions indicated in the Contract Documents, or (ii) are of an unusual nature, differing from the conditions ordinarily encountered and generally recognized as inherent in the Work are collectively referred to herein as “Differing Site Conditions.” If First United Ethanol, LLC November 16, 2006 Design-Builder encounters a Differing Site Condition, Design-Builder will be entitled to an adjustment in the Contract Price and/or Contract Time(s) to the extent Design-Builder’s cost and/or time of performance are adversely impacted by the Differing Site Condition. 11.2.2 Upon encountering a Differing Site Condition, Design-Builder shall provide prompt written notice to Owner of such condition, which notice shall not be later than fourteen (14) business days after such condition has been encountered. Design-Builder shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.

Appears in 1 contract

Samples: Lump Sum Design Build Agreement (First United Ethanol LLC)