Disputed Changes. If Contractor should dispute a decision by Princeton University as to whether a change has occurred or whether, or to what extent, a change in the Work will result in a change in the Contract Price, the Contract Time or the Project Schedule, then Contractor shall, if directed by Princeton University in a Disputed Change Order or other written directive, nevertheless perform such work pursuant to Clause H5; provided that the performance of the work shall not prejudice any claim that Contractor may have with respect to such work, so long as Contractor has given Princeton University timely notice of such claim pursuant to Clause H3, and so long as Contractor maintains the records required under Clause H5 and paragraph (g) below.
Appears in 7 contracts
Samples: Boa Services, Boa Services, Part I Agreement