Early Work. Early Work shall mean Construction Phase Services authorized by Amendment that the parties agree should be performed in advance of establishment of the GMP. Permissible Early Work shall be limited to: early procurement of materials and supplies; early release of bid or proposal packages for site development and related activities; and any other advance work related to critical components of the Project for which performance prior to establishment of the GMP will materially affect the critical path schedule of the Project.
Appears in 25 contracts
Samples: General Contract, www.deschuteslibrary.org, wou.edu
Early Work. Early Work shall mean Construction Phase Services authorized by Amendment that the parties agree should be performed in advance of establishment of the GMP. Permissible Early Work shall be limited to: to early procurement of materials and supplies; , early release of bid or proposal packages construction for site development and related activities; , and any other advance work related to critical components of the Project for which performance prior to establishment of the GMP will materially affect the critical path Critical Path schedule of the Project.
Appears in 3 contracts
Samples: www.tn.gov, www.tn.gov, www.tn.gov
Early Work. Early Work shall mean means Construction Phase Services authorized by Amendment that the parties agree should be performed in advance of establishment of before establishing the GMP. Permissible Early Work shall be is limited to: early procurement of materials and supplies; early release of bid or proposal packages for site development and related activities; and any other advance work related to critical components of the Project project for which performance prior to establishment of before establishing the GMP will materially affect the critical path schedule of the Project.
Appears in 2 contracts
Samples: www.co.marion.or.us, www.co.marion.or.us
Early Work. Early Work shall mean means Construction Phase Services authorized by Amendment that the parties agree should be performed in advance of establishment of before establishing the GMP. Permissible Early Work shall be is limited to: early procurement of materials and supplies; early release of bid or proposal packages for site development and related activities; and any other advance work related to critical components of the Project for which performance prior to establishment of before establishing the GMP will materially affect the critical path schedule of the Project.
Appears in 2 contracts
Samples: Multnomah County Construction Services Contract, Emergency Construction Services Contract
Early Work. Early Work shall mean means Construction Phase Services authorized by Amendment that the parties agree should be performed in advance of establishment of before establishing the GMP. Permissible Early Work shall be is limited to: early procurement of materials and supplies; early release of bid or proposal packages for site development and related activities; and any other advance work related to critical components of the ofthe Project for which performance prior to establishment of before establishing the GMP will materially affect the critical path schedule of the Project.
Appears in 2 contracts
Samples: www.astoria.gov, content.myconnectsuite.com
Early Work. Early Work shall mean Construction Phase Services authorized by Amendment that the parties agree should be performed in advance of establishment of the GMP. Permissible Early Work shall be limited to: to early procurement of materials and supplies; early release of bid or proposal packages for site development and related activities; and any other advance work related to critical components of the Project for which performance prior to establishment of the GMP will materially affect the critical path schedule of the Project.
Appears in 2 contracts
Samples: www.cityofalbany.net, www.bidnet.com
Early Work. Early Work shall mean Construction Phase Services authorized by Amendment that the parties agree should be performed in advance of establishment of the GMP. Permissible Early Work shall be limited to: to early procurement of materials Materials and supplies; , early release of bid or proposal packages construction for site development and related activities; , and any other advance work Work related to critical components of the Project for which performance prior to establishment of the GMP will materially affect the critical path Critical Path schedule of the Project.
Appears in 2 contracts
Samples: www.tn.gov, www.tn.gov
Early Work. Early Work shall mean Construction Phase Services authorized by an Early Work Amendment that the parties agree should be performed in advance of establishment of the GMP. Permissible Early Work shall be limited to: early procurement of materials and supplies; early release of bid or proposal packages for site development and related activities; and any other advance work related to critical components of the Project for which performance prior to establishment of the GMP will materially affect the critical path schedule of the Project.
Appears in 1 contract
Samples: www.pdx.edu
Early Work. “Early Work shall mean Work” means Construction Phase Services Services, construction materials and other Work authorized by Amendment that the parties Parties agree should be performed by CM/GC in advance of establishment of the GMP. Permissible Early Work shall be is limited to: early procurement of materials and supplies; early release of bid or proposal packages for site development and related activities; and any other advance work related to critical components of the Project for which performance prior to establishment of before establishing the GMP will materially affect the critical path schedule of the Project.
Appears in 1 contract
Samples: Sample Construction
Early Work. Early Work shall mean Construction Phase Services authorized by Amendment that the parties agree should be performed in advance of establishment of the GMP. Permissible Early Work shall require written Owner authorization and be limited to: early procurement of materials and supplies; early release of bid or proposal packages for site development and related activities; and any other advance work related to critical components of the Project for which performance prior to establishment of the GMP will materially affect the critical path schedule of the Project.
Appears in 1 contract
Samples: www.hobbsschools.net