DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications, addenda, Change Orders and other Modifications, in good order and marked currently to record changes and selections made during construction, and in addition approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be available to the Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work.
Appears in 4 contracts
Samples: Construction Contract (Digex Inc/De), Construction Contract (National Instruments Corp /De/), Construction Contract (Digex Inc/De)
DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications, addenda, Change Orders and other Modifications, in good order and marked currently to record changes and selections made during construction, and in addition approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be available to the Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work.Change
Appears in 2 contracts
Samples: General Conditions of the Contract for Construction, General Conditions of the Contract for Construction
DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 3.10.1 The Contractor shall maintain at the site for the Owner one record copy of the all Drawings, Specifications, addendaAddenda, Change Orders and other Modifications, in good order and marked currently to record all changes and selections made during construction, and in addition approved Shop Drawings, Product Data, Samples Data and similar required submittalsSamples. These shall be available to the Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work.
Appears in 2 contracts
Samples: Owner Contractor Agreement, Owner Contractor Agreement
DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications, addendaAddenda, Change Orders and other Modifications, in good order and marked currently to record field changes and selections made during construction, and in addition one record copy of approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be available to the Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work.
Appears in 2 contracts
Samples: Lease Agreement (Immunicon Corp), Standard Form of Agreement Between Owner and Contractor (Corixa Corp)
DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications, addendaAddenda, Change Orders and other Modifications, in good order and marked currently to record changes and selections made during construction, and in addition approved Shop Drawings, Product Data, Samples and similar required submittalssubmittal. These shall be available to the Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work.
Appears in 1 contract
Samples: Architectural Services Agreement
DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications, addendaAddenda, Change Orders Orders, and other Modifications, in good order Order and marked currently to record field changes and selections made during construction, and in addition one record copy of approved Shop Drawings, Product Data, Samples Samples, and similar required submittals. These shall be available to the Owner and Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work.
Appears in 1 contract
Samples: Construction Contract
DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 The Contractor shall maintain at the Project site for the Owner one record copy of the Drawings, Specifications, addenda, Change Orders and other Modifications, in good order and marked currently to record changes and selections made during construction, and in addition approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be available to the Construction Manager and Architect and shall be delivered to the Architect Construction Manager for submittal to the Owner upon completion of the Work.
Appears in 1 contract
Samples: Standard Form of Agreement (Windsor Woodmont Black Hawk Resort Corp)
DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications, addenda, Change Orders and other Modifications, in good order and marked currently to record changes and selections made during construction, and in addition approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be available to the Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work, signed by the Contractor and certifying that they show complete and exact “as built” conditions, stating sizes, kind of materials, locations and similar matters.
Appears in 1 contract
Samples: Contract for Construction
DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications, addenda, Change Orders and other Modificationsmodifications, in good order and marked currently to record field changes and selections made during construction, and in addition one record copy of approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be available to the Architect Architect/Engineer and shall be delivered to the Architect Architect/Engineer for submittal to the Owner upon completion of the WorkWork or Contractor’s request for Substantial Completion Inspection.
Appears in 1 contract
Samples: Construction Manager Agreement
DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 4.10.1 The Contractor shall maintain at the site for the Owner one record copy of the all Drawings, Specifications, addendaAddenda, Change Orders and other Modifications, in good order and marked currently to record changes and selections made during construction, and in addition approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be available to the Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work.
Appears in 1 contract
Samples: Service Contract
DOCUMENTS AND SAMPLES AT THE SITE. § 3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications, addendaAddenda, Change Orders and other Modifications, in good order and marked currently to record field changes and selections made during construction, and in addition one record copy of approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be available to the Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work.
Appears in 1 contract
Samples: Construction Contract (Sierra Pacific Resources /Nv/)
DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications, addendaAddenda, Change Orders and other Modifications, in good order and marked currently to record changes and selections made during construction, and in addition approved Shop Drawings, Product Data, Samples and similar required submittalssubmittal. These shall be available to the Architect Engineer and shall be delivered to the Architect for submittal to the Owner upon completion of the Work.
Appears in 1 contract
Samples: Construction Contract
DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications, addendaAddenda, Change Orders and other Modifications, in good order and marked currently to record field changes and selections made during construction, and in addition one record copy of approved Shop Drawings, Product DataDate, Samples and similar required submittals. These shall be available to the Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work as a cost of the Work.
Appears in 1 contract
DOCUMENTS AND SAMPLES AT THE SITE. §3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications, addendaAddenda, Change Orders Orders, Construction Change Directives, and other Modifications, in good order and marked currently to record field changes and selections made during construction, and in addition one record copy of approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be available to the Architect Owner and Architect/Engineer and shall be delivered to the Architect for submittal to the Owner upon completion of the Work.Architect/Engineer
Appears in 1 contract
Samples: Services Agreement
DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 The XXXX Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications, addendaAddenda, Change Orders and other Modifications, in good order and marked currently to record field changes and selections made during construction, and in addition one record copy of approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be available to the Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work.
Appears in 1 contract