Early Work Packages. 6.6.2.1 Early Work Packages may be awarded to the XXXX during the preconstruction phase services of the Project to facilitate the early preparation of the Site, purchase long lead time materials and equipment and otherwise accelerate certain portions of the Work in advance of the agreement between the Owner and CMAR regarding the GMP Proposal for the entire Work. These Early Work Packages will be ready for commencement of their construction before it is appropriate to arrive at an overall GMP for the entire Work. Early Work Package shall be defined as a portion of Work that the Parties agree should be executed during the preconstruction phase services of the Project. 6.6.2.2 Either Owner or the CMAR may propose Early Work Packages to proceed prior to that time the GMP Proposal for the entire Work is approved by the Owner. Based upon the written agreement of the Parties, the CMAR may either perform, if selected by the Owner as the successful bidder or proposer, or subcontract such Early Work Packages before the GMP Proposal for the entire Work has been submitted and approved. The approved GMP amount for the scope of Work in any early Work Package shall be included in the subsequent GMP Proposal for the entire Work as an individual line item with reference made to the appropriate GMP Amendment. The XXXX’x fee for billing purposes for such Early Work Package scope of Work shall not exceed the pro rata portion of the fee that the Cost of Work of the Early Work Package as performed bears to the Owner’s Budget. The CMAR will be obligated to provide payment and performance bonds in accordance with Article 5 of the General Conditions for the GMP amount of any early Work Package. 6.6.2.3 The Owner may choose to accelerate the completion of certain portions of the design work so that some specific Early Work Packages may be awarded by the CMAR prior to the completion of the remaining Construction Documents or acceptance by the Owner of the GMP Proposal for the entire Work. The CMAR shall verify that the Design Professional has provided the documents necessary to Bid and award any Early Work Package. Any Early Work Package shall contain language which makes those subcontracts 100% assignable to Owner at Owner’s option, in the event this Agreement is terminated, and that the Subcontractors shall be obligated to accept that assignment if it should occur. 6.6.2.4 For any Early Work Package, the CMAR shall submit to Owner a GMP Proposal in accordance with Section 6.6 of this Agreement.
Appears in 1 contract
Early Work Packages. 6.6.2.1 Early Work Packages The parties anticipate that there may be awarded to the XXXX during the preconstruction phase services one or more elements of the Project to facilitate the early preparation of the Site, purchase long lead time materials and equipment and otherwise accelerate certain portions of the Implementation Work in advance of the agreement between the Owner and CMAR regarding the GMP Proposal for the entire Work. These Early Work Packages will be that are ready for commencement of their construction before it is appropriate to arrive at an overall agreed-upon Base Guaranteed Maximum Price in accordance with Section 5.8 (GMP for Project Submittal). The Project Company shall recommend such phases or elements of the entire WorkProject Implementation Work (“Early Work Packages”) to the KRRC Contract Representative, as appropriate, through the performance of the Preliminary Services, based on Early Work Package submittals (“Early Work Package Submittals”). The KRRC shall have the discretion to authorize the commencement of Project Implementation Work associated with an Early Work Package pursuant to this Section. The agreement of the parties as to an Early Work Package shall be defined as effectuated through a portion of Contract Amendment authorizing the Project Implementation Work that the Parties agree should be executed during the preconstruction phase services of the Project.
6.6.2.2 Either Owner or the CMAR may propose Early Work Packages to proceed prior to that time the GMP Proposal for the entire Work is approved by the Owner. Based upon the written agreement of the Parties, the CMAR may either perform, if selected by the Owner as the successful bidder or proposer, or subcontract such Early Work Packages before the GMP Proposal for the entire Work has been submitted and approved. The approved GMP amount for the scope of Work in any early Work Package shall be included in the subsequent GMP Proposal for the entire Work as an individual line item associated with reference made to the appropriate GMP Amendment. The XXXX’x fee for billing purposes for such Early Work Package scope of Work shall not exceed the pro rata portion of the fee that the Cost of Work of the Early Work Package as performed bears and specifying the terms and conditions of compensation payable to the Owner’s BudgetProject Company and the completion dates associated with such Project Implementation Work (an “Early Work Package Amendment”). The CMAR will All work performed pursuant to an Early Work Package Amendment shall constitute Project Implementation Work hereunder and shall be obligated to provide payment and performance bonds performed in accordance with Article 5 of the General Conditions for Contract Standards. Neither the GMP amount of KRRC nor the Project Company shall have any early Work Package.
6.6.2.3 The Owner may choose obligation to accelerate the completion of certain portions of the design work so that some specific enter into an Early Work Packages may Package Amendment. All Early Work Package Amendments agreed upon in accordance with this Section shall be awarded by taken into consideration in the CMAR prior to the completion of the remaining Construction Documents or acceptance by the Owner preparation of the GMP Proposal for the entire WorkProject Submittal submitted in accordance with Section 5.8 (GMP Project Submittal). The CMAR Project Company shall verify that the Design Professional has provided the documents necessary to Bid and award any Early Work Package. Any furnish Early Work Package shall contain language which makes those subcontracts 100% assignable Bonds with penal sums equal to Owner at Owner’s option, in the event this Agreement is terminated, and that Early Work Package Price applicable to the Subcontractors shall be obligated to accept that assignment if it should occur.
6.6.2.4 For any Early Work Package, in compliance with the CMAR shall submit requirements set forth in Section 16.2 (Bonds) prior to Owner the KRRC’s issuance of a GMP Proposal Notice to Proceed for the Early Work Package in accordance with Section 6.6 subsection (I) (Commencement of Early Work Package) of this AgreementSection.
Appears in 1 contract
Samples: Project Agreement for Design, Construction, Demolition and Habitat Restoration Services
Early Work Packages. 6.6.2.1 Early Work Packages may be awarded to the XXXX during the preconstruction phase services of the Project to facilitate the early preparation of the Site, purchase long lead time materials and equipment and otherwise accelerate certain portions of the Work in advance of the agreement between the Owner and CMAR XXXX regarding the GMP Proposal for the entire Work. These Early Work Packages will be ready for commencement of their construction before it is appropriate to arrive at an overall GMP for the entire Work. Early Work Package shall be defined as a portion of Work that the Parties agree should be executed during the preconstruction phase services of the Project.
6.6.2.2 Either Owner or the CMAR XXXX may propose Early Work Packages to proceed prior to that time the GMP Proposal for the entire Work is approved by the Owner. Based upon the written agreement of the Parties, the CMAR XXXX may either perform, if selected by the Owner as the successful bidder or proposer, or subcontract such Early Work Packages before the GMP Proposal for the entire Work has been submitted and approved. The approved GMP amount for the scope of Work in any early Work Package shall be included in the subsequent GMP Proposal for the entire Work as an individual line item with reference made to the appropriate GMP Amendment. The XXXX’x fee for billing purposes for such Early Work Package scope of Work shall not exceed the pro rata portion of the fee that the Cost of Work of the Early Work Package as performed bears to the Owner’s Budget. The CMAR XXXX will be obligated to provide payment and performance bonds in accordance with Article 5 of the General Conditions for the GMP amount of any early Work Package.
6.6.2.3 The Owner may choose to accelerate the completion of certain portions of the design work so that some specific Early Work Packages may be awarded by the CMAR XXXX prior to the completion of the remaining Construction Documents or acceptance by the Owner of the GMP Proposal for the entire Work. The CMAR XXXX shall verify that the Design Professional has provided the documents necessary to Bid and award any Early Work Package. Any Early Work Package shall contain language which makes those subcontracts 100% assignable to Owner at Owner’s option, in the event this Agreement is terminated, and that the Subcontractors shall be obligated to accept that assignment if it should occur.
6.6.2.4 For any Early Work Package, the CMAR XXXX shall submit to Owner a GMP Proposal in accordance with Section 6.6 of this Agreement.
Appears in 1 contract
Early Work Packages. 6.6.2.1 Early Work Packages may be awarded to the XXXX during the preconstruction phase services of the Project to facilitate the early preparation of the Site, purchase long lead time materials and equipment and otherwise accelerate certain portions of the Work in advance of the agreement between the Owner and CMAR XXXX regarding the GMP Proposal for the entire Work. These Early Work Packages will be ready for commencement of their construction before it is appropriate to arrive at an overall GMP for the entire Work. Early Work Package shall be defined as a portion of Work that the Parties agree should be executed during the preconstruction phase services of the Project.
6.6.2.2 Either Owner or the CMAR XXXX may propose Early Work Packages to proceed prior to that time the GMP Proposal for the entire Work is approved by the Owner. Based upon the written agreement of the Parties, the CMAR XXXX may either perform, if selected by the Owner as the successful bidder or proposer, or subcontract such Early Work Packages before the GMP Proposal for the entire Work has been submitted and approved. The approved GMP amount for the scope of Work in any early Work Package shall be included in the subsequent GMP Proposal for the entire Work as an individual line item with reference made to the appropriate GMP Amendment. The XXXX’x fee for billing purposes for such Early Work Package scope of Work shall not exceed the pro rata portion of the fee that the Cost of Work of the Early Work Package as performed bears to the Owner’s Budget. The CMAR will be obligated to provide payment and performance bonds in accordance with Article 5 of the General Conditions for the GMP amount of any early Work Package.GMP
6.6.2.3 The Owner may choose to accelerate the completion of certain portions of the design work so that some specific Early Work Packages may be awarded by the CMAR XXXX prior to the completion of the remaining Construction Documents or acceptance by the Owner of the GMP Proposal for the entire Work. The CMAR XXXX shall verify that the Design Professional Engineer has provided the documents necessary to Bid and award any Early Work Package. Any Early Work Package shall contain language which makes those subcontracts 100% assignable to Owner at Owner’s option, in the event this Agreement is terminated, and that the Subcontractors shall be obligated to accept that assignment if it should occur.
6.6.2.4 For any Early Work Package, the CMAR shall submit to Owner a GMP Proposal in accordance with Section 6.6 of this Agreement.shall
Appears in 1 contract