Common use of Discretionary Time Extensions for Best Interest of District Clause in Contracts

Discretionary Time Extensions for Best Interest of District. District reserves the right to extend the time for completion of the Work if District determines that such extension is in the best interest of District. In the event that a discretionary extension is granted at the request of Contractor, District shall have the right to charge to Contractor all or any part, as District may deem proper, of the actual cost of construction management, engineering, inspection, supervision, incidental and other overhead expenses that accrue during the period of the extension, and to deduct all or any portion of that amount from the final payment for the Work.

Appears in 6 contracts

Samples: Facilities Lease, Facilities Lease, Facilities Lease