ENDORSEMENTS AND CONDITIONS. Endorsements 1. This licence is granted in accordance with proposals submitted on [ ], and approved by the Minister (as defined in the Agreement) on [ ], under the Agreement. 2. The Joint Venturers are permitted to, in accordance with approved proposals, take stone, sand, clay and gravel from the land the subject of this licence for the construction, operation and maintenance of the Railway (including any Railway spur line) constructed within or approved for construction within the area of land the subject of this licence. 3. Notwithstanding the Mining Xxx 0000, no royalty shall be payable under the Mining Xxx 0000 in respect of stone, sand, clay and gravel which the Joint Venturers are permitted by the Agreement to obtain from the land the subject of this licence. 4. [Any further endorsement which the Minister for Mines may, consistent with the provisions of the Agreement, determines and thereafter impose in respect of this licence including during the term of the Agreement.] Conditions (a) Except as provided in paragraph (b), the Joint Venturers shall within 2 years after the Railway Operation Date surrender in accordance with the provisions of the Mining Xxx 0000 the area of this licence down to a maximum of 100 metres width or as otherwise approved by the Minister (as defined in the Agreement) for the safe operation of the Railway then constructed or approved for construction under approved proposals. (b) Paragraph (a) shall not apply to land the subject of this licence that was included in this licence pursuant to clause 9E(6)(h) or clause 9E(6)(i) of the Agreement. 2. The Joint Venturers shall as soon as possible after the construction of a Railway spur line or of an expansion or extension thereof as the case may be surrender in accordance with the Mining Xxx 0000 the land the subject of this licence that was included in this licence pursuant to clause 9E(6)(h) of the Agreement for the purpose of such construction down to a maximum of 100 metres in width or as otherwise approved by the Minister (as defined in the Agreement) for the safe operation of that Railway spur line or expansion or extension thereof as the case may be then constructed or approved for construction under approved proposals. 3. [Any further conditions which the Minister for Mines may, consistent with the provisions of the Agreement, determines and thereafter impose in respect of this licence including during the term of the Agreement.] Locality: Mineral Field Area: DATED at Perth this day of .
Appears in 5 contracts
Samples: Iron Ore (Mount Goldsworthy) Agreement, Iron Ore (Mount Goldsworthy) Agreement Act 1964, Iron Ore (Mount Goldsworthy) Agreement Act 1964
ENDORSEMENTS AND CONDITIONS. Endorsements
1. This licence is granted in accordance with proposals submitted on [ ], and approved by the Minister (as defined in the Agreement) on [ ], under the Agreement.
2. The Joint Venturers are permitted to, in accordance with approved proposals, take stone, sand, clay and gravel from the land the subject of this licence for the construction, operation and maintenance of the Railway (including any Railway spur line) constructed within or approved for construction within the area of land the subject of this licence.
3. Notwithstanding the Mining Xxx 0000, no royalty shall be payable under the Mining Xxx 0000 in respect of stone, sand, clay and gravel which the Joint Venturers are permitted by the Agreement to obtain from the land the subject of this licence.
4. [Any further endorsement which the Minister for Mines may, consistent with the provisions of the Agreement, determines and thereafter impose in respect of this licence including during the term of the Agreement.] Conditions
(a) Except as provided in paragraph (b), the Joint Venturers shall within 2 years after the Railway Operation Date surrender in accordance with the provisions of the Mining Xxx 0000 the area of this licence down to a maximum of 100 metres width or as otherwise approved by the Minister (as defined in the Agreement) for the safe operation of the Railway then constructed or approved for construction under approved proposals.
(b) Paragraph (a) shall not apply to land the subject of this licence that was included in this licence pursuant to clause 9E(6)(h) or clause 9E(6)(i) of the Agreement.
2. The Joint Venturers shall as soon as possible after the construction of a Railway spur line or of an expansion or extension thereof as the case may be surrender in accordance with the Mining Xxx 0000 the land the subject of this licence that was included in this licence pursuant to clause 9E(6)(h) of the Agreement for the purpose of such construction down to a maximum of 100 metres in width or as otherwise approved by the Minister (as defined in the Agreement) for the safe operation of that Railway spur line or expansion or extension thereof as the case may be then constructed or approved for construction under approved proposals.
3. [Any further conditions which the Minister for Mines may, consistent with the provisions of the Agreement, determines and thereafter impose in respect of this licence including during the term of the Agreement.] Locality: Mineral Field Area: DATED at Perth this day of . WHEREAS by the Agreement (hereinafter called "“the Agreement")”) approved by and scheduled the Iron Ore (Mount Goldsworthy) Agreement Xxx 0000, as from time to time added to, varied or amended, the State agreed to grant to [ ] (hereinafter with their successors and permitted assigns called "“the Joint Venturers")”) a miscellaneous licence for the construction use and maintenance of a Lateral Access Road (as defined in the Agreement) AND WHEREAS the Joint Venturers pursuant to clause 9E(6)(a)(ii) of the Agreement have made application for the said licence; NOW in consideration of the rents reserved by and the provisions of the Agreement and in pursuance of the Iron Ore (Mount Goldsworthy) Agreement Xxx 0000, as from time to time added to, varied or amended, the Joint Venturers are hereby authorised to construct use and maintain a road on the land more particularly delineated and described from time to time in the Schedule hereto in accordance with the provisions of the Agreement and proposals approved under the Agreement for a term of 4 years commencing on the date hereof (subject to the sooner determination of the term upon the cessation or determination of the Agreement) and for the purposes and upon and subject to the terms covenants and conditions set out in the Agreement and the Mining Xxx 0000 as it applies to this licence, and any amendments to the Agreement and the Mining Xxx 0000 from time to time and to the terms and conditions (if any) now or hereafter endorsed hereon and the payment of rentals in respect of this licence in accordance with clause 9E(6)(a)(ii) of the Agreement PROVIDED ALWAYS that this licence shall not be determined or forfeited otherwise than in accordance with the Agreement. In this licence: ‑ If the Joint Venturers be more than one the liability of the Joint Venturers hereunder shall be joint and several. ‑ Reference to an Act includes all amendments to that Act for the time being in force and also any Act passed in substitution therefore or in lieu thereof and to the regulations and by‑laws of the time being in force thereunder.
Appears in 2 contracts
Samples: Iron Ore (Mount Goldsworthy) Agreement Act 1964, Iron Ore (Mount Goldsworthy) Agreement Act 1964
ENDORSEMENTS AND CONDITIONS. Endorsements
1. This licence is granted in accordance with proposals submitted on [ ], and approved by the Minister (as defined in the Agreement) on [ ], under the Agreement.
2. The Joint Venturers are permitted to, in accordance with approved proposals, take stone, sand, clay and gravel from the land the subject of this licence for the construction, operation and maintenance of the Railway (including any Railway spur line) constructed within or approved for construction within the area of land the subject of this licence.
3. Notwithstanding the Mining Xxx 0000Act 1978, no royalty shall be payable under the Mining Xxx 0000 Act 1978 in respect of stone, sand, clay and gravel which the Joint Venturers are permitted by the Agreement to obtain from the land the subject of this licence.
4. [Any further endorsement which the Minister for Mines may, consistent with the provisions of the Agreement, determines and thereafter impose in respect of this licence including during the term of the Agreement.] Conditions
(a) Except as provided in paragraph (b), the Joint Venturers shall within 2 years after the Railway Operation Date surrender in accordance with the provisions of the Mining Xxx 0000 Act 1978 the area of this licence down to a maximum of 100 metres width or as otherwise approved by the Minister (as defined in the Agreement) for the safe operation of the Railway then constructed or approved for construction under approved proposals.
(b) Paragraph (a) shall not apply to land the subject of this licence that was included in this licence pursuant to clause 9E(6)(h) or clause 9E(6)(i) of the Agreement.
2. The Joint Venturers shall as soon as possible after the construction of a Railway spur line or of an expansion or extension thereof as the case may be surrender in accordance with the Mining Xxx 0000 Act 1978 the land the subject of this licence that was included in this licence pursuant to clause 9E(6)(h) of the Agreement for the purpose of such construction down to a maximum of 100 metres in width or as otherwise approved by the Minister (as defined in the Agreement) for the safe operation of that Railway spur line or expansion or extension thereof as the case may be then constructed or approved for construction under approved proposals.
3. [Any further conditions which the Minister for Mines may, consistent with the provisions of the Agreement, determines and thereafter impose in respect of this licence including during the term of the Agreement.] Locality: Mineral Field Area: DATED at Perth this day of .
Appears in 1 contract
ENDORSEMENTS AND CONDITIONS. Endorsements
1. This licence is granted in accordance with proposals submitted on [ ]] , and approved by the Minister (as defined in the Agreement) on [ ]] , under the Agreement.
2. The Joint Venturers are permitted to, in accordance with approved proposals, take stone, sand, clay and gravel from the land the subject of this licence for the construction, operation and maintenance of the Railway (including any Railway spur line) constructed within or approved for construction within the area of land the subject of this licence.
3. Notwithstanding the Mining Xxx 0000Act 1978 , no royalty shall be payable under the Mining Xxx 0000 Act 1978 in respect of stone, sand, clay and gravel which the Joint Venturers are permitted by the Agreement to obtain from the land the subject of this licence.
4. [Any further endorsement which the Minister for Mines may, consistent with the provisions of the Agreement, determines and thereafter impose in respect of this licence including during the term of the Agreement.] Conditions
(a) Except as provided in paragraph (b), the Joint Venturers shall within 2 years after the Railway Operation Date surrender in accordance with the provisions of the Mining Xxx 0000 Act 1978 the area of this licence down to a maximum of 100 metres width or as otherwise approved by the Minister (as defined in the Agreement) for the safe operation of the Railway then constructed or approved for construction under approved proposals.
(b) Paragraph (a) shall not apply to land the subject of this licence that was included in this licence pursuant to clause 9E(6)(h) or clause 9E(6)(i) of the Agreement.
2. The Joint Venturers shall as soon as possible after the construction of a Railway spur line or of an expansion or extension thereof as the case may be surrender in accordance with the Mining Xxx 0000 Act 1978 the land the subject of this licence that was included in this licence pursuant to clause 9E(6)(h) of the Agreement for the purpose of such construction down to a maximum of 100 metres in width or as otherwise approved by the Minister (as defined in the Agreement) for the safe operation of that Railway spur line or expansion or extension thereof as the case may be then constructed or approved for construction under approved proposals.
3. [Any further conditions which the Minister for Mines may, consistent with the provisions of the Agreement, determines and thereafter impose in respect of this licence including during the term of the Agreement.] SCHEDULE Land description Locality: Mineral Field Area: DATED at Perth this day of .. MINISTER FOR MINES THIRD SCHEDULE WESTERN AUSTRALIA IRON ORE (MOUNTGOLDSWORTHY) AGREEMENT ACT 1964 MINING ACT 1978 MISCELLANEOUS LICENCE FOR A LATERAL ACCESS ROAD No. MISCELLANEOUS LICENCE [ ]
Appears in 1 contract
Samples: Iron Ore (Mount Goldsworthy) Agreement Act 1964 Fourth Variation Agreement
ENDORSEMENTS AND CONDITIONS. Endorsements
1. This licence is granted in accordance with proposals submitted on [ ], and approved by the Minister (as defined in the Agreement) on [ ], under the Agreement.
2. The Joint Venturers are permitted to, in accordance with approved proposals, take stone, sand, clay and gravel from the land the subject of this licence for the construction, operation and maintenance of the Railway (including any Railway spur line) constructed within or approved for construction within the area of land the subject of this licence.
3. Notwithstanding the Mining Xxx 0000, no royalty shall be payable under the Mining Xxx 0000 in respect of stone, sand, clay and gravel which the Joint Venturers are permitted by the Agreement to obtain from the land the subject of this licence.
4. [Any further endorsement which the Minister for Mines may, consistent with the provisions of the Agreement, determines and thereafter impose in respect of this licence including during the term of the Agreement.] Conditions
(a) Except as provided in paragraph (b), the Joint Venturers shall within 2 years after the Railway Operation Date surrender in accordance with the provisions of the Mining Xxx 0000 the area of this licence down to a maximum of 100 metres width or as otherwise approved by the Minister (as defined in the Agreement) for the safe operation of the Railway then constructed or approved for construction under approved proposals.
(b) Paragraph (a) shall not apply to land the subject of this licence that was included in this licence pursuant to clause 9E(6)(h) or clause 9E(6)(i) of the Agreement.
2. The Joint Venturers shall as soon as possible after the construction of a Railway spur line or of an expansion or extension thereof as the case may be surrender in accordance with the Mining Xxx 0000 the land the subject of this licence that was included in this licence pursuant to clause 9E(6)(h) of the Agreement for the purpose of such construction down to a maximum of 100 metres in width or as otherwise approved by the Minister (as defined in the Agreement) for the safe operation of that Railway spur line or expansion or extension thereof as the case may be then constructed or approved for construction under approved proposals.
3. [Any further conditions which the Minister for Mines may, consistent with the provisions of the Agreement, determines and thereafter impose in respect of this licence including during the term of the Agreement.] SCHEDULE Land description Locality: Mineral Field Area: DATED at Perth this day of . MINISTER FOR MINES THIRD SCHEDULE WESTERN AUSTRALIA IRON ORE ( MOUNT GOLDSWORTHY ) AGREEMENT XXX 0000 MINING XXX 0000 MISCELLANEOUS LICENCE FOR A LATERAL ACCESS ROAD No.MISCELLANEOUS LICENCE [ ]
Appears in 1 contract