Electrical Loss Factor Adjustment to Interconnection Point Sample Clauses

Electrical Loss Factor Adjustment to Interconnection Point. In the event, and to the extent, that the meters used to determine the output of the Facility are not measuring deliveries of electric energy physically at the Interconnection Point, the metered amount of electric energy shall be adjusted to or from the Interconnection Point (as applicable) by a loss factor determined by Alabama Power, in accordance with Prudent Industry Practices. Alabama Power shall provide QF with a copy of any study or analysis prepared by Alabama Power in determining such loss factor.
AutoNDA by SimpleDocs
Electrical Loss Factor Adjustment to Interconnection Point. In the event, and to the extent, that the meters used to determine the output of the Facility are not measuring deliveries of electric energy physically at the Interconnection Point, the metered amount of electric energy shall be adjusted to or from the Interconnection Point (as applicable) by a loss factor determined by Buyer, in accordance with Prudent Industry Practices. Buyer shall provide Seller with a copy of any study or analysis prepared by Buyer in determining such loss factor.‌

Related to Electrical Loss Factor Adjustment to Interconnection Point

  • Interconnection Customer’s Interconnection Facilities The Interconnection Customer shall design, procure, construct, install, own and/or control the Interconnection Customer’s Interconnection Facilities described in Appendix A at its sole expense.

  • Traffic Measurement and Billing over Interconnection Trunks 6.1 For billing purposes, each Party shall pass Calling Party Number (CPN) information on at least ninety-five percent (95%) of calls carried over the Interconnection Trunks.

  • Interconnection Customer’s Interconnection Facilities Construction The Interconnection Customer’s Interconnection Facilities shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Participating TO and Interconnection Customer agree on another mutually acceptable deadline, the Interconnection Customer shall deliver to the Participating TO and CAISO “as-built” drawings, information and documents for the Interconnection Customer’s Interconnection Facilities and the Electric Generating Unit(s), such as: a one-line diagram, a site plan showing the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities, plan and elevation drawings showing the layout of the Interconnection Customer’s Interconnection Facilities, a relay functional diagram, relaying AC and DC schematic wiring diagrams and relay settings for all facilities associated with the Interconnection Customer's step-up transformers, the facilities connecting the Large Generating Facility to the step-up transformers and the Interconnection Customer’s Interconnection Facilities, and the impedances (determined by factory tests) for the associated step-up transformers and the Electric Generating Units. The Interconnection Customer shall provide the Participating TO and the CAISO specifications for the excitation system, automatic voltage regulator, Large Generating Facility control and protection settings, transformer tap settings, and communications, if applicable. Any deviations from the relay settings, machine specifications, and other specifications originally submitted by the Interconnection Customer shall be assessed by the Participating TO and the CAISO pursuant to the appropriate provisions of this LGIA and the LGIP.

  • Participating TO’s Interconnection Facilities The Participating TO shall design, procure, construct, install, own and/or control the Participating TO’s Interconnection Facilities described in Appendix A at the sole expense of the Interconnection Customer. Unless the Participating TO elects to fund the capital for the Participating TO’s Interconnection Facilities, they shall be solely funded by the Interconnection Customer.

  • Energy Resource Interconnection Service (ER Interconnection Service).