DSA Notification. Inspector shall notify DSA: 10.10.1.1. At least forty-eight (48) hours prior to the start of any Construction Work at a Site. 10.10.1.2. At least forty-eight (48) hours prior to completion of any foundation excavations/trenches. 10.10.1.3. At least forty-eight (48) hours prior to the first concrete pour/placement at a Site. 10.10.1.4. When Construction Work has been suspended for a period of more than two (2) weeks.
Appears in 4 contracts
Samples: Agreement for Project Inspection Services, Project Inspection Services Agreement, Agreement for Project Inspection Services
DSA Notification. Inspector shall notify DSA:
10.10.1.112.1.1. At least forty-eight (48) hours prior to the start of any Construction Work at a each Site.
10.10.1.212.1.2. At least forty-eight (48) hours prior to completion of any foundation excavations/trenches.
10.10.1.312.1.3. At least forty-eight (48) hours prior to the first concrete pour/placement at a any Site.
10.10.1.412.1.4. When Construction Work has been suspended for a period of more than two (2) weeks.
Appears in 3 contracts
Samples: Project Inspection Services Agreement, Project Inspection Services Agreement, Project Inspection Services Agreement
DSA Notification. Inspector shall notify DSA:
10.10.1.1. At least forty-eight (48) hours prior to the start of any Construction Work at a the Site.
10.10.1.2. At least forty-eight (48) hours prior to completion of any foundation excavations/trenches.
10.10.1.3. At least forty-eight (48) hours prior to the first concrete pour/placement at a the Site.
10.10.1.4. When Construction Work has been suspended for a period of more than two (2) weeks.
Appears in 3 contracts
Samples: Project Inspection Services Agreement, Project Inspection Services Agreement, Project Inspection Services Agreement
DSA Notification. Inspector shall notify DSA:
10.10.1.115.1.1. At least forty-eight (48) hours prior to the start of any Construction Work at a Sitethe Project.
10.10.1.215.1.2. At least forty-eight (48) hours prior to completion of any foundation excavations/trenches.
10.10.1.315.1.3. At least forty-eight (48) hours prior to the first concrete pour/placement at a Sitethe Project.
10.10.1.415.1.4. When Construction Work has been suspended for a period of more than two (2) weeks.
Appears in 1 contract
Samples: Professional Services
DSA Notification. Inspector shall notify DSA:
10.10.1.1. At least forty-eight forty‐eight (48) hours prior to the start of any Construction Work at a the Site.
10.10.1.2. At least forty-eight forty‐eight (48) hours prior to completion of any foundation excavations/trenches.
10.10.1.3. At least forty-eight forty‐eight (48) hours prior to the first concrete pour/placement at a the Site.
10.10.1.4. When Construction Work has been suspended for a period of more than two (2) weeks.
Appears in 1 contract
DSA Notification. Inspector The Project Inspector(s) shall notify DSA:
10.10.1.1. At : (i) at least forty-eight (48) hours prior to the start of any Construction Work construction; (ii) at a Site.
10.10.1.2. At least forty-eight (48) hours prior to in advance of completion of any foundation excavations/trenches.
10.10.1.3. At ; (iii) at least forty-eight (48) hours prior to in advance of the first concrete pour/placement at a Site.
10.10.1.4. When Construction ; and (iv) when Work has been suspended for a period of more than two (2) weeks.
Appears in 1 contract
Samples: Project Inspector Services Agreement